(1) Before construction a detailed plan must be submitted to the department that shows how adequate and competent construction inspection will be provided.
(2) The construction quality assurance plan shall include a:
(a) Construction schedule with a summary of planned construction activities, their sequence, interrelationships, durations, and terminations.
(b) Description of the construction management organization, management procedures, lines of communication, and responsibility.
(c) Description of anticipated quality control testing that includes type of test, frequency, and who will perform the tests.
(d) Description of the change order process that includes who will initiate change orders, as well as who will review, negotiate, and approve change orders.
(e) Description of the technical records handling methodology that includes where plans and specifications, as-built drawings, field orders, and change orders will be kept.
(f) Description of the construction inspection program that includes inspection responsibility, anticipated inspection frequency, deficiency resolution, and inspector qualifications.