HB 2847 - DIGEST
(SUBSTITUTED FOR - SEE 1ST SUB)
Provides that, if the local government or its designee does not take final action on a project permit application within one hundred twenty days after the application is deemed complete, the applicant may file a petition for a peremptory writ of mandamus in the superior court of the county where the application was submitted to compel the local government or its designee to issue the approval.
Repeals 1998 c 286 s 8 and 1995 c 347 s 433 (uncodified).