HB 2765-S - DIGEST
(DIGEST AS ENACTED)
Provides that the timber management plan must be filed with the county legislative authority either: (1) When an application for classification under this chapter is submitted;
(2) When a sale or transfer of timber land occurs and a notice of continuance is signed; or
(3) Within sixty days of the date the application for reclassification under this chapter or from designated forest land is received. The application for reclassification shall be accepted, but shall not be processed until the timber management plan is received. If the timber management plan is not received within sixty days of the date the application for reclassification is received, the application for reclassification shall be denied.
Declares that, if circumstances require it, the county assessor may allow in writing an extension of time for submitting a timber management plan when an application for classification or reclassification or notice of continuance is filed.