School districts shall demonstrate that they have complied with RCW
28A.335.190 and
43.19.1906 and shall not enter into contract(s) for construction until the following certified copies have been submitted and approved by the superintendent of public instruction:
(1) Each advertisement for bid;
(2) Tabulated statement of all bids received;
(3) Recommendation of the board of directors for award of contract(s) on the basis of bids received, including all accepted alternates;
(4) Alternate bids;
(5) Names and addresses of all bidders;
(6) Certified statement of costs for special inspections and testing;
(7) Certified statement of amount of local and/or other disbursable funds available specifically for the project, exclusive of state funds, with the source of funds identified, including identity and amount of nonhigh school district funds when applicable;
(8) School district board acceptance of a constructability review and implementation.
If the recommended contractor is not the low bidder, the school district shall give reasons pursuant to statutory provisions set forth in RCW
43.19.1911.
[Statutory Authority: RCW
28A.525.020. WSR 08-20-008, § 392-344-110, filed 9/18/08, effective 10/19/08; WSR 06-16-032, recodified as § 392-344-110, filed 7/25/06, effective 8/25/06. Statutory Authority: 1990 c 33. WSR 90-17-009, § 180-29-110, filed 8/6/90, effective 9/6/90. Statutory Authority: RCW
28A.47.830. WSR 83-21-067 (Order 12-83), § 180-29-110, filed 10/17/83.]