The county road administration board/county contract shall include, but not be limited to, the following provisions:
(1) Such contract must be signed and returned to the county road administration board within forty-five days of its mailing by the county road administration board.
(2) The project will be constructed in accordance with:
(a) The information furnished to the county road administration board; and
(b) The plans and specifications prepared under the supervision of the county engineer.
(3) The county will notify the county road administration board when a contract has been awarded, when construction has started, and when the project has been completed.
(4) The county road administration board will reimburse counties based on progress vouchers received and approved on individual projects, subject to the availability of county ferry capital improvement funds appropriated by the legislature.
(5) The county will reimburse the county road administration board in the event that a project post audit reveals ineligible expenditure of county ferry capital improvement funds. Said funds will be returned to the county fuel tax account for distribution in accordance with RCW
46.68.120.
[Statutory Authority: Chapter
36.79 RCW. WSR 08-10-026, § 136-400-100, filed 4/28/08, effective 5/29/08; WSR 99-01-021, § 136-400-100, filed 12/7/98, effective 1/7/99. Statutory Authority: RCW
36.78.070 and
36.79.060. WSR 96-17-013, § 136-400-100, filed 8/12/96, effective 9/12/96. Statutory Authority: 1991 c 310 § 1(4). WSR 91-21-138 (Order 85), § 136-400-100, filed 10/23/91, effective 11/23/91.]