(1) If the sponsor chooses to proceed with the certification process, they must prepare a draft instrument and submit an electronic and hard copy to the department.
(2) The sponsor must develop the instrument using feedback from the department, the IRT, and comments received during the prospectus phase.
(3) The draft instrument must contain all of the information identified in WAC
173-700-222 to be complete.
(4) After receiving the draft instrument, the department shall determine whether the instrument is complete and notify the sponsor within thirty days. If the draft instrument is not complete, the department shall notify the sponsor in writing of its determination and identify any additional information that is necessary to complete the instrument. Once a modified draft instrument is submitted, the department must notify the sponsor as soon as it determines that the draft instrument is complete.
[Statutory Authority: Chapter
90.84 RCW. WSR 09-19-013 (Order 04-13), § 173-700-224, filed 9/3/09, effective 10/4/09.]