Passed by the Senate February 16, 2004 YEAS 48   BRAD OWEN ________________________________________ President of the Senate Passed by the House March 2, 2004 YEAS 94   FRANK CHOPP ________________________________________ Speaker of the House of Representatives | I, Milton H. Doumit, Jr., Secretary of the Senate of the State of Washington, do hereby certify that the attached is SUBSTITUTE SENATE BILL 6265 as passed by the Senate and the House of Representatives on the dates hereon set forth. MILTON H. DOUMIT JR. ________________________________________ Secretary | |
Approved March 22, 2004. GARY F. LOCKE ________________________________________ Governor of the State of Washington | March 22, 2004 - 4:18 p.m. Secretary of State State of Washington |
State of Washington | 58th Legislature | 2004 Regular Session |
READ FIRST TIME 01/30/04.
AN ACT Relating to permit timelines; amending RCW 77.55.100; and adding a new section to chapter 43.42 RCW.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF WASHINGTON:
NEW SECTION. Sec. 1 A new section is added to chapter 43.42 RCW
to read as follows:
(1) The legislature finds that there are numerous efforts ongoing
to streamline and improve permitting processes. These include the work
of the transportation permit efficiency and accountability committee,
chapter 47.06C RCW, and the efforts of the office of regulatory
assistance to develop an integrated permit system, chapter 245, Laws of
2003. While these efforts are ongoing and likely to yield procedural
improvements in permit processing by 2006, there is an immediate need
to coordinate permitting timelines for large, multiagency permit
streamlining efforts.
(2) With the agreement of all participating permitting agencies and
the permit applicant, state permitting agencies may establish timelines
to make permit decisions, including the time periods required to
determine that the permit applications are complete, to review the
applications, and to process the permits. Established timelines shall
not be shorter than those otherwise required for each permit under
other applicable provisions of law, but may extend and coordinate such
timelines. The goal of the established timelines is to achieve the
maximum efficiencies possible through concurrent studies and
consolidation of applications, permit review, hearings, and comment
periods. A timeline established under this subsection with the
agreement of each permitting agency shall commit each permitting agency
to act within the established timeline.
Sec. 2 RCW 77.55.100 and 2003 c 391 s 2 are each amended to read
as follows:
(1) In the event that any person or government agency desires to
construct any form of hydraulic project or perform other work that will
use, divert, obstruct, or change the natural flow or bed of any of the
salt or fresh waters of the state, such person or government agency
shall, before commencing construction or work thereon and to ensure the
proper protection of fish life, secure the approval of the department
as to the adequacy of the means proposed for the protection of fish
life. This approval shall not be unreasonably withheld or unreasonably
conditioned.
(2)(a) The department shall grant or deny approval of a standard
permit within forty-five calendar days of the receipt of a complete
application and notice of compliance with any applicable requirements
of the state environmental policy act, made in the manner prescribed in
this section. The period of forty-five calendar days may be extended,
if the permit is part of a multiagency permit streamlining effort and
all participating permitting agencies and the permit applicant agree to
an extended timeline longer than forty-five calendar days. The permit
must contain provisions allowing for minor modifications to the plans
and specifications without requiring reissuance of the permit.
(b) The applicant may document receipt of application by filing in
person or by registered mail. A complete application for approval
shall contain general plans for the overall project, complete plans and
specifications of the proposed construction or work within the mean
higher high water line in salt water or within the ordinary high water
line in fresh water, and complete plans and specifications for the
proper protection of fish life.
(c) The forty-five day requirement shall be suspended if:
(i) After ten working days of receipt of the application, the
applicant remains unavailable or unable to arrange for a timely field
evaluation of the proposed project;
(ii) The site is physically inaccessible for inspection; or
(iii) The applicant requests delay. Immediately upon determination
that the forty-five day period is suspended, the department shall
notify the applicant in writing of the reasons for the delay.
(d) For purposes of this section, "standard permit" means a written
permit issued by the department when the conditions under subsections
(3) and (5)(b) of this section are not met.
(3)(a) The department may issue an expedited written permit in
those instances where normal permit processing would result in
significant hardship for the applicant or unacceptable damage to the
environment. In cases of imminent danger, the department shall issue
an expedited written permit, upon request, for work to repair existing
structures, move obstructions, restore banks, protect property, or
protect fish resources. Expedited permit requests require a complete
written application as provided in subsection (2)(b) of this section
and shall be issued within fifteen calendar days of the receipt of a
complete written application. Approval of an expedited permit is valid
for up to sixty days from the date of issuance.
(b) For the purposes of this subsection, "imminent danger" means a
threat by weather, water flow, or other natural conditions that is
likely to occur within sixty days of a request for a permit
application.
(c) The department may not require the provisions of the state
environmental policy act, chapter 43.21C RCW, to be met as a condition
of issuing a permit under this subsection.
(d) The department or the county legislative authority may
determine if an imminent danger exists. The county legislative
authority shall notify the department, in writing, if it determines
that an imminent danger exists.
(4) Approval of a standard permit is valid for a period of up to
five years from date of issuance. The permittee must demonstrate
substantial progress on construction of that portion of the project
relating to the approval within two years of the date of issuance. If
the department denies approval, the department shall provide the
applicant, in writing, a statement of the specific reasons why and how
the proposed project would adversely affect fish life. Protection of
fish life shall be the only ground upon which approval may be denied or
conditioned. Chapter 34.05 RCW applies to any denial of project
approval, conditional approval, or requirements for project
modification upon which approval may be contingent.
(5)(a) In case of an emergency arising from weather or stream flow
conditions or other natural conditions, the department, through its
authorized representatives, shall issue immediately, upon request, oral
approval for removing any obstructions, repairing existing structures,
restoring stream banks, or to protect property threatened by the stream
or a change in the stream flow without the necessity of obtaining a
written approval prior to commencing work. Conditions of an oral
approval to protect fish life shall be established by the department
and reduced to writing within thirty days and complied with as provided
for in this section. Oral approval shall be granted immediately, upon
request, for a stream crossing during an emergency situation.
(b) For purposes of this section and RCW 77.55.110, "emergency"
means an immediate threat to life, the public, property, or of
environmental degradation.
(c) The department or the county legislative authority may declare
and continue an emergency when one or more of the criteria under (b) of
this subsection are met. The county legislative authority shall
immediately notify the department if it declares an emergency under
this subsection.
(6) The department shall, at the request of a county, develop five-year maintenance approval agreements, consistent with comprehensive
flood control management plans adopted under the authority of RCW
86.12.200, or other watershed plan approved by a county legislative
authority, to allow for work on public and private property for bank
stabilization, bridge repair, removal of sand bars and debris, channel
maintenance, and other flood damage repair and reduction activity under
agreed-upon conditions and times without obtaining permits for specific
projects.
(7) This section shall not apply to the construction of any form of
hydraulic project or other work which diverts water for agricultural
irrigation or stock watering purposes authorized under or recognized as
being valid by the state's water codes, or when such hydraulic project
or other work is associated with streambank stabilization to protect
farm
and agricultural land as defined in RCW 84.34.020. These
irrigation or stock watering diversion and streambank stabilization
projects shall be governed by RCW 77.55.110.
A landscape management plan approved by the department and the
department of natural resources under RCW 76.09.350(2), shall serve as
a hydraulic project approval for the life of the plan if fish are
selected as one of the public resources for coverage under such a plan.
(8) For the purposes of this section and RCW 77.55.110, "bed" means
the land below the ordinary high water lines of state waters. This
definition does not include irrigation ditches, canals, storm water
run-off devices, or other artificial watercourses except where they
exist in a natural watercourse that has been altered by man.
(9) The phrase "to construct any form of hydraulic project or
perform other work" does not include the act of driving across an
established ford. Driving across streams or on wetted stream beds at
areas other than established fords requires approval. Work within the
ordinary high water line of state waters to construct or repair a ford
or crossing requires approval.
(10) The department shall not require a fishway on a tide gate,
flood gate, or other associated man-made agricultural drainage
facilities as a condition of a hydraulic project approval if such
fishway was not originally installed as part of an agricultural
drainage system existing on or before May 20, 2003.
(11) Any condition requiring a self-regulating tide gate to achieve
fish passage in an existing hydraulic project approval under this
section may not be enforced.