(1) The project area may not, without prior approval of the board or director, be converted to a use other than that for which funds were originally approved.
(2) The board may only approve a conversion when the sponsor:
(a) Demonstrates the need to convert the project area including all efforts to consider practical alternatives, how they were evaluated, and the reasons they were not pursued;
(b) Provides an opportunity for the public to participate in the identification, development and evaluation of the alternatives, including a minimum public comment period of at least thirty days; and
(c) Provides another project area to serve as a replacement for the restoration project. The replacement must:
(i) Be of reasonably equivalent habitat utility and location;
(ii) Be administered by the same sponsor unless otherwise approved by the board;
(iii) Be a new project area that satisfies need(s) identified in the sponsor's current plan as described in WAC
286-13-035 or the other relevant local or statewide plan;
(iv) Be administered under similar stewardship methods as the converted project area;
(v) Be eligible in the same grant program or category from which funds were originally allocated, unless otherwise approved by the board; and
(vi) Satisfies the conversion without grant assistance from the board.