(1) Before constructing or modifying industrial wastewater facilities, engineering reports and plans and specifications for the project must be submitted to and approved by the department.
(2) All engineering reports and plans and specifications should be submitted by the owner consistent with a compliance schedule issued by the department or at least thirty days before the time approval is desired. The department will generally review and either approve (or conditionally approve), comment on, or disapprove those plans and reports within the thirty-day period unless circumstances prevent, in which case the owner will be notified and informed of the reason for the delay.
(3) Construction or modification of industrial wastewater facilities shall conform to the following schedule of tasks unless waived in accordance with subsection (5).
(a) Submission and approval of an engineering report;
(b) Submission and approval of plans and specifications;
(c) Submission of an operation and maintenance manual.
(4) Where two or more years has elapsed since approval of the engineering report or plans and specifications, it may be necessary to update that document to reflect changed water quality conditions, regulatory requirements, or engineering technology.
(5) Upon request by the owner, the department may waive the requirement for a three step submission of documents for industrial facilities. In such a case the department will require instead conceptual plans that also include the appropriate (as determined by the department) information from the engineering report and an operation and maintenance manual.
[Statutory Authority: RCW
90.48.110. WSR 00-15-021 (Order 00-09), § 173-240-110, filed 7/11/00, effective 8/11/00. Statutory Authority: Chapters
43.21A and
90.48 RCW. WSR 83-23-063 (Order DE 83-30), § 173-240-110, filed 11/16/83. Statutory Authority: RCW
90.48.110. WSR 79-02-033 (Order DE 78-10), § 173-240-110, filed 1/23/79. Formerly chapter 372-20 WAC.]