EUIadj | = | (Energyhist- Energysaved)/GFA |
Where: | | |
Energyhist | = | Historical annual energy use, kBtu |
Energysaved | = | Estimated annual energy savings, kBtu |
GFA | = | Gross floor area, ft2 |
Following the completion of an energy audit that has identified EEMs sufficient to meet the building's energy target, the applicant shall implement those EEMs per the requirements of Section 9.
8.4.1 Level 1 Audit. Buildings shall perform a Level 1 audit (walk-through analysis) as defined in ANSI/ASHRAE/ACCA Standard 211-2018 Standard for Commercial Building Energy Audits, Section 5.312.
8.4.2 Level 2 Audit.Buildings shall perform a Level 2 Audit (energy survey and engineering analysis) as defined in ANSI/ASHRAE/ACCA Standard 211-2018 Standard for Commercial Building Energy Audits, Section 5.412.
8.5.1 Audit results. The energy audit report shall define the actions necessary for the building owner to achieve the energy and cost savings that are recommended in the report.
Energy audit results shall be presented in a summary table that includes, at a minimum, an estimate of each of the following:
• A list of recommended EEMs that, if implemented, will either meet the energy target for the building if it has a target or, if it does not have an energy target, will meet the economic criteria set by the standard in Section 9.
• The estimated energy savings and peak demand savings associated with each recommended EEM, expressed in the cost units used on the building owner's energy bills, and the units used for comparison with the energy target.
• The estimated (modeled) energy cost savings associated with each recommended EEM.
• The estimated cost of implementation for each recommended EEM. The costs of implementation shall include the required monitoring of energy savings per the requirements of Section 9.
The economic evaluation of measures are required by Normative Annex X.
8.5.2 Interactive effects. Energy savings analysis shall include interactive effects of all selected EEMs. When considering multiple EEMs with interactive effects, the order of analysis shall start with load reduction measures and proceed through distribution systems and associated equipment efficiencies and then plant and heat-rejection systems. Any interactive effects on equipment sizing and part load performance of equipment shall be accounted for due to reduced loads on subsequent systems.
8.5.4.1 Nonfederal facilities. The minimum financial criteria required for reporting is specified in Normative Annex X.
8.5.4.2 U.S. Federal Facilities - Not adopted.
8.5.5 End-use analysis. The energy audit shall include an end-use analysis that compares the estimated energy use of the facility after implementation of all selected EEMs to historical utility consumption. The intent of this requirement is to ensure that estimates of the base-case end-use energy estimates and potential energy-savings estimates in the energy audit report are reasonable.
8.5.5.2 Requirements for Level 2 Audits. The energy auditor is required to estimate the energy use of all end uses that individually comprise more than 5% of total historical building energy use. The energy estimates for these end uses shall be summed and compared to historical energy consumption for the facility. The sum of the base-case end-use energy estimates must be between 90% and 100% of the historical energy use at the site.
This comparison shall be conducted separately for each fuel type, such as electricity, natural gas, or fuel oil, for which EEMs are identified. On-site energy sources such as solar, photovoltaic, geothermal, and wind shall be included.
Correction for historical weather for the base year versus average weather used in baseline estimates may be used.
The same energy-use estimates that comprise the end-use analysis shall also be used as the basis for energy savings calculations. The qualified energy auditor shall verify that each EEM savings estimate is reasonable in comparison to the historical energy consumption of that end use based on energy consumption survey data or experience with similar sites.
The qualified energy auditor shall verify that the combined savings from multiple EEMs shall take into account interactive effects among measures.
Miscellaneous plug loads may be estimated on average equipment power density and building area. (See Form D in Normative Annex Z.)
[Statutory Authority: RCW
19.27A.210. WSR 20-22-059, § 194-50-080, filed 10/30/20, effective 11/30/20.]