Exception: | This requirement does not apply to roads outside the construction site. |
(b) A firm, properly graded, drained area, readily accessible to the work with adequate space for the safe storage of materials and the safe operation of the erector's equipment.
(4)
Preplanning of overhead hoisting operations. You must preplan all hoisting operations in steel erection to ensure that the requirements of WAC
296-155-704(4) are met.
(5)
Site-specific erection plan. Where employers elect, due to conditions specific to the site, to develop alternate means and methods that provide employee protection in accordance with WAC
296-155-704 (3)(e),
296-155-709 (1)(d) or (5)(d), a site-specific erection plan must be developed by a qualified person and be available at the worksite. Guidelines for establishing a site-specific erection plan are contained in Appendix A to this part.
(6) You must perform steel erection under the supervision of a competent person who is present at the worksite.
[Statutory Authority: RCW
49.17.010,
49.17.040,
49.17.050,
49.17.060. WSR 16-09-085, § 296-155-703, filed 4/19/16, effective 5/20/16. Statutory Authority: RCW
49.17.010, [49.17].040, and [49.17].050. WSR 02-13-115, § 296-155-703, filed 6/19/02, effective 9/1/02.]