If, during the course of work under a contract for public improvements or work for which amounts are required to be reserved under RCW
60.28.010, the contract completion date is changed, and said change will work an undue hardship upon the contractor when compared to the increased costs to the state agency if a change in election is allowed, said agency may, in its discretion, allow the contractor to change his election under the available options.