(1) Complete an inspection application which can be obtained from us.
(2) Send the completed application, application fee, and inspection fee to us prior to the date you would like an inspection performed. (See WAC
296-150P-3000.)
(3) During the inspection, have your approved design plans, specifications, and test results available for our inspector.
(4) A recreational park trailer inspection will be completed in two or more phases. The "cover" inspection during the construction of the unit before the electrical, plumbing, mechanical, heating, and structural systems are covered. The final inspection takes place after the recreational park trailer is complete.
[Statutory Authority: RCW
43.22.340 and
43.22.420. WSR 97-16-043, § 296-150P-0610, filed 7/31/97, effective 12/1/97.]