CERTIFICATION OF ENROLLMENT
SUBSTITUTE HOUSE BILL 1671
56th Legislature
1999 Regular Session
Passed by the House March 5, 1999 Yeas 97 Nays 0
Speaker of the House of Representatives
Speaker of the House of Representatives
Passed by the Senate April 8, 1999 Yeas 47 Nays 0 |
CERTIFICATE
We, Dean R. Foster and Timothy A. Martin, Co-Chief Clerks of the House of Representatives of the State of Washington, do hereby certify that the attached is SUBSTITUTE HOUSE BILL 1671 as passed by the House of Representatives and the Senate on the dates hereon set forth.
Chief Clerk
Chief Clerk |
President of the Senate |
|
Approved |
FILED |
|
|
Governor of the State of Washington |
Secretary of State State of Washington |
_______________________________________________
SUBSTITUTE HOUSE BILL 1671
_______________________________________________
Passed Legislature - 1999 Regular Session
State of Washington 56th Legislature 1999 Regular Session
By House Committee on Judiciary (originally sponsored by Representatives Constantine, Radcliff, Kessler, Mastin, Sullivan, Grant, G. Chandler, Reardon, Lisk, Esser, Alexander, McMorris and Mitchell)
Read first time 02/25/1999.
AN ACT Relating to actions arising out of public works contracts; and amending RCW 39.04.240.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF WASHINGTON:
Sec. 1. RCW 39.04.240 and 1992 c 171 s 1 are each amended to read as follows:
(1)
The provisions of RCW 4.84.250 through 4.84.280 shall apply to an action
arising out of a public works contract in which the state or a municipality, or
other public body that contracts for public works, is a party, except that:
(a) The maximum ((amount of the pleading shall be two hundred fifty thousand
dollars)) dollar limitation in RCW 4.84.250 shall not apply; and (b)
in applying RCW 4.84.280, the time period for serving offers of settlement on
the adverse party shall be the period not less than thirty days and not more
than one hundred twenty days after completion of the service and filing of the
summons and complaint.
(2) The rights provided for under this section may not be waived by the parties to a public works contract that is entered into on or after June 11, 1992, and a provision in such a contract that provides for waiver of these rights is void as against public policy. However, this subsection shall not be construed as prohibiting the parties from mutually agreeing to a clause in a public works contract that requires submission of a dispute arising under the contract to arbitration.
--- END ---