You must meet the requirements … | in this section: |
Make sure suspended scaffolds and scaffold components meet these strength requirements | |
Make sure suspended scaffold outrigger beams meet these requirements | |
Make sure counterweights are safe and used properly | |
Make sure tiebacks meet these requirements | |
Make sure suspended scaffold support devices meet these requirements | |
Make sure scaffold hoists meet these requirements | |
Make sure scaffold hoists retain enough suspension rope | |
Make sure wire rope is in good condition | |
Make sure wire suspension rope connections meet these requirements | |
Make sure wire rope clips are used properly | |
Prevent swaying of two-point and multipoint suspension scaffolds | |
Use emergency escape and rescue devices appropriately | |
Protect suspension ropes from heat or corrosive substances | |
Take precautions while welding | |
Prohibit use of gasoline-powered equipment on suspended scaffolds | |
Meet these requirements when using catenary scaffolds | |
Meet these requirements when using float (ship) scaffolds | |
Meet these requirements when using interior hung scaffolds | |
Meet these requirements when using multilevel suspended scaffolds | |
Meet these requirements when using multipoint adjustable suspension scaffolds | |
Meet these requirements when using needle beam scaffolds | |
Meet these requirements when using single-point adjustable suspension scaffolds | |
Meet these requirements when using two-point adjustable suspension scaffolds (swing stages) | |
[Statutory Authority: RCW
49.17.010,
49.17.040,
49.17.050. WSR 15-23-086, § 296-874-300, filed 11/17/15, effective 12/18/15. Statutory Authority: RCW
49.17.010,
49.17.040,
49.17.050,
49.17.060. WSR 05-01-054, § 296-874-300, filed 12/7/04, effective 3/1/05.]