(1)
Issuance. Whenever a source is found to be in violation of an emission standard or other provision of this chapter, ecology or the authority may issue a regulatory order requiring that the source be brought into compliance within a specified time. The order shall contain a schedule for installation, with intermediate benchmark dates and a final completion date, and shall constitute a compliance schedule. Requirements for public involvement (WAC
173-400-171) must be met.
(2) Federal action. A source shall be considered to be in compliance with this chapter if all the provisions of its individual compliance schedule included with a regulatory order are being met. Such compliance does not preclude federal enforcement action by the EPA until and unless the schedule is submitted and adopted as an amendment to the state implementation plan.
(3) Penalties for delayed compliance. Sources on a compliance schedule but not meeting emissions standards may be subject to penalties as provided in the Federal Clean Air Act.
[Statutory Authority: Chapter
70.94 RCW. WSR 91-05-064 (Order 90-06), § 173-400-161, filed 2/19/91, effective 3/22/91.]