Title of Rule: Title 136 WAC, Day labor limit and day labor definitions.

Purpose: Amendments to WAC 136-16-022 Day labor limit and 136-18-020 Definitions.

Other Identifying Information: Per 2001 legislation, Bill Number SSB 5733.

Statutory Authority for Adoption: Chapter 36.79 RCW.

Name of Agency Personnel Responsible for Drafting: Randy Hart, 2404 Chandler Court S.W., Suite 240, Olympia, 98504, (360) 753-5989; Implementation: Karen Pendleton, 2404 Chandler Court S.W., Suite 240, Olympia, 98504, (360) 753-5989; and Enforcement: Jay Weber, 2404 Chandler Court S.W., Suite 240, Olympia, 98504, (360) 753-5989.

Name of Proponent: County Road Administration Board, governmental.

Rule is not necessitated by federal law, federal or state court decision.

Explanation of Rule, its Purpose, and Anticipated Effects: The amendments affect counties with population's equal or exceeding 50,000 for day labor limits, and sets new rules for counties with populations with less than 50,000 populations.

Proposal Changes the Following Existing Rules: The amendments affect counties with population's equal or exceeding 50,000 for day labor limits, and sets new rules for counties with populations with less than 50,000 populations.

No small business economic impact statement has been prepared under chapter 19.85 RCW.

RCW 34.05.328 does not apply to this rule adoption.

Hearing Location: County Road Administration Board, 2404 Chandler Court S.W., Suite 240, Olympia, WA 98504-0913, on October 18, 2001, at 2:00 p.m.

Assistance for Persons with Disabilities: Contact Karen Pendleton by October 12, 2001, TDD (800) 833-6384 or (360) 753-5989.

Submit Written Comments to: Karen Pendleton, 2404 Chandler Court S.W., Suite 240, Olympia, WA 98504-0913, fax (360) 586-0386, by October 12, 2001.

Date of Intended Adoption: October 18, 2001.

August 17, 2001

Jay P. Weber

Executive Director

OTS-5099.1


AMENDATORY SECTION(Amending WSR 99-01-021, filed 12/7/98, effective 1/7/99)

WAC 136-16-022   Day labor limit.   The statutory day labor limit shall be computed in accordance with RCW 36.77.065 in the following manner for counties with populations equal to or exceeding 50,000:

(1) When the total annual county road construction budget is four million dollars or more, the day labor limit is eight hundred thousand dollars or fifteen percent of the total annual county road construction budget, whichever is greater.

(2) When the total annual county road construction budget is ((in excess of)) one million five hundred thousand dollars or more and less than four million dollars, the day labor limit is five hundred twenty-five thousand dollars or twenty percent of the total annual county road construction budget, whichever is greater.

(3) When the total annual county road construction budget is ((in excess of)) five hundred thousand dollars or more and less than one million five hundred thousand dollars, the day labor limit is two hundred and fifty thousand dollars or thirty-five percent of the total annual county road construction budget, whichever is greater.

(4) When the total annual county road construction budget is less than five hundred thousand dollars, the day labor limit shall be two hundred and fifty thousand dollars, unless the county legislative authority, by resolution, elects the alternate procedure set forth in RCW 36.77.065. When such alternate procedure is chosen, an individual project limit of thirty-five thousand dollars shall apply, and each project shall be administered in accordance with chapter 136-18 WAC.

(5) The statutory day labor limit shall be computed in accordance with RCW 36.77.065 in the following manner for counties with populations less than 50,000:

(a) When the total annual county road construction budget is four million dollars or more, the day labor limit is eight hundred eighty thousand dollars or twenty-five percent of the total annual county road construction budget, whichever is greater.

(b) When the total annual county road construction budget is one million five hundred thousand dollars or more and less than four million dollars, the day labor limit is five hundred seventy-seven thousand dollars or thirty percent of the total annual county road construction budget, whichever is greater.

(c) When the total annual county road construction budget is five hundred thousand dollars or more and less than one million five hundred thousand dollars, the day labor limit is two hundred seventy-five thousand dollars or forty-five percent of the total annual county road construction budget, whichever is greater.

(d) When the total annual county road construction budget is less than five hundred thousand dollars, the day labor limit shall be two hundred seventy-five thousand dollars, unless the county legislative authority, by resolution, elects the alternate procedure set forth in RCW 36.77.065. When such alternate procedure is chose, an individual project limit of thirty-eight thousand five hundred dollars shall apply, and each project shall be administered in accordance with chapter 136-18 WAC.

Determination by the county road administration board that a violation of RCW 36.77.065 has occurred shall be cause for issuance of a conditional certificate of good practice by the board as specified in WAC 136-04-060 on behalf of the county in which the violation occurred. The first condition of such a conditional certificate of good practice shall be that the county be required, at the next regular or special meeting of the county road administration board, to show cause why a certificate of good practice should not be denied to that county.

[Statutory Authority: Chapter 36.79 RCW. 99-01-021, 136-16-022, filed 12/7/98, effective 1/7/99. Statutory Authority: RCW 36.78.070 and 36.79.060. 96-17-013, 136-16-022, filed 8/12/96, effective 9/12/96. Statutory Authority: RCW 36.78.070. 90-07-076 (Order 76), 136-16-022, filed 3/21/90, effective 4/21/90. Statutory Authority: Chapter 36.78 RCW. 80-16-020 (Order 40), 136-16-022, filed 10/29/80; 80-09-084 (Order 38), 136-16-022, filed 7/22/80.]

OTS-5098.1


AMENDATORY SECTION(Amending WSR 96-17-013, filed 8/12/96, effective 9/12/96)

WAC 136-18-020   Definitions.   For purposes of implementing statutory requirements relative to day labor construction work, the following definitions shall apply:

(1) Construction - the building of a new road facility or improvement of an existing facility to a higher geometric or structural standard.

(2) Day labor construction - construction work performed by personnel carried on the county payroll using county owned, leased or rented equipment.

(3) Authorization date - the date that construction is authorized.

(4) Start of construction - the date that construction work commences.

(5) End of construction - the date that construction work is completed.

(6) Completion date - the date on which a county road project is closed in the accounting records.

(7) Estimated construction costs - the county engineer's estimate of the cost of contemplated construction work, not including preliminary engineering and right of way acquisition costs.

(8) Estimated project costs - the county engineer's estimate of the cost of engineering, right of way acquisition, and construction.

(9) True and complete construction costs - the accounting record of all construction costs attributed to a county road project from the authorization date to the completion date.

(10) True and complete project costs - the accounting record of all engineering, right of way acquisition, and construction costs attributed to a county road project from the authorization date to the completion date.

(11) Day labor county road project - day labor construction authorized by action of the county legislative authority in those counties where a cumulative dollar limit applies to all day labor construction.

(12) Special day labor county road project - day labor construction which will result in a facility with independent utility, authorized by action of the county legislative authority in those counties:

(a) With populations equal to or exceeding 50,000 and where the total construction budget is less than five hundred thousand dollars and the legislative authority has by resolution elected to perform day labor construction in an amount not to exceed thirty-five thousand dollars including labor, equipment and materials on any one project.

(b) With populations less than 50,000 and where the total construction budget is less than five hundred thousand dollars and the legislative authority has by resolution elected to perform day labor construction in an amount not to exceed thirty-eight thousand five hundred dollars including labor, equipment and materials on any one project.

[Statutory Authority: RCW 36.78.070 and 36.79.060. 96-17-013, 136-18-020, filed 8/12/96, effective 9/12/96. Statutory Authority: Chapter 36.78 RCW. 80-16-019 (Order 39), 136-18-020, filed 10/29/80; 79-01-098 (Order 35), 136-18-020, filed 1/3/79; Order 27, 136-18-020, filed 1/27/76.]