Group (2009 International Building Code) | IA | IB | IIA | IIB | IIIA | IIIB | IV | VA | VB |
A-1 Assembly, theaters, with stage | 211.15 | 203.98 | 198.73 | 190.05 | 178.25 | 173.30 | 183.31 | 162.97 | 156.05 |
A-1 Assembly, theaters, without stage | 193.16 | 185.99 | 180.74 | 172.06 | 160.31 | 155.36 | 165.32 | 145.04 | 138.12 |
A-2 Assembly, nightclubs | 163.22 | 158.56 | 154.17 | 148.00 | 138.96 | 135.24 | 142.52 | 126.06 | 121.36 |
A-2 Assembly, restaurants, bars, banquet halls | 162.22 | 157.56 | 152.17 | 147.00 | 136.96 | 134.24 | 141.52 | 124.06 | 120.36 |
A-3 Assembly, churches | 195.10 | 187.93 | 182.68 | 174.00 | 162.21 | 157.26 | 167.26 | 146.94 | 140.02 |
A-3 Assembly, general, community halls, libraries, museums | 163.81 | 156.64 | 150.39 | 142.71 | 129.91 | 125.96 | 135.97 | 114.63 | 108.71 |
A-4 Assembly, arenas | 192.16 | 184.99 | 178.74 | 171.06 | 158.31 | 154.36 | 164.32 | 143.04 | 137.12 |
B Business | 164.76 | 158.78 | 153.49 | 145.97 | 132.45 | 127.63 | 139.92 | 116.43 | 110.93 |
E Educational | 176.97 | 170.85 | 165.64 | 158.05 | 146.37 | 138.98 | 152.61 | 127.91 | 123.09 |
F-1 Factory and industrial, moderate hazard | 97.87 | 93.28 | 87.66 | 84.46 | 75.44 | 72.26 | 80.79 | 62.17 | 58.48 |
F-2 Factory and industrial, low hazard | 96.87 | 92.28 | 87.66 | 83.46 | 75.44 | 71.26 | 79.79 | 62.17 | 57.48 |
H-1 High hazard, explosives | 91.74 | 87.15 | 82.53 | 78.33 | 70.49 | 66.31 | 74.66 | 57.22 | N.P. |
H-2, 3, 4 High hazard | 91.74 | 87.15 | 82.53 | 78.33 | 70.49 | 66.31 | 74.66 | 57.22 | 52.53 |
H-5 HPM | 164.76 | 158.78 | 153.49 | 145.97 | 132.45 | 127.63 | 139.92 | 116.43 | 110.93 |
I-1 Institutional, supervised environment | 164.82 | 159.04 | 154.60 | 147.90 | 135.84 | 132.25 | 144.15 | 121.88 | 117.55 |
I-2 Institutional, hospitals | 277.07 | 271.09 | 265.80 | 258.28 | 243.90 | N.P. | 252.23 | 227.88 | N.P. |
I-2 Institutional, nursing homes | 193.00 | 187.02 | 181.74 | 174.22 | 160.98 | N.P. | 168.16 | 144.96 | N.P. |
I-3 Institutional, restrained | 187.72 | 181.73 | 176.45 | 168.93 | 156.64 | 150.82 | 162.87 | 140.63 | 133.13 |
I-4 Institutional, day care facilities | 164.82 | 159.04 | 154.60 | 147.90 | 135.84 | 132.25 | 144.15 | 121.88 | 117.55 |
M Mercantile | 121.57 | 116.92 | 111.53 | 106.36 | 96.96 | 94.25 | 100.88 | 84.07 | 80.36 |
R-1 Residential, hotels | 166.21 | 160.43 | 155.99 | 149.29 | 137.39 | 133.80 | 145.70 | 123.43 | 119.10 |
R-2 Residential, multiple family | 139.39 | 133.61 | 129.17 | 122.47 | 111.23 | 107.64 | 119.54 | 97.27 | 92.94 |
R-3 Residential, one and two family | 131.18 | 127.60 | 124.36 | 121.27 | 116.43 | 113.53 | 117.42 | 108.79 | 101.90 |
R-4 Residential, care/assisted living facilities | 164.82 | 159.04 | 154.60 | 147.90 | 135.84 | 132.25 | 144.15 | 121.88 | 117.55 |
S-1 Storage, moderate hazard | 90.74 | 86.15 | 80.53 | 77.33 | 68.49 | 65.31 | 73.66 | 55.22 | 51.53 |
S-2 Storage, low hazard | 89.74 | 85.15 | 80.53 | 76.33 | 68.49 | 64.31 | 72.66 | 55.22 | 50.53 |
U Utility, miscellaneous | 71.03 | 67.02 | 62.71 | 59.30 | 52.86 | 49.43 | 56.33 | 41.00 | 39.06 |
a | Private garages use utility, miscellaneous |
b | Unfinished basements (all use group) = $15.00 per sq. ft. |
c | For shell only buildings deduct 20 percent |
d | N.P. = not permitted |
Total Valuation | Fee |
$1.00 to $500.00 | $23.50 |
$501.00 to $2,000.00 | $23.50 for the first $500.00 plus $3.05 for each additional $100.00, or fraction thereof, to and including $2,000.00 |
$2,001.00 to $25,000.00 | $69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00, or fraction thereof, to and including $25,000.00 |
$25,001.00 to $50,000.00 | $391.25 for the first $25,000.00 plus $10.10 for each additional $1,000.00, or fraction thereof, to and including $50,000.00 |
$50,001.00 to $100,000.00 | $643.75 for the first $50,000.00 plus $7.00 for each additional $1,000.00, or fraction thereof, to and including $100,000.00 |
$100,001.00 to $500,000.00 | $993.75 for the first $100,000.00 plus $5.60 for each additional $1,000.00, or fraction thereof, to and including $500,000.00 |
$500,001.00 to $1,000,000.00 | $3,233.75 for the first $500,000.00 plus $4.75 for each additional $1,000.00, or fraction thereof, to and including $1,000,000.00 |
$1,000,001.00 and up | $5,608.75 for the first $1,000,000.00 plus $3.65 for each additional $1,000.00, or fraction thereof |
INITIAL FILING FEE (first time applicants) | $77.20 | ||
DESIGN PLAN FEES: | |||
INITIAL FEE - MASTER DESIGN (code cycle), 50% of permit fee × 1.156* | |||
INITIAL FEE - ONE YEAR DESIGN, 35% of permit fee × 1.156* | |||
RENEWAL FEE - 10% of permit fee × 1.156 + | $98.90 | ||
RESUBMIT FEE - 10% of permit fee × 1.156 + | $98.90 | ||
ADDENDUM (approval expires on same date as original plan) - 10% of permit fee × 1.156 + | $98.90 | ||
ELECTRONIC PLAN SUBMITTAL FEE $6.10 per page for the first set of plans and $1.00 per page for each additional set of plans. These fees are in addition to any applicable design plan fees required under this section. | |||
PLUMBING PLAN FEE, $20.70 + PER FIXTURE FEE of | $6.80 | ||
MEDICAL GAS PLAN FEE, $20.70 + PER OUTLET FEE of | $6.80 | ||
Note: Mechanical systems are included in the primary plan fee | |||
FIRE SAFETY PLAN REVIEW AS REQUIRED (Required for all structures that are more than 4,000 square feet and for all A, I, and H occupancy) | |||
MASTER DESIGN - 25% of permit fee × 1.156 | |||
One year design - 15% of the permit fee × 1.156 | |||
ELECTRICAL PLAN REVIEW - Find fees @ http://apps.leg.wa.gov/wac/default.aspx?cite=296-46B-906 | |||
RECIPROCAL PLAN REVIEW: | |||
INITIAL FEE-MASTER DESIGN (minimum 3 hours) | $98.90 per hour | ||
INITIAL FEE-ONE YEAR DESIGN (minimum 2 hours) | $98.90 per hour | ||
RENEWAL FEE (minimum 1 hour) | $98.90 | ||
ADDENDUM (minimum 1 hour) | $98.90 per hour | ||
PLANS APPROVED BY DESIGN PROFESSIONALS - 10% of permit fee × 1.156 + | $98.90 | ||
APPROVAL OF EACH SET OF DESIGN PLANS BEYOND FIRST THREE SETS - 5% of permit fee × 1.156 + | $98.90 | ||
DEPARTMENT INSPECTION FEES | |||
INSPECTION/REINSPECTION (Per hour** plus travel time** and mileage***) | $98.90 | ||
TRAVEL (Per hour**) | $98.90 | ||
PER DIEM*** | |||
HOTEL**** | |||
MILEAGE*** | |||
RENTAL CAR**** | |||
PARKING**** | |||
AIRFARE**** | |||
DEPARTMENT AUDIT FEES: | |||
AUDIT (Per hour**) | $98.90 | ||
TRAVEL (Per hour**) | $98.90 | ||
PER DIEM*** | |||
HOTEL**** | |||
MILEAGE*** | |||
RENTAL CAR**** | |||
PARKING**** | |||
AIRFARE**** | |||
INSIGNIA FEES: | |||
FIRST SECTION | $316.30 | ||
EACH ADDITIONAL SECTION | $28.20 | ||
REISSUED-LOST/DAMAGED | $77.20 | ||
OTHER FEES: | |||
FIELD TECHNICAL SERVICE (Per hour** plus travel time** and mileage***) | $98.90 | ||
NOTIFICATION TO LOCAL ENFORCEMENT AGENCY (NLEA) | $42.60 | ||
PUBLICATION PRINTING AND DISTRIBUTION OF RCWs AND WACs (One free copy per year upon request) | $15.70 | ||
REFUND FEE | $28.90 |
* | Minimum plan review fee is 2 1/2 hours at the field technical service rate. |
** | Minimum charge of 1 hour; time spent greater than 1 hour is charged in 1/2 hour increments. |
*** | Per state guidelines. |
**** | Actual charges incurred. |