(Effective until July 1, 2023)

PDFWAC 51-50-0429

Section 429Electric vehicle charging infrastructure.

429.1 Scope. The provisions of this section shall apply to the construction of new buildings.
EXCEPTIONS:
1. Occupancies classified as Group R-3 or Group U.
 
2. Group A, Group E, or Group M occupancies, except where employee parking spaces are designated. The provisions of Section 429 shall apply only to those designated employee parking spaces.
429.2 Required electric vehicle charging infrastructure. Where parking is provided, ten percent of parking spaces shall be provided with electric vehicle charging infrastructure in compliance with Sections 429.3, 429.4 and 429.5. When the calculation of percent served results in a fractional parking space, the applicant shall round up to the next whole number.
429.3 Electrical room(s). Electrical room(s) serving buildings with on-site parking spaces must be sized to accommodate the potential for electrical equipment and distribution required to serve a minimum of 20 percent of the total parking spaces with 208/240 V 40-amp, circuit or equivalent electric vehicle charging infrastructure.
429.4 Electric vehicle charging infrastructure. Electric vehicle charging infrastructure shall meet the following requirements:
1. A minimum number of 208/240 V 40-amp, circuit or equivalent electric vehicle charging stations required to serve the parking spaces specified in Section 429.2. The electric vehicle charging stations shall be located to serve spaces designated for parking and charging electric vehicles.
2. Additional service capacity, space for future meters, panel capacity or space for additional panels, and raceways for future installation of electric vehicle charging stations. The service capacity and raceway size shall be designed to accommodate the future installation of the number of 208/240 V 40-amp, circuit or equivalent electric vehicle charging stations specified in Section 429.2. The raceway shall terminate at spaces designated for parking and charging electric vehicles in the future.
Where designated electric vehicle charging locations serve exterior on-grade parking spaces that are located more than 4 feet from a building, raceways shall be extended below grade to a pull box in the vicinity of the designated future electric vehicle charging locations or stub above grade in the vicinity of the designated future electric vehicle charging locations, protected from vehicles by a curb or other device.
EXCEPTION:
In lieu of surface-mounted raceway between the electrical panel and the designated electric vehicle charging locations, it is permitted to provide permanent markings indicating the pathway for future raceway, and one-inch diameter capped sleeves through each wall and floor assembly that are penetrated along that route. This pathway and the locations of capped sleeves shall also be indicated on the electrical plans. Raceway shall be installed for any portion of the pathway located below slabs, below grade, or within floor, wall or roof assemblies.
Load management infrastructure may be used to adjust the size and capacity of the required building electric service equipment and circuits on the customer facilities, as well as electric utility owned infrastructure, as allowed by applicable local and national electric codes.
429.5 Electric vehicle charging infrastructure for accessible parking spaces. When electric vehicle charging infrastructure is required, ten percent of accessible parking space, rounded to the next whole number, shall be provided with electric vehicle charging infrastructure. The electric vehicle charging infrastructure may also serve adjacent parking spaces not designated as accessible parking. A maximum of ten percent rounded to the next whole number, of the accessible parking spaces are allowed to be included in the total number of electric vehicle parking spaces required under Section 429.2.
[Statutory Authority: RCW 19.27.077, 19.27.031 and 19.27.074. WSR 21-16-063, § 51-50-0429, filed 7/29/21, effective 8/29/21.]
(Effective July 1, 2023)

PDFWAC 51-50-0429

Section 429Electric vehicle charging infrastructure.

429.1 General. The provisions of this section shall apply to the construction of new buildings and accessory structures, including parking lots and parking garages.
Electric vehicle supply equipment (EVSE) shall be installed in accordance with applicable requirements of chapter 19.28 RCW and the National Electrical Code, Article 625.
EXCEPTION:
Electric vehicle charging infrastructure is not required if any of the following conditions are met:
 
1. There is no public utility or commercial power supply.
 
2. Dwelling units without garages or other on-site parking.
429.2 Electric vehicle (EV) charging infrastructure. Buildings and accessory structures shall be provided with EV charging stations, EV-Ready parking spaces, and EV-capable parking spaces in accordance with Table 429.2. Calculations shall be rounded up to the nearest whole number. Where a building contains more than one occupancy, the electric vehicle charging infrastructure percentages of Table 429.2 shall be applied to the number of spaces required for each occupancy.
EXCEPTIONS:
1. Except for Group A, Group E, and Group M occupancies, on-site parking with less than 10 parking spaces shall not be required to comply with Section 429.2.
 
2. Group A, Group E, and Group M occupancies shall comply with one of the following, whichever is greater:
 
2.1. The provisions of Section 429.2 shall apply only to designated employee parking spaces.
 
2.2. One of each 200 parking spaces or fraction thereof shall be EV Ready. One of each 200 parking spaces or fraction thereof shall be an EV Charging Station.
Table 429.2
Electric Vehicle Charging Infrastructure
Occupancy
Number of EV
Charging Stations
Number of EV-Ready Parking Spaces
Number of EV-Capable Parking Spaces
Group A, B, E, F, H, I, M, and S occupancies
10% of total parking spaces
10% of total parking spaces
10% of total parking spaces
Group R occupancies
 
Buildings that do not contain more than two dwelling units
Not required
One for each dwelling unit
Not required
 
Dwelling units with private garages
Not required
One for each dwelling unit
Not required
All other Group R occupancies
10% of total parking spaces
25% of total parking spaces
10% of total parking spaces
429.2.1 EV charging stations and EV-Ready parking spaces. A minimum of 40-ampere dedicated 208/240-volt branch circuit shall be installed for each EV Ready parking space and each EV Charging Station. The branch circuits shall terminate at a receptacle outlet or EV charger in close proximity to the proposed location of the EV Ready parking space or the EV Charging Station.
429.2.2 EV-Capable parking spaces. A listed raceway capable of accommodating a minimum of 40-ampere dedicated 208/240-volt branch circuit shall be installed for each EV-Capable parking space. The raceway shall terminate into a cabinet, box or other enclosure in close proximity to the proposed location of the EV-Capable parking space. Raceways and related components that are planned to be installed underground, and in enclosed, inaccessible or concealed areas and spaces, shall be installed at the time of original construction.
429.3 Electrical room(s) and equipment. Electrical room(s) and/or dedicated electrical equipment shall be sized to accommodate the requirements of Section 429.
The electrical service and the electrical system, including any on-site distribution transformer(s), shall have sufficient capacity to simultaneously charge all EVs at all required EV Charging Stations, EV Ready parking spaces, and EV-Capable parking spaces at a minimum of 40-amperes each.
EXCEPTION:
Automatic Load Management System (ALMS) may be used to adjust the maximum electrical capacity required for the EV-Ready and EV-Capable parking spaces. The ALMS must be designed to allocate charging capacity among multiple future EV Charging Stations at a minimum of 16 amperes per EV charger.
429.4 Electric vehicle charging infrastructure for accessible parking spaces. Ten percent of the accessible parking spaces, rounded to the next whole number, shall be EV Charging Stations. Additional 10 percent of the accessible parking spaces, rounded to the next whole number, shall be EV Ready. Not fewer than one for each type of EV charging system shall be accessible.
The electric vehicle charging infrastructure may also serve adjacent parking spaces not designated as accessible parking. A maximum of 10 percent of the accessible parking spaces, rounded to the next whole number, are allowed to be included in the total number of electric vehicle parking spaces required under Section 429.2.
[Statutory Authority: RCW 19.27.031 and 19.27.074. WSR 22-13-094, § 51-50-0429, filed 6/14/22, effective 7/1/23. Statutory Authority: RCW 19.27.077, 19.27.031 and 19.27.074. WSR 21-16-063, § 51-50-0429, filed 7/29/21, effective 8/29/21.]