All applications by corporations and LLCs for certificates of authorization must be completed on forms provided by the board and submitted to the offices of the board. A complete application requires the following: Payment of the appropriate fee as listed in chapter
196-26A WAC; affidavit of designated professional engineer and/or land surveyor; and, a copy of resolution naming the designated engineer, or land surveyor, or both.
[Statutory Authority: RCW
18.43.035. WSR 23-01-052, § 196-25-010, filed 12/14/22, effective 1/14/23. Statutory Authority: Chapters
18.43 and
18.235 RCW. WSR 04-04-001, § 196-25-010, filed 1/21/04, effective 2/21/04. Statutory Authority: RCW
18.43.035 and
18.43.130. WSR 98-12-053, § 196-25-010, filed 5/29/98, effective 7/1/98.]