(1) Ecology will evaluate these drills.
(2) At the start of the unannounced drill, ecology will notify the Class 2 facility of the drill objectives, expectations and scenario.
(3) The Class 2 facility may request to be excused from an unannounced deployment drill if conducting the drill poses an unreasonable safety or environmental risk, or significant economic hardship. If ecology approves the request, ecology will call the drill on another date.
(4) Ecology will provide the facility with a drill evaluation. If deficiencies are found during the drill, ecology may require a redrill after the facility corrects the deficiencies.
[Statutory Authority: RCW
88.46.160,
88.46.165, and chapter
90.56 RCW. WSR 06-20-034 (Order 06-02), § 173-180-820, filed 9/25/06, effective 10/26/06.]