5292-S AMH TTE H4705.2
SSB 5292 - H COMM AMD ADOPTED 3-8-02
By Committee on Technology, Telecommunications & Energy
Strike everything after the enacting clause and insert the following:
"Sec. 1. RCW 80.52.030 and 1995 c 69 s 2 are each amended to read as follows:
The definitions set forth in this section apply throughout this chapter unless the context clearly requires otherwise.
(1) "Public agency" means a public utility district, joint operating agency, city, county, or any other state governmental agency, entity, or political subdivision.
(2) "Major public
energy project" means a plant or installation capable, or intended to be
capable, of generating electricity in an amount greater than ((two)) four
hundred ((fifty)) megawatts, measured using maximum continuous electric
generating capacity, less minimum auxiliary load, at average ambient
temperature and pressure. Where two or more such plants are located within the
same geographic site, each plant shall be considered a major public energy
project. An addition to an existing facility is not deemed to be a major
energy project unless the addition itself is capable, or intended to be
capable, of generating electricity in an amount greater than ((two)) four
hundred ((fifty)) megawatts. A project which is under construction on
July 1, 1982, shall not be considered a major public energy project unless the
official agency budget or estimate for total construction costs for the project
as of July 1, 1982, is more than two hundred percent of the first official
estimate of total construction costs as specified in the senate energy and
utilities committee WPPSS inquiry report, volume one, January 12, 1981, and
unless, as of July 1, 1982, the projected remaining cost of construction for
that project exceeds two hundred million dollars.
(3) "Cost of construction" means the total cost of planning and building a major public energy project and placing it into operation, including, but not limited to, planning cost, direct construction cost, licensing cost, cost of fuel inventory for the first year's operation, interest, and all other costs incurred prior to the first day of full operation, whether or not incurred prior to July 1, 1982.
(4) "Cost of acquisition" means the total cost of acquiring a major public energy project from another party, including, but not limited to, principal and interest costs.
(5) "Bond" means a revenue bond, a general obligation bond, or any other indebtedness issued by a public agency or its assignee.
(6) "Applicant" means a public agency, or the assignee of a public agency, requesting the secretary of state to conduct an election pursuant to this chapter.
(7) "Cost-effective" means that a project or resource is forecast:
(a) To be reliable and available within the time it is needed; and
(b) To meet or reduce the electric power demand of the intended consumers at an estimated incremental system cost no greater than that of the least-cost similarly reliable and available alternative project or resource, or any combination thereof.
(8) "System cost" means an estimate of all direct costs of a project or resource over its effective life, including, if applicable, the costs of distribution to the consumer, and, among other factors, waste disposal costs, end-of-cycle costs, and fuel costs (including projected increases), and such quantifiable environmental costs and benefits as are directly attributable to the project or resource."
Correct the title.
EFFECT: Increases the threshold for major public energy projects from 250 MW to 400 MW. A major public energy project requires a public vote by voters within the jurisdiction of the public agency proposing the project before financing is approved.
--- END ---