Each gas pipeline company must comply with chapter
19.122 RCW, including:
(1) Subscribe to the appropriate one-number locator service;
(2) Provide, upon receipt of locate notice, reasonably accurate information as to its locatable underground facilities by surface-marking the location of the facilities;
(3) Respond with locate markings within two business days after receipt of the notice or within a time mutually agreed upon between the operator and the excavator requesting the utility locate information.
[Statutory Authority: RCW
80.01.040,
80.04.060 and
81.88.040. WSR 08-12-046 (Docket PG-070975, General Order R-549), § 480-93-250, filed 5/30/08, effective 6/30/08. Statutory Authority: RCW
80.01.040,
81.01.010, and
81.88.060. WSR 07-18-010 (Docket PG-061027, General Order R-544), § 480-93-250, filed 8/23/07, effective 9/23/07.]