6384-S.E AMH CB AMH5296.4

ESSB 6384  - H COMM AMD
     By Committee on Capital Budget

ADOPTED AS AMENDED 02/28/2006

     Strike everything after the enacting clause and insert the following:

"NEW SECTION.  Sec. 1   A supplemental capital budget is hereby adopted and, subject to the provisions set forth in this act, the several dollar amounts hereinafter specified, or so much thereof as shall be sufficient to accomplish the purposes designated, are hereby appropriated and authorized to be incurred for capital projects during the period beginning with the effective date of this act and ending June 30, 2007, out of the several funds specified in this act.

SUPPLEMENTAL APPROPRIATIONS

NEW SECTION.  Sec. 101   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE OFFICE OF FINANCIAL MANAGEMENT
     Infrastructure Study (06-2-850)

     The appropriation in this section is subject to the following conditions and limitations:
     (1) The legislature finds that the December 16, 2005, inventory and evaluation of the state's public infrastructure programs and funds report completed pursuant to section 129(1), chapter 518, Laws of 2005 identified the need for systematic improvements to infrastructure grant, loan, and technical assistance programs. The report identified needed improvements, including (a) the development of common infrastructure program processes, procedures, and financing mechanisms; and (b) the consolidation of programs to improve coordination and efficiency of the state's investments and to minimize duplication.
     (2) The appropriation in this section is provided solely for the office of financial management, in consultation with staff from appropriate fiscal committees of the legislature and affected state agencies, to:
     (a) Identify and prioritize processes, procedures, financing mechanisms, and programs for integration, standardization, or consolidation;
     (b) Identify program overlaps and gaps between the state's infrastructure programs;
     (c) Identify local projects funded by the legislature but not included in existing grant, loan, or technical assistance programs and analyze whether the projects meet the programs' criteria;
     (d) Identify a strategy to include projects such as those identified in (c) of this subsection within existing or potential consolidated programs. Consider program processes, procedures, criteria, policies, and rules related but not limited to project review and selection, funding limits, and participation requirements;
     (e) Identify or develop a comprehensive funding structure to support the integration and standardization of processes, procedures, and consolidated programs; and
     (f) Report recommendations to the appropriate fiscal committees of the legislature by December 15, 2006.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $100,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $100,000

NEW SECTION.  Sec. 102   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE JOINT LEGISLATIVE AUDIT AND REVIEW COMMITTEE
     Life-cycle Cost Model Update (06-2-851)

     The appropriation in this section is subject to the following conditions and limitations: Funding is provided solely to update the life-cycle cost model developed by the joint legislative audit and review committee. The joint legislative audit and review committee shall:
     (1) Update the model's assumptions;
     (2) Enhance the model's ability to inform decision-makers about the current and long-term capital and operating impacts of facility leasing options compared to state ownership; and
     (3) Revise the model to allow for comparisons of alternate financing approaches, including but not limited to the use of certificates of participation, 63-20 financing, and state general obligation bond funding.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $50,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $50,000

Sec. 103   2005 c 488 s 109 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT
     Drinking Water Assistance Program (06-4-003)

Appropriation:
     Drinking Water Assistance Account--State . . . . . . . . . . . . $8,100,000
     Drinking Water Assistance Repayment
          Account--State . . . . . . . . . . . . (($11,500,000))
       $21,780,000
          Subtotal Appropriation . . . . . . . . . . . . (($19,600,000))
       $29,880,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $78,400,000
          TOTAL . . . . . . . . . . . . (($98,000,000))
       $108,280,000

Sec. 104   2005 c 488 s 112 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT
     Building for the Arts (06-4-005)

     The appropriation in this section is subject to the following conditions and limitations:
     (1) The appropriation is subject to the provisions of RCW 43.63A.750.
     (2) The appropriation is provided solely for the following list of projects:

ProjectsLocationRecommendation
((African-American museumSeattle$700,000))
McIntyre hallMount Vernon$350,000
Northwest film forumSeattle$100,000
Historic Cooper schoolSeattle$500,000
Merc playhouseTwisp$6,000
Masquers theatreSoap Lake$145,000
Cornish College of the ArtsSeattle$700,000
Dahmen barn workshopUniontown$79,000
Roxy theatreMorton$75,000
Duwamish longhouseSeattle$65,000
Everett symphonyEverett$215,000
Admiral theatreBremerton$180,000
Pratt fine arts centerSeattle$300,000
Arlington performing artsArlington$375,000
Seattle Academy of Fine ArtSeattle$35,000
Academy of children's theatreRichland$150,000
Empire theatreTekoa$25,000
Children's museumSpokane$75,000
World kite museumLong Beach$115,000
McCaw hallSeattle$1,000,000
KidsQuest children's museumBellevue$200,000
Total(($5,390,000))
$4,690,000


Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . (($5,390,000))
       $4,690,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $16,000,000
          TOTAL . . . . . . . . . . . . (($21,390,000))
       $20,690,000

Sec. 105   2005 c 488 s 125 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT
     Housing Assistance, Weatherization, and Affordable Housing (04-4-003)

     The reappropriations in this section ((is)) are subject to the following conditions and limitations:
     (1) $1,700,000 of the reappropriation is provided solely to promote development of safe and affordable housing units for persons eligible for services from the division of developmental disabilities within the department of social and health services.
     (2) $700,000 of the reappropriation is provided solely for grants to nonprofit organizations and public housing authorities for revolving loan, self-help housing programs for low and moderate income families.
     (3) $84,500 of the reappropriation is provided solely for shelters, transitional housing, or other housing facilities for victims of domestic violence.
     (4) $600,000 of the reappropriation is provided solely for facilities housing low-income migrant, seasonal, or temporary farmworkers. It is the intent of the legislature that operation of the facilities built under this section be in compliance with 8 U.S.C. Sec. 1342. The department shall work with the farmworker housing advisory committee to prioritize funding of projects to the areas of highest need. Funding may also be provided, to the extent qualified projects are submitted, for health and safety projects.
     (5) $1,400,000 of the reappropriation is provided solely for the development of emergency shelters and transitional housing opportunities for homeless families with children.
     (6) ((Up to $1,000,000 of the reappropriation is provided to help capitalize a self-insurance risk pool for nonprofit corporations in Washington that develop housing units for low-income persons and families. The self-insurance risk pool shall be approved by the state risk manager. The self-insurance risk pool shall repay to the state the amount of the reappropriation provided to the risk pool under this section whenever the capitalization exceeds the minimum requirements established by the office of the risk manager. Any reappropriation authority not expended by June 30, 2007, shall lapse.)) $960,000 of the Washington housing trust account appropriation is provided solely for implementation of the multiunit residential building liability revolving fund program authorized in chapter ... (Second Substitute House Bill No. 3070), Laws of 2006. If the bill is not enacted by June 30, 2006, the amounts in this subsection shall lapse.

Reappropriation:
     State Taxable Building Construction
          Account--State . . . . . . . . . . . . (($25,780,000))
       $24,820,000
Appropriation:
     Washington Housing Trust Account--State . . . . . . . . . . . . $960,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $55,220,000
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $81,000,000

Sec. 106   2005 c 488 s 131 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT
     Local/Community Projects (06-4-008)

     The appropriation in this section is subject to the following conditions and limitations:
     (1) The projects must comply with RCW 43.63A.125(2)(c) and other requirements for community projects administered by the department.
     (2) Funding for the Inland Northwest Science and Technology Center shall be held in reserve until the balance of phase I funding has been secured or committed from local government and community sources.
     (3) The Washington state arts commission shall design a plaque that shall be affixed to buildings or displayed as part of a project receiving any appropriation from this section. The plaque shall provide information to the public that the building or project has been made possible by the tax dollars of Washington citizens. The commission may contact the secretary of state to obtain approval for use of the Washington seal in the design of the plaque. The final design shall be approved by the chairs and ranking members of the house of representatives capital budget committee and the senate ways and means committee.
     (4) The appropriation is provided solely for the following list of projects:

ProjectsRecommendation
7th street theatre$600,000
Alder creek pioneer association carousel museum$450,000
Asian counseling and referral service$2,000,000
Bailey Gatzert children's play area$75,000
Bridge for kids$850,000
Brookside school ADA playground equipment$25,000
Buena library$50,000
Cannon house$250,000
Central area motivation program (CAMP)$250,000
Cesar Chavez park$150,000
Chambers creek footbridge$177,000
Childhaven$150,000
Clark Lake park and retreat center$500,000
Colman school preconstruction activities(($500,000))
$1,200,000
Columbia breaks fire interpretive center$150,000
Covington aquatics center phase 1$350,000
Crossroads community center and park$250,000
Cutter theater$71,000
Des Moines beach park historic buildings$300,000
Discovery park$1,000,000
East Whatcom regional resource center$1,750,000
Eatonville family park$50,000
El Centro de la Raza$900,000
Filipino community center$200,000
Foster creek$150,000
Fox theater$2,398,000
GC health clinic$12,000
Grand Army of the Republic cemetery$5,000
Granite Falls museum expansion$50,000
Greenbridge plaza in White Center$200,000
Habitat park south hill$400,000
Hanford reach interpretive center$2,000,000
Hidden river environmental education center$50,000
ICL education center$200,000
Japanese cultural and community center$200,000
Joel Pritchard park$2,500,000
Joe's creek project$856,000
Juanita creek channel and riparian restoration$500,000
Julia Butler Hansen home restoration$10,000
LeRoi smelter smokestack monument$3,000
Lewis and Clark confluence project$1,500,000
McCaw hall$2,000,000
Meridian habitat park$400,000
Miners' memorial$36,500
Miracle league handicapped baseball$57,000
MOBIUS/Inland Northwest science and technology center
$1,500,000
Mt. Baker theater$200,000
Mt. Vernon Jasper Gates statue$12,000
Multicultural center of Kitsap county$250,000
Nathaniel Orr home site museum interpretive center$29,000
Neighborhood house rainier vista$213,000
New Lakewood clinic$350,000
Northeast community center expansion$250,000
Northshore performing arts center$1,000,000
Northwest communities education center$1,000,000
Oak Harbor multi-purpose community and sports facility
$50,000
Omak grandstand$250,000
Pacific Northwest salmon center$1,000,000
Pacific science center$900,000
Performing arts center (PACE)$500,000
Puget Sound freight building warehouse--Thea Foss waterway
$2,000,000
Relocation of Sieke Japanese gardens$250,000
River walk and Sammamish river restoration$200,000
Roslyn city hall$150,000
Ruth Dykeman children's center$27,000
Sandman historical tug restoration$10,000
Seattle Aquarium$1,500,000
Seattle community center (1115 E. Pike street)$13,000
Seward park environmental and audubon center$400,000
Snohomish senior center$150,000
Sno-Valley senior activity center kitchen$50,000
Sound way property preservation$500,000
Spokane river whitewater course$400,000
Sumas ballpark$250,000
Synthetic sportsfield partnership at Robinswood park$400,000
Tall ships moorage$300,000
Tukwila kayak and canoe launching facility$20,000
Undeveloped woodlands linked to interurban nature trail
$150,000
Vancouver museum$125,000
Vancouver national historical reserve west barracks$1,000,000
Veterans memorial museum$100,000
West Seattle community resource center$500,000
West central community center$500,000
West Hylebos wetlands boardwalk$100,000
Wilson playfield land acquisition$200,000
Wing Luke Asian art museum$2,000,000
Youth housing/drop-in center$400,000
Total(($39,391,000))
$44,474,500


Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . (($39,391,000))
       $44,474,500

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($39,391,000))
       $44,474,500

Sec. 107   2005 c 488 s 138 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT
     Job/Economic Development Grants (06-4-950)

     The appropriation in this section is subject to the following conditions and limitations:
     (1) The appropriation is provided solely for the following list of projects:

ProjectsRecommendation
Belfair sewer improvements$8,000,000
Bellingham waterfront restoration$2,000,000
Bremerton Harborside$4,000,000
Burien town square$2,000,000
Carnation sewer$2,000,000
City of Covington(($1,000,000))
$3,000,000
Infrastructure for Renton Boeing property$5,000,000
Military communities infrastructure projects$5,000,000
Pacific Northwest national labs campus infrastructure project
$6,000,000
Rainier court$1,500,000
Redevelop Snohomish riverfront$1,500,000
Ridgefield employment center project$2,000,000
Tukwila Southcenter parkway infrastructure$6,000,000
Yakima town center restoration$4,000,000
Total(($50,000,000))
$52,000,000

     (2) $1,000,000 of the appropriation for the Pacific Northwest national labs campus infrastructure project is provided solely for giga-pop infrastructure.
     (3) $1,000,000 of the public works assistance account--state appropriation and $2,000,000 of the state building construction account--state appropriation are provided solely for the city of Covington.
     (4)
$5,000,000 of the appropriation is provided solely for military communities infrastructure projects ((is provided solely for grants to support projects in Island county, Kitsap county, Pierce county, Snohomish county, and Spokane county when a military base in that county is identified for potential closure in the federal base realignment and closure process. The grants will be used to address infrastructure improvements that will aid in the removal of the base from the closure list. The office of financial management shall establish a process for selecting projects for funding based on criteria used to determine the federal base realignment and closure list and recommendations by the department of community, trade, and economic development and the military department. Final allocation of the grants shall be at the discretion and with the approval of the director of the office of financial management)). Military communities infrastructure projects shall include:
     (a) Grants to counties and cities for the purchase of development easements to restrict the use of accident potential zones and clear zones. The office of financial management shall establish a competitive process for selecting projects to receive the grants. Final allocation of these grants shall be at the discretion and with the approval of the director of the office of financial management.
     The grants are subject to the following conditions:
     (i) The county or city must be subject to and in compliance with RCW 36.70A.530;
     (ii) The grants may not be used to remove encroachments into these zones allowed by county or city zoning or permitting actions;
     (iii) The county or city must have an encroachment prevention plan preventing future encroachment into these zones; and
     (iv) The grant provided by the state must not exceed one-third of the project cost with funds from local and federal sources providing the balance of the funds.
     (b) $481,000 of the appropriation is provided solely for improvements to a military department site on Fairchild air force base.


Appropriation:
     Public Works Assistance Account--State . . . . . . . . . . . . $50,000,000
     State Building Construction Account--State . . . . . . . . . . . . $2,000,000
          Subtotal Appropriation . . . . . . . . . . . . $52,000,000


     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($50,000,000))
       $52,000,000

NEW SECTION.  Sec. 108   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT
     Energy Freedom Program (E3SHB No. 2939) (06-2-854)

     The appropriation in this section is subject to the following conditions and limitations:
     (1) The appropriation is provided solely to implement the energy freedom program created in chapter . . . (Engrossed Third Substitute House Bill No. 2939), Laws of 2006. If the bill is not enacted by June 30, 2006, the appropriation shall lapse.
     (2) The department shall not expend more than $466,000 of the appropriation on administrative costs.

Appropriation:
     Energy Freedom Account--State . . . . . . . . . . . . $10,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $10,000,000

Sec. 109   2006 c ... s 2 (E2SHB No. 2393) (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT
     Energy Freedom Program (06-2-852)

     The appropriation in this section is subject to the following conditions and limitations:
     (1)(a) The appropriation is provided solely for low-interest loans to political subdivisions for renewable energy projects including the development of biofuel oilseed crushers, supporting infrastructure, and facilities. The political subdivision may negotiate an appropriate agreement with the bioenergy industry for the use of the oilseed crushers, supporting infrastructure, and facilities.
     (b) For purposes of this section, political subdivision means any port district, county, city, town, special purpose district, and any other municipal corporations or quasi-municipal corporations in the state.
     (2) The appropriation is provided solely for the following list of projects:

ProjectRecommendation
Spokane conservation district$2,750,000
Odessa public development authority$2,750,000
Port of Columbia county$2,750,000
Port of Sunnyside$750,000
Total$9,000,000

     (3) All agreements negotiated between the political subdivision and the bioenergy industry for use of the oilseed crushers, supporting infrastructure, or facilities funded in this section must provide for at least a fifty percent match by the industry partner. The industry match may include, but is not limited to, investments in rail, buildings, refining capacity, or seed stock.
     (4) All other project funds must be disbursed prior to energy freedom loans, except where required on a matching basis by other federal or state programs.
     (5) The department shall disburse loans to the political subdivision on a reimbursement basis only.
     (6) The department may defer loan repayment for up to twenty-four months or until the projects start to receive revenue from operations, whichever is sooner.
     (7) Upon written notice to the political subdivision, the department may suspend or cancel its loans if any of the following occur:
     (a) The political subdivision fails to make satisfactory and reasonable progress to complete the project, or the department concludes the political subdivision will be unable to complete the project or any portion of it; or
     (b) The political subdivision or bioenergy industry partners have made misrepresentations in any information furnished to the department or the legislature in connection with the project.
     (8) In the event that any portion of the loan has been paid to the political subdivision under this section at the time of breach, or failure of the political subdivision to satisfactorily perform, the department may require that the full amount of the loan, or a portion thereof, be repaid within a period specified by the department.
     (9) Future loan repayments shall be deposited into the energy freedom account created in section 3 of this act.
     (10) Chapter 39.12 RCW applies to the renewable energy projects funded in whole or in part by the appropriation in this section.
     (11) It is the intent of the legislature to provide loans for the development of a Washington state biodiesel industry based on Washington grown oilseed. The legislature is aware that in the development of this industry, the start-up process may necessitate the use of other oilseeds until Washington state growers plant sufficient crops to support this industry. The legislature also understands the realities of weather and market conditions in this process. The conversion to maximum Washington grown oilseed must be accomplished as quickly as possible. The political subdivision shall: (a) Develop a plan for outreach to local growers and an estimate of when maximum Washington state oilseed-based production will be reached; (b) develop a goal for the political subdivision to return a portion of the biofuel to local oilseed producers; and (c) report this information to the department of community, trade, and economic development by December 1, 2006. The department shall report on the implementation of this section by January 1, 2007, to the appropriate committees of the legislature.

Appropriation:
     ((State Taxable Building Construction))
          Energy Freedom Account--State . . . . . . . . . . . . $9,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $9,000,000

NEW SECTION.  Sec. 110   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT
     Grays Harbor PUD Bioenergy Project (06-04-852)

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $1,500,000
     Energy Freedom Account--State . . . . . . . . . . . . $6,000,000
          Subtotal Appropriation . . . . . . . . . . . . $7,500,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $7,500,000

Sec. 111   2005 c 488 s 142 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF GENERAL ADMINISTRATION
     Legislative Building: Rehabilitation and Capital Addition (01-1-008)

Reappropriation:
     Thurston County Capital Facilities Account--State . . . . . . . . . . . . (($100,000))
       $214,063

     Prior Biennia (Expenditures) . . . . . . . . . . . . $106,280,442
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($106,380,442))
       $106,494,505

NEW SECTION.  Sec. 112   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF GENERAL ADMINISTRATION
     Pritchard-Legislative Support Building Predesign (06-2-851)

     The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for predesign of the Joel M. Pritchard building as a legislative support facility and public cafeteria. The predesign shall include, but not be limited to, the following: (1) A rehabilitation plan addressing electrical and mechanical systems, plumbing, seismic safety, fire protection, accessibility, energy consumption, and space use including the conversion of the upper floor stack space into usable office space or alternative uses; (2) an assessment of the facility requirements of legislative support agencies including the code reviser, the joint legislative audit and review committee, the legislative service center, and the legislative evaluation and accountability program as potential building tenants; and (3) a financing strategy for the facility that may consider a combination of funding sources including state general obligation bonds and the use of alternative financing mechanisms that utilize dedicated revenue streams through the conversion of existing lease payments into debt service payments.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $250,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $250,000

Sec. 113   2005 c 488 s 143 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF GENERAL ADMINISTRATION
     Cherberg Building: Rehabilitation (02-1-005)

     The reappropriation in this section is subject to the following conditions and limitations:
     (1) The reappropriation is for the purpose of furthering the John A. Cherberg building rehabilitation project, including but not limited to the following: Project final design and initial phase of reconstruction; purchase and remodel of the two modular buildings currently owned by the Legislative building rehabilitation project; and remodel of a portion of the Joel M. Pritchard building for use as swing space during reconstruction.
     (2) The appropriations in this section are subject to the following conditions and limitations:
     (a) Funding is provided solely for design, construction, and other costs related to the relocation efforts associated with this project.
     (((d))) (b) The department may negotiate agreements with the senate for additional fees to manage the John A. Cherberg building rehabilitation project.
     (((e))) (c) Upon completion of the project, the temporary modular buildings shall be sold and removed, and the parking lot shall be restored and landscaped.
     (d) $5,000 of the appropriation in this section is provided solely for a competitive grant for the redesign and repair of the gnomon on the capitol campus sundial adjacent to the Cherberg building. All Washington public community and technical colleges are encouraged to submit design proposals to the Washington state arts commission by December 31, 2006. Final selection shall be made by the commission.

Reappropriation:
     State Building Construction Account--State . . . . . . . . . . . . $2,500,000
Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $12,253,000
     Thurston County Capital Facilities Account--State . . . . . . . . . . . . $1,439,000
          Subtotal Appropriation . . . . . . . . . . . . $13,692,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $3,100,000
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $19,292,000

Sec. 114   2005 c 488 s 152 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF GENERAL ADMINISTRATION
     ((General Administration Building Rehabilitation)) North Capital Campus Executive Office Building(s) (06-1-002)

     The appropriation in this section is subject to the following conditions and limitations: Funding is provided solely for predesign for replacement or renovation of the general administration building combined with the development of an office building on the block adjoining Capital Way and 11th avenue. The combined development is intended to provide: (1) Executive office space for statewide elected officials; (2) public access space for the state library collection and historically significant documents from the state archives and the state historical museum; and (3) high density general office space that can adapt to changing state needs. The project will maximize interagency sharing of support services such as information technology, printing and mailing, management and storage of supplies, reception areas, and other common functions. The project will also include sufficient parking to provide a significant net increase in parking spaces beyond what is required for the new office space. The project shall also include leasable ground floor retail space on Capital Way. The department shall consult with statewide elected officials and the city of Olympia in developing the predesign. ((The predesign shall evaluate the use of the Pritchard building as one of the options for use by the state library and historically significant documents from the state archives and state historical museum.)) Due to the intended replacement of the building adjoining Capital Way and 11th avenue, the department shall not charge the facility depreciation component of lease charges for nonprofit tenants in that facility during the 2005-2007 biennium.

Appropriation:
     Thurston County Capital Facilities Account--State . . . . . . . . . . . . (($750,000))
       $1,650,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . (($65,500,000))
       $312,017,000
          TOTAL . . . . . . . . . . . . (($66,250,000))
       $313,667,000

Sec. 115   2005 c 488 s 156 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF GENERAL ADMINISTRATION
     Statewide Office Facilities: Preservation Minor Works (06-1-003)

     The appropriations in this section are subject to the following conditions and limitations: Funding is provided for electrical and elevator upgrades in the insurance building.

Appropriation:
     Thurston County Capital Facilities Account--State . . . . . . . . . . . . $2,965,000
     General Administration Service Account--State . . . . . . . . . . . . $1,850,000
          Subtotal Appropriation . . . . . . . . . . . . $4,815,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $16,239,000
          TOTAL . . . . . . . . . . . . $21,054,000

NEW SECTION.  Sec. 116   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF GENERAL ADMINISTRATION
     Capital Campus Master Plan (06-2-001)

Appropriation:
     General Administration Services Account--State . . . . . . . . . . . . $200,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $200,000

NEW SECTION.  Sec. 117   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF GENERAL ADMINISTRATION
     Senate Electronic Voting Machine (06-2-852)

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $500,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $500,000

Sec. 118   2005 c 488 s 201 (uncodified) is amended to read as follows:
FOR THE CRIMINAL JUSTICE TRAINING COMMISSION
     School Mapping (06-1-100)

     The appropriations in this section ((is)) are subject to the following conditions and limitations: ((The appropriation is provided solely for the initial mapping of schools and production of software and may not be used to supplant any local government's existing school or other building mapping program that can transfer data to a statewide first responder building mapping information system.)) Mapping of ((public buildings, including)) school buildings((,)) shall be undertaken under standards adopted by the Washington association of sheriffs and police chiefs mapping software standards as required by RCW 36.28A.070. The ((criminal justice training commission)) Washington association of sheriffs and police chiefs shall work with the office of the superintendent of public instruction to ensure school mapping is part of newly constructed or renovated construction projects ((and shall develop policies and procedures to ensure efficient use and implementation of such procedures)). For school construction projects funded through the state board of education's state school construction assistance program during the 2005-2007 biennium, the Washington association of sheriffs and police chiefs shall prioritize the initial mapping or remapping of the state board of education's state school construction assistance program projects that are colocated with schools funded by the appropriation in this section. Additionally, the Washington association of sheriffs and police chiefs shall develop policies and procedures to ensure efficient use and implementation of such procedures.
     It is the intention of the legislature that the design of new and remodeled facilities incorporate mapping and remapping as needed.
     The Washington association of sheriffs and police chiefs will consult with the office of the superintendent of public instruction and report to the fiscal committees of the legislature on efficient and low-cost ways to maintain up-to-date maps.


Appropriation:
     Education Construction Account--State . . . . . . . . . . . . $4,500,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $4,500,000

Sec. 119   2005 c 488 s 206 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES
     Echo Glen Children's Center - Housing Units (00-1-041)

Reappropriation:
     State Building Construction Account--State . . . . . . . . . . . . $500,000
Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $5,800,000


     Prior Biennia (Expenditures) . . . . . . . . . . . . $5,605,495
     Future Biennia (Projected Costs) . . . . . . . . . . . . (($16,100,000))
       $10,300,000
          TOTAL . . . . . . . . . . . . $22,205,495

NEW SECTION.  Sec. 120   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES
     Green Hill School: New Intensive Management Unit Building, and Health Center and Administration Building (06-2-202)

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $1,250,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $12,500,000
          TOTAL . . . . . . . . . . . . $13,750,000

Sec. 121   2005 c 488 s 238 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES
     Washington Information Network 2-1-1 (06-2-850)

     The appropriation in this section is subject to the following conditions and limitations: The department shall require the organizations to prepare a financing plan that specifies the full cost of implementing the system statewide including capital costs and operating costs by September 1, 2006. The financing plan shall identify appropriate sources of revenue to support full implementation and ongoing operational costs. Allowable uses of appropriated funds include the purchase of software, equipment, programming, and improvements located in states adjacent to Washington and that support the 2-1-1 information network in Washington.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $1,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $1,000,000

NEW SECTION.  Sec. 122   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF VETERANS AFFAIRS
     Retsil Building 9 Renovation - Transient Program (06-1-008)

Appropriation:
     General Fund--Federal . . . . . . . . . . . . $318,000
     State Building Construction Account--State . . . . . . . . . . . . $171,000
          Subtotal Appropriation . . . . . . . . . . . . $489,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $489,000

Sec. 123   2005 c 488 s 252 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF CORRECTIONS
     Coyote Ridge Corrections Center: Expansion (98-2-011)

     The appropriations in this section are subject to the following conditions and limitations:
     (1) (($179,000,000)) The appropriation in this section is provided solely to design and construct a ((1,280)) 1,792 bed medium-security prison at Coyote Ridge corrections center in Connell.
     (2) The facility shall be a publicly-owned and operated facility.
     (3) The new facility shall include at least 512 hybrid-security beds that have a lower cost to construct than conventional medium security beds but still maintain a medium security perimeter.
     (4) Design of the facility shall incorporate efficiencies in administrative space and support services realized by sharing services within the region. The department shall examine other states' and private industry standard designs, and report on how efficiencies will be incorporated into the design of the facility to the office of financial management and to legislative fiscal staff not later than September 1, 2005. Nothing in this subsection requires the department to adopt design parameters that would endanger public safety or generate increased operating costs.
     (5) Once opened, a portion of the new facility shall be used to alleviate the crowded conditions in reception at the Washington corrections center in Shelton.

Reappropriation:
     State Building Construction Account--State . . . . . . . . . . . . $921,140
Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . (($179,000,000))
       $229,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $986,347
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($180,907,487))
       $230,907,487

Sec. 124   2005 c 488 s 255 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF CORRECTIONS
     Monroe Corrections Center: 100-Bed Management and Segregation Unit (00-2-008)

Reappropriation:
     General Fund--Federal . . . . . . . . . . . . $819,229
     State Building Construction Account--State . . . . . . . . . . . . (($18,674,000))
       $17,747,000
          Subtotal Reappropriation . . . . . . . . . . . . (($19,493,229))
       $18,566,229
Appropriation:
     General Fund--Federal . . . . . . . . . . . . $927,000


     Prior Biennia (Expenditures) . . . . . . . . . . . . $19,944,803
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $39,438,032

Sec. 125   2005 c 488 s 264 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF CORRECTIONS
     Washington State Penitentiary: North Close Security Compound (04-2-005)

Reappropriation:
     State Building Construction Account--State . . . . . . . . . . . . $124,000,000
Appropriation:
     ((General Fund--Federal . . . . . . . . . . . . $927,000))
     State Building Construction Account--State . . . . . . . . . . . . (($5,891,000))
       $6,818,000
          ((Subtotal Appropriation . . . . . . . . . . . . $6,818,000))

     Prior Biennia (Expenditures) . . . . . . . . . . . . $9,940,000
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $140,758,000

NEW SECTION.  Sec. 126   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF CORRECTIONS
     Washington State Penitentiary: Replace Correctional Industry Roof (06-1-023)

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $1,453,000
     Charitable, Educational, Penal, and Reformatory
          Institutions Account--State . . . . . . . . . . . . $1,998,000
          Subtotal Appropriation . . . . . . . . . . . . $3,451,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $3,451,000

NEW SECTION.  Sec. 127   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF CORRECTIONS
     Cedar Creek Corrections Center: 100 Bed Expansion (06-2-851)

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $6,228,500

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $6,228,500

NEW SECTION.  Sec. 128   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF CORRECTIONS
     Larch Corrections Center: 80 Bed Expansion (06-2-852)

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $3,071,500

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $3,071,500

Sec. 129   2005 c 488 s 287 (uncodified) is amended to read as follows:
FOR THE EMPLOYMENT SECURITY DEPARTMENT
     Employment Resource Center (05-2-001)

     The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is provided solely ((to)) for services and activities including the purchase and ((install)) installation of state of the art equipment for a 40,000 square foot facility supporting work force development programs using funds available to the state in section 903(d) of the Social Security Act (Reed act).

Reappropriation:
     Unemployment Compensation Administration
          Account--Federal . . . . . . . . . . . . $6,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $6,000,000

Sec. 130   2005 c 488 s 323 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
     Centennial Clean Water Program (06-4-007)

     The appropriations in this section are subject to the following conditions and limitations:
     (1) Up to $10,000,000 of the state building construction account--state appropriation is provided for the extended grant payment to Spokane for the Spokane-Rathdrum Prairie aquifer.
     (2) $5,000,000 of the state building construction account--state appropriation is provided solely for water quality grants for hardship communities with a population of less than 5,000. The department shall give priority consideration to: (a) Communities subject to a regulatory order from the department of ecology for noncompliance with water quality rules; (b) projects for which design work has been completed; and (c) projects with a local match from reasonable water quality rates and charges.
     (3) $1,000,000 of the state building construction account--state appropriation is provided solely to design appropriate wastewater treatment facilities to serve the Hoodsport to Skokomish reservation areas of Hood Canal. The exact facilities will be based upon the recommendations from an analysis of wastewater management options for the Hoodsport to Skokomish river currently being undertaken by Mason county.
     (4) $750,000 of the state building construction account--state appropriation is provided solely for assistance in management and clean up activities at Long Lake in Kitsap county and $50,000 of the state building construction account--state appropriation is provided solely for assistance in cleaning up Wapato Lake in Pierce county. The assistance is contingent on the lake communities adopting a lake management plan that meets the department's requirement.
     (5) $320,000 of the water quality account--state appropriation is provided solely to Mason county to develop a septic system data base and identify failing septic systems in Hood Canal.
     (6) $70,000 of the water quality account--state appropriation is provided solely to Kitsap county for surveys of septic systems in Hood Canal.
     (7) $70,000 of the water quality account--state appropriation is provided solely to Jefferson county for surveys of septic systems in Hood Canal.
     (8) Up to $1,500,000 of the water quality account--state appropriation is provided solely for grants for on-site sewage replacement. This appropriation may be used to: (a) Establish new or expand existing on-site sewage repair and replacement loan or grant programs by county governments or tribes; or (b) develop a pilot program to administer an on-site sewage repair and replacement loan program through a qualified private or nonprofit lending institution. This appropriation must be used in conjunction with the water pollution control revolving account--state appropriation in section 134 of this act provided for this purpose. Of this amount, up to $1,000,000 may be used to help financially distressed homeowners repair and replace failing on-site sewage systems, and up to $500,000 may be used to help local governments plan, implement, and administer the local loan fund assistance programs. The total overall local government and tribal administration costs may not exceed seven percent of the total statewide grant and loan on-site program. The department must report on the use of these funds to the Puget Sound water quality action team as part of its activities under the 2005-2007 Puget Sound conservation and recovery plan.
     (9) $3,500,000 of the state toxics control account--state appropriation is provided solely for wastewater treatment upgrades at Twanoh, Dosewallips, Fort Casey, Fort Ebey, Birch Bay, and Sequim Bay state parks.

     (10) $1,000,000 of the state toxics control account--state appropriation is provided solely for the city of Carnation wastewater treatment facility.
     (11)
The remaining appropriation in this section is provided for statewide water quality implementation and planning grants and loans.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $20,000,000
     Water Quality Account--State . . . . . . . . . . . . (($7,500,000))
       $9,000,000
     State Toxics Control Account--State . . . . . . . . . . . . (($10,500,000))
       $15,000,000
          Subtotal Appropriation . . . . . . . . . . . . (($38,000,000))
       $44,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $211,808,000
          TOTAL . . . . . . . . . . . . (($249,808,000))
       $255,808,000

Sec. 131   2005 c 488 s 324 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
     State Drought Preparedness (05-4-009)

     The reappropriation in this section is subject to the following conditions and limitations:
     (1) The reappropriation in this section is provided solely for response to the statewide drought that was declared pursuant to chapter 43.83B RCW. The department of ecology may provide funding or compensation for purchase or lease of water rights and to public bodies as defined in RCW 43.83B.050 in connection with projects and measures designed to alleviate drought conditions which may affect: Public health and safety; drinking water supplies; agricultural activities; or fish and wildlife survival.
     (2) Projects or measures for which funding or compensation will be provided must be connected with a water system, water source, or water body which is receiving, or has been projected to receive, less than seventy-five percent of normal water supply, as the result of natural drought conditions. This reduction in water supply must be such that it is causing, or will cause, undue hardship for the entities or fish or wildlife depending on the water supply. General criteria for guidelines to be established by the department of ecology for distribution of funds must include: A balanced and equitable distribution of the funds among the different sectors affected by drought; a funding process that ensures funds are available for drought impacts that arise both early and later during the course of the drought; and preference for projects that leverage other federal and local funds.
     (3) Up to $1,500,000 of the reappropriation in this section is provided to the Roza irrigation district for the purchase or lease of water rights.
     (4) Of the funds provided in this section, $150,000 is provided solely to support the development and demonstration of water management measures in the Walla Walla Basin that improve and protect instream flow and water quality, and which also help sustain agricultural and economic vitality. The director of the department shall report to the legislature by December 31, 2006, with any findings, conclusions, and recommendations regarding such water management measures.
     (5) $50,000 of the reappropriation in this section is provided solely to Chelan county to assess the feasibility of storing water in Campbell creek canyon to supplement instream flows in Peshastin creek, as part of the Peshastin irrigation district.


Reappropriation:
     State Drought Preparedness Account--State . . . . . . . . . . . . (($8,200,000))
       $7,230,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($8,200,000))
       $7,230,000

Sec. 132   2005 c 488 s 325 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
     Local Toxics Grants for Clean up and Prevention (06-4-008)

     The appropriation in this section is subject to the following conditions and limitations:
     (1) $4,000,000 of the appropriation is provided solely for grants to local governments for local projects that implement the state "never waste" plan. Grant funds will emphasize additional organics composting and conversion, green building, and moderate risk waste projects described in the plan. Of this amount, up to $1,600,000 may be used for one-time funding for auto switch recycling consistent with the memorandum of agreement being finalized with the auto recyclers association.
     (2) $2,000,000 of the appropriation is provided for emission reduction projects for local governments to retrofit public sector diesel engines with exhaust emission control devices or to make other modifications or operational changes, including cleaner fuels, to allow public sector fleets to reduce their emissions.
     (3) $3,000,000 of the appropriation is provided solely for grants to local governments needing assistance in complying with the new phase II storm water permit requirements. Of this amount, $300,000 is provided solely for Mason county to prepare storm water management plans for Belfair and Hoodsport consistent with the storm water program in the Puget Sound conservation and recovery plan.
     (4) (($60,000,000)) $70,900,000 of the appropriation is provided solely for remedial action grants. Of this amount, $1,000,000 is provided to the town of Warden to respond to contamination of their existing water system.
     (5) From within this appropriation, the department shall prepare an online guide to help small businesses and homeowners learn what to do if they discover toxic wastes on their property. The guide shall provide information about local resources for clean up and disposal of toxic wastes.
     (6) $8,000,000 of the appropriation is provided solely for coordinated prevention grants provided to local governments for local government solid and hazardous waste planning, household and small business hazardous waste collection and disposal, recycling capital purchases and program development, and local solid waste enforcement.

Appropriation:
     Local Toxics Control Account--State . . . . . . . . . . . . (($80,000,000))
       $98,900,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $45,000,000
     Future Biennia (Projected Costs) . . . . . . . . . . . . $180,000,000
          TOTAL . . . . . . . . . . . . (($315,000,000))
       $323,900,000

Sec. 133   2005 c 488 s 327 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
     Safe Soil Remediation and Awareness Projects (06-2-001)

Appropriation:
     State Toxics Control Account--State . . . . . . . . . . . . (($2,000,000))
       $5,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($2,000,000))
       $5,000,000

Sec. 134   2005 c 488 s 329 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
     Water Pollution Control Revolving Account (06-4-002)

     The appropriations in this section are subject to the following conditions and limitations:
     (1) The department shall give priority loan funding consideration to on-site septic system rehabilitation and replacement programs in Mason, Kitsap, and Jefferson counties for at least $1,000,000 from the water pollution control revolving account--state in the second year of the funding cycle.
     (2) Up to $5,000,000 of the water pollution control revolving account--state appropriation is provided solely for loans for on-site sewage replacement. This appropriation may be used to: (a) Establish new or expand existing on-site sewage repair and replacement loan programs by county governments or tribes; or (b) develop a pilot program to administer an on-site sewage repair and replacement loan program through a qualified private or nonprofit lending institution. This appropriation must be used in conjunction with water quality account--state appropriation in section 130 of this act provided for this purpose. The department must work with the department of health, the Puget Sound water quality action team, local governments, and the lending industry in developing and piloting this program. The department shall provide a status report on the loan program to the governor and the appropriate legislative fiscal committees by June 30, 2007, including any recommendations for improving the program. The department must report on the use of these funds to the Puget Sound water quality action team as part of its activities under the 2005-2007 Puget Sound conservation and recovery plan.

Appropriation:
     Water Pollution Control Revolving
          Account--State . . . . . . . . . . . . $162,839,146
     Water Pollution Control Revolving
          Account--Federal . . . . . . . . . . . . $76,777,140
          Subtotal Appropriation . . . . . . . . . . . . $239,616,286

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $912,000,000
          TOTAL . . . . . . . . . . . . $1,151,616,286

NEW SECTION.  Sec. 135   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
     Motor Vehicle Mercury Removal Program (06-2-850)

     The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is for one-time funding to implement the memorandum of agreement establishing the Washington motor vehicle mercury switch removal program. If chapter ... (Second Substitute House Bill No. 1731), Laws of 2006 is enacted by June 30, 2006, then the amount in this section shall be appropriated to the Hood Canal aquatic rehabilitation program under the interagency committee for outdoor recreation in section 151 of this act.

Appropriation:
     State Toxics Control Account--State . . . . . . . . . . . . $1,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $1,000,000

NEW SECTION.  Sec. 136   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
     Early Spill Response Equipment Caching (06-1-003)

     The appropriation in this section is subject to the following conditions and limitations: $1,450,000 of the appropriation is provided solely for grants to local governments to secure and place hazardous material spill response equipment at critical locations around the state. Grant funds will emphasize strategic placement of equipment that will allow for quick access and deployment by state, local, or tribal responders in the event of a spill.

Appropriation:
     Local Toxics Control Account--State . . . . . . . . . . . . $1,450,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $1,450,000

NEW SECTION.  Sec. 137   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
     Local Innovative Storm Water Grants (06-2-006)

     The appropriation in this section is subject to the following conditions and limitations: This appropriation is provided solely for grants to local governments in Puget Sound to fund innovative, low-impact development storm water management projects to meet critical storm water management needs and protect or restore water quality. Projects may include use of bioretention, rainwater harvest, permeable pavement, vegetated roofs, and other low-impact development techniques. Projects funded in Puget Sound must meet the design guidelines contained in the low impact development technical guidance manual for Puget Sound, unless the municipality can demonstrate that site conditions warrant a deviation from the design guidelines and the deviations in design shall provide similar performance. All projects must include performance monitoring. The department must report on the use of these funds to the Puget Sound water quality action team as part of its activities under the 2005-2007 Puget Sound conservation and recovery plan.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $2,500,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $2,500,000

NEW SECTION.  Sec. 138   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
     Waste Tire Clean Up (06-1-002)

     The appropriation in this section is subject to the following conditions and limitations: Funding is provided solely for the department to initiate clean up of waste tires at the highest risk sites statewide. This clean up work must include major progress at the Goldendale site in Klickitat county.

Appropriation:
     Waste Tire Removal Account--State . . . . . . . . . . . . $4,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $4,000,000

NEW SECTION.  Sec. 139   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
     Clean Up Toxics Sites - Puget Sound (06-4-001)

     The appropriation in this section is subject to the following conditions and limitations: Funding is provided for the clean up of contaminated sites that lie adjacent to and are within one-half mile of Puget Sound. Clean ups must include orphan and abandoned sites that pose a threat to Puget Sound with the highest priority sites being cleaned up first. The department must report on the use of these funds to the Puget Sound water quality action team as part of its activities under the 2005-2007 Puget Sound conservation and recovery plan.

Appropriation:
     State Toxics Control Account--State . . . . . . . . . . . . $4,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $4,000,000

NEW SECTION.  Sec. 140   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
     Clean Up Toxic Sites - Upland and Aquatics (06-1-005)

     The appropriation in this section is subject to the following conditions and limitations: The department must report on the use of these funds to the Puget Sound water quality action team as part of its activities under the 2005-2007 Puget Sound conservation and recovery plan.

Appropriation:
     State Toxics Control Account--State . . . . . . . . . . . . $5,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $5,000,000

NEW SECTION.  Sec. 141   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
     Columbia River Basin Water Supply Development Program (06-2-950)

     The appropriation in this section is subject to the following conditions and limitations: The appropriation is provided solely for implementation of the Columbia river basin water supply development program in chapter ... (Engrossed Second Substitute House Bill No. 2860), Laws of 2006.

Appropriation:
     Columbia River Basin Water Supply
          Development Account--State . . . . . . . . . . . . $10,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $10,000,000

Sec. 142   2005 c 488 s 340 (uncodified) is amended to read as follows:
FOR THE STATE PARKS AND RECREATION COMMISSION
     Minor Works: Facility Preservation (04-1-001)

     The reappropriations in this section are subject to the following conditions and limitations: The reappropriations in this section are provided solely to continue minor works projects that reduce the deferred maintenance backlog.

Reappropriation:
     State Building Construction Account--State . . . . . . . . . . . . $147,269
     Parks Renewal and Stewardship Account--State . . . . . . . . . . . . (($2,600,000))
       $679,079
          Subtotal Reappropriation . . . . . . . . . . . . (($2,747,269))
       $826,348

     Prior Biennia (Expenditures) . . . . . . . . . . . . $4,990,231
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($7,737,500))
       $5,816,579

Sec. 143   2005 c 488 s 341 (uncodified) is amended to read as follows:
FOR THE STATE PARKS AND RECREATION COMMISSION
     Parkland Acquisition (04-2-013)

Reappropriation:
     Parkland Acquisition Account--State . . . . . . . . . . . . (($412,690))
       $191,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($412,690))
       $191,000

Sec. 144   2005 c 488 s 342 (uncodified) is amended to read as follows:
FOR THE STATE PARKS AND RECREATION COMMISSION
     Recreation Development (04-2-002)

     The reappropriation in this section is subject to the following conditions and limitations:
     (1) Up to $100,000 of the reappropriation shall be used to retain a consultant to conduct a predesign study for a headquarters building located in Thurston county. The predesign shall compare a new leased facility against options to build and evaluate appropriate funding strategies.
     (2) (($900,000)) Up to $700,000 of the reappropriation is provided ((solely)) to install fee collection stations at selected parks statewide. Any unused funding of this reappropriation may be expended on other recreation development projects.
     (3) In addition to the annual project progress reporting requirement of RCW 43.88.160(3), the commission shall file quarterly project progress reports with the office of financial management.

Reappropriation:
     State Building Construction Account--State . . . . . . . . . . . . $700,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $2,200,000
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $2,900,000

Sec. 145   2005 c 488 s 346 (uncodified) is amended to read as follows:
FOR THE STATE PARKS AND RECREATION COMMISSION
     Beacon Rock - Pierce Trust (06-1-030)

     The appropriation in this section is subject to the following conditions and limitations:
     (1) The appropriation in this section is provided solely for improvements to ((the group camp at)) Beacon Rock state park.
     (2) The funding has been provided solely and directly for this project.

Appropriation:
     Parks Renewal and Stewardship Account--Private/Local . . . . . . . . . . . . $350,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $350,000

NEW SECTION.  Sec. 146   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE STATE PARKS AND RECREATION COMMISSION
     Sustainable Development and Restoration (06-1-011)

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $500,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $500,000

Sec. 147   2005 c 488 s 360 (uncodified) is amended to read as follows:
FOR THE STATE PARKS AND RECREATION COMMISSION
     Parkland Acquisition Account (06-2-020)

     The appropriation in this section is subject to the following conditions and limitations: The state parks and recreation commission shall provide lists of potential purchases and sales to the office of financial management and the legislature prior to committing the state parks and recreation commission to any sale or purchase of land or buildings and prior to any allotments made for those purchases. Included in the lists will be any potential operating or capital cost impacts known to the state parks and recreation commission.

Appropriation:
     Parkland Acquisition Account--State . . . . . . . . . . . . (($4,000,000))
       $6,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $16,000,000
          TOTAL . . . . . . . . . . . . (($20,000,000))
       $22,000,000

Sec. 148   2005 c 488 s 365 (uncodified) is amended to read as follows:
FOR THE STATE PARKS AND RECREATION COMMISSION
     Park Development (06-1-950)

     The appropriation in this section is subject to the following conditions and limitations:
     (1) $250,000 is provided solely to construct a pedestrian/emergency vehicle access bridge across Connor creek to allow for beach access.
     (2) $500,000 is provided solely to determine long-term park zoning, design park amenities and services, and provide site permit and initial construction development at Nisqually-Mashel. The state parks and recreation commission shall provide a predesign in accordance with the office of financial management's predesign instructions.
     (3) $150,000 is provided solely for initial park development at Sequim Bay-Miller Peninsula. The state parks and recreation commission shall provide a predesign in accordance with the office of financial management's predesign instructions.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $900,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $900,000

NEW SECTION.  Sec. 149   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE STATE PARKS AND RECREATION COMMISSION
     Hood Canal Wastewater and Improvement Projects (06-1-850)

     The appropriation in this section is subject to the following conditions and limitations: The appropriation is provided solely for wastewater and clean water improvement projects at the following locations:

Projects       Amount
Twanoh state park       $100,000
Dosewallips state park       $1,200,000
Belfair state park       $700,000
Potlatch state park       $1,050,000
Kitsap Memorial state park       $500,000
Scenic Beach state park       $900,000
Twanoh and Triton Cove state parks       $300,000
Shine Tidelands state park       $850,000
Pleasant Harbor state park       $150,000
Triton Cove state park       $170,000
Total       $5,920,000

Appropriation:
     Hood Canal Aquatic Rehabilitation Bond
          Account--State . . . . . . . . . . . . $5,920,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $5,920,000

NEW SECTION.  Sec. 150   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE STATE PARKS AND RECREATION COMMISSION
     Puget Sound Wastewater and Improvement Projects (06-1-851)

     The appropriation in this section is subject to the following conditions and limitations: The appropriation is provided solely for wastewater and clean water improvement projects at the following locations:

Projects       Amount
Sequim Bay state park       $125,000
Fort Flagler state park       $750,000
Larabee state park       $750,000
Fort Worden state park       $300,000
Camano Island state park       $300,000
Deception Pass state park       $350,000
Possession Point       $250,000
Illahee state park       $1,100,000
Kopachuck state park       $1,200,000
Penrose Point state park       $700,000
Blake Island state park       $250,000
Fay Bainbridge state park       $1,300,000
Total       $7,375,000

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $7,375,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $7,375,000

NEW SECTION.  Sec. 151   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Hood Canal Aquatic Rehabilitation Program (06-4-850)

     The appropriation in this section is subject to the following conditions and limitations:
     (1) The Puget Sound action team and the local management board shall develop a list of projects, studies, and activities relating to the recovery of Hood Canal in accordance with RCW 90.88.030. The list developed shall be based upon the project's likely value in addressing and resolving Hood Canal's low-dissolved oxygen concentrations.
     (2) The Puget Sound action team and the local management board shall recommend to the interagency committee for outdoor recreation and the governor a prioritized list of projects to be funded under subsection (1) of this section. The governor may remove projects from the list recommended by the Puget Sound action team and the local management board and shall submit this amended list in the capital budget request to the legislature. The list shall include, but not be limited to, a description of each project and the amount of recommended state funding.
     (3) The interagency committee for outdoor recreation shall not sign contracts or otherwise financially obligate funds from the Hood Canal aquatic rehabilitation bond account before the legislature has appropriated funds for a specific list of projects. The legislature may remove projects from the list recommended by the Puget Sound action team and the local management board.

Appropriation:
     Hood Canal Aquatic Rehabilitation Bond
          Account--State . . . . . . . . . . . . $1,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $42,600,000
          TOTAL . . . . . . . . . . . . $43,600,000

Sec. 152   2005 c 488 s 368 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Firearms and Archery Range Program (FARP) (98-2-004)

Reappropriation:
     Firearms Range Account--State . . . . . . . . . . . . (($31,478))
       $61,478

     Prior Biennia (Expenditures) . . . . . . . . . . . . $542,191
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($573,669))
       $603,669

Sec. 153   2005 c 488 s 369 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Nonhighway Off-road Vehicle Program (NOVA) (98-2-002)

Reappropriation:
     Nonhighway and Off-Road Vehicle Activities
          Program Account--State . . . . . . . . . . . . (($1,243,986))
       $1,322,986

     Prior Biennia (Expenditures) . . . . . . . . . . . . $9,851,937
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($11,095,923))
       $11,174,923

Sec. 154   2005 c 488 s 370 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Washington Wildlife and Recreation Program (WWRP) (98-2-003)

     The reappropriations in this section are subject to the following conditions and limitations: Any amount of the reappropriations that is not obligated to a specific project may be used to fund alternate projects approved by the legislature from the same account in biennia succeeding that in which the moneys were originally appropriated.

Reappropriation:
     Outdoor Recreation Account--State . . . . . . . . . . . . $4,547,515
     Habitat Conservation Account--State . . . . . . . . . . . . (($1,170,894))
       $4,382,894
          Subtotal Reappropriation . . . . . . . . . . . . (($5,718,409))
       $8,930,409

     Prior Biennia (Expenditures) . . . . . . . . . . . . $71,883,173
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($77,601,582))
       $80,813,582

Sec. 155   2005 c 488 s 372 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Salmon Recovery Funding Board Programs (SRFB) (00-2-001)

Reappropriation:
     General Fund--Federal . . . . . . . . . . . . (($11,227,424))
       $13,320,424
     Salmon Recovery Account--State . . . . . . . . . . . . (($2,366,010))
       $3,597,010
          Subtotal Reappropriation . . . . . . . . . . . . (($13,593,434))
       $16,917,434

     Prior Biennia (Expenditures) . . . . . . . . . . . . $88,031,707
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($101,625,141))
       $104,949,141

Sec. 156   2005 c 488 s 376 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Firearms and Archery Range Program (02-0-001)

Reappropriation:
     Firearms Range Account--State . . . . . . . . . . . . (($44,677))
       $120,677

     Prior Biennia (Expenditures) . . . . . . . . . . . . $355,323
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($400,000))
       $476,000

Sec. 157   2005 c 488 s 382 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Wildlife and Recreation Program (WWRP) (02-4-003)

     The reappropriations in this section are subject to the following conditions and limitations: Any amount of the reappropriations that is not obligated to a specific project may be used to fund projects in the following order: (1) The department of natural resources Cypress Island project; and (2) alternate projects approved by the legislature from the same account in biennia succeeding that in which the funds were originally appropriated.

Reappropriation:
     Outdoor Recreation Account--State . . . . . . . . . . . . (($2,041,864))
       $3,525,864
     Habitat Conservation Account--State . . . . . . . . . . . . $6,928,926
          Subtotal Reappropriation . . . . . . . . . . . . (($8,970,790))
       $10,454,790

     Prior Biennia (Expenditures) . . . . . . . . . . . . $36,029,210
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($45,000,000))
       $46,484,000

Sec. 158   2005 c 488 s 385 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Boating Facilities Program (BFP) (04-4-003)

Reappropriation:
     Recreation Resources Account--State . . . . . . . . . . . . (($3,753,480))
       $4,484,480

     Prior Biennia (Expenditures) . . . . . . . . . . . . $3,753,479
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($7,506,959))
       $8,237,959

Sec. 159   2005 c 488 s 386 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Firearms and Archery Range Program (04-4-006)

Reappropriation:
     Firearms Range Account--State . . . . . . . . . . . . (($144,997))
       $154,997

     Prior Biennia (Expenditures) . . . . . . . . . . . . $105,003
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($250,000))
       $260,000

Sec. 160   2005 c 488 s 387 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Family Forest Fish Blockages Program (04-4-011)

Reappropriation:
     State Building Construction Account--State . . . . . . . . . . . . (($780,379))
       $1,191,379

     Prior Biennia (Expenditures) . . . . . . . . . . . . $1,219,621
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($2,000,000))
       $2,411,000

Sec. 161   2005 c 488 s 390 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     National Recreation Trails Program (NRTP) (04-4-008)

Reappropriation:
     General Fund--Federal . . . . . . . . . . . . (($1,130,000))
       $1,447,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $1,130,000
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($2,260,000))
       $2,577,000

Sec. 162   2005 c 488 s 391 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Nonhighway and Off-Road Vehicle Activities Program (NOVA) (04-4-004)

Reappropriation:
     NOVA Program Account--State . . . . . . . . . . . . (($5,492,729))
       $5,620,729

     Prior Biennia (Expenditures) . . . . . . . . . . . . $1,433,581
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($6,926,310))
       $7,054,310

Sec. 163   2005 c 488 s 392 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Salmon Recovery Funding Board Programs (SRFB) (04-4-001)

Reappropriation:
     General Fund--Federal . . . . . . . . . . . . (($32,832,305))
       $35,876,305
     State Building Construction Account--State . . . . . . . . . . . . (($11,500,000))
       $13,885,000
          Subtotal Reappropriation . . . . . . . . . . . . (($44,332,305))
       $49,761,305

     Prior Biennia (Expenditures) . . . . . . . . . . . . $1,000,000
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($45,332,305))
       $50,761,305

Sec. 164   2005 c 488 s 398 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Family Forest Fish Passage Program (06-4-011)

     The appropriations in this section are subject to the following conditions and limitations:
     (1) The appropriation is provided solely for the salmon recovery funding board in consultation with the small forest landowner office of the department of natural resources and the department of fish and wildlife to provide grants to correct fish passage blockages on nonindustrial forest lands. Selection of projects must be coordinated with the other salmon recovery grant programs provided in section 403 of this act.
     (2) In addition to the annual project progress reporting requirement of RCW 43.88.160(3), the committee shall file quarterly project progress reports with the office of financial management.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $4,150,000
     General Fund--Federal . . . . . . . . . . . . $217,000
          Subtotal Appropriation . . . . . . . . . . . . $4,367,000


     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($4,150,000))
       $4,367,000

Sec. 165   2005 c 488 s 401 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Nonhighway and Off-Road Vehicle Program (NOVA) (06-4-004)

     The appropriation in this section is subject to the following conditions and limitations: $345,000 of the appropriation is for implementation of the off-road vehicle data base authorized in chapter ... (Substitute House Bill No. 2658), Laws of 2006. If the bill is not enacted by June 30, 2006, the amount in this section shall be used for the nonhighway and off-road vehicle program.

Appropriation:
     Nonhighway and Off-Road Vehicle Activities
          Program Account--State . . . . . . . . . . . . $7,579,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $39,946,858
          TOTAL . . . . . . . . . . . . $47,525,858

Sec. 166   2005 c 488 s 402 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     National Recreation Trails Program (NRTP) (06-4-008)

     The appropriation in this section is subject to the following conditions and limitations: $500,000 is provided solely for mountains to sound greenway outdoor recreation projects on the I-90 corridor located in King county and western Kittitas county. Projects must be recreational or scenic in nature, including recreational trail development and expansion, visitor facilities enhancement, sign location, snopark improvements, and property acquisition.

Appropriation:
     General Fund--Federal . . . . . . . . . . . . (($2,350,000))
       $2,800,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $9,400,000
          TOTAL . . . . . . . . . . . . (($11,750,000))
       $12,200,000

Sec. 167   2005 c 488 s 395 (uncodified) is amended to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Boating Facilities Program (BFP) (06-4-003)

     The appropriation in this section is subject to the following conditions and limitations: Any amount of the appropriation that is not obligated to a specific project in the first application round shall be used to fund boat sewage disposal facilities.

Appropriation:
     Recreation Resources Account--State . . . . . . . . . . . . (($8,350,000))
       $7,271,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $36,597,535
          TOTAL . . . . . . . . . . . . (($44,947,535))
       $43,868,535

NEW SECTION.  Sec. 168   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION
     Local Parks - Level of Service Standard Study (06-2-851)

     The appropriation in this section is subject to the following conditions and limitations:
     (1) The appropriation in this section is provided solely for the interagency committee for outdoor recreation to develop recommendations for a statewide approach to a recreation level of service for local and regional active recreation facilities, including indicators with which to measure progress in achieving level of service objectives. The recommendations must be coordinated with those of the priorities of government effort. The interagency committee for outdoor recreation shall also recommend standardized definitions for types of parks and recreational facilities, and a process for periodically measuring performance indicators and reporting the results. The interagency committee for outdoor recreation may enter into a contract with an entity with expertise in parks facility planning, level of service standards, and geographic information systems.
     (2) The interagency committee for outdoor recreation shall submit a report to the appropriate committees of the legislature by January 1, 2007. The report must include the following: (a) Level of service standards including individual participation measures; (b) service area analysis using geographic information system tools and techniques; and (c) recommendations to incorporate level of service reporting into grant-in-aid programs.

Appropriation:
     Youth Athletic Facility Account--State . . . . . . . . . . . . $50,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $50,000

Sec. 169   2005 c 488 s 414 (uncodified) is amended to read as follows:
FOR THE STATE CONSERVATION COMMISSION
     Skokomish Anaerobic Digester (06-4-009)

     The appropriation in this section is subject to the following conditions and limitations: The appropriation is provided solely for a grant to the Mason conservation district for construction of an anaerobic digester in the Skokomish river watershed. Up to (($50,000)) $65,000 of this amount may be spent on completing design concepts and feasibility analysis. The remaining funds shall be allotted only after the following has occurred: (1) Mason conservation district secures nonstate matching funds or in-kind contributions of at least twenty-five percent of the total project cost; (2) a feasibility study is completed and submitted to the Puget Sound action team and the state conservation commission; and (3) the Puget Sound action team and the state conservation commission approve the project proposal.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $560,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $560,000

Sec. 170   2005 c 488 s 425 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF FISH AND WILDLIFE
     Facility, Infrastructure, Lands, and Access Condition Improvements (06-1-002)

     The appropriations in this section are subject to the following limitations: $5,000 of the appropriation in this section is provided solely for bank stabilization of the south Toledo access road.

Appropriation:
     General Fund--Federal . . . . . . . . . . . . $650,000
     State Building Construction Account--State . . . . . . . . . . . . $6,457,000
          Subtotal Appropriation . . . . . . . . . . . . $7,107,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $26,600,000
          TOTAL . . . . . . . . . . . . $33,707,000

Sec. 171   2005 c 488 s 427 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF FISH AND WILDLIFE
     Fish and Wildlife Population and Habitat Protection (06-1-003)

     The appropriations in this section are subject to the following conditions and limitations:
     (((2))) (1) It is the intent of the legislature that expenditures from the wildlife account--state appropriation shall only be made to the extent funds are available in the account and will not result in a reduction to other programs or activities.
     (2) The department of fish and wildlife, in coordination with the department of natural resources, shall pursue claims against the Columbia rural electric association and Asplundh for damage to state property caused by the school fire in the Wooten wildlife area. Any compensation received from such claims will be deposited in the state wildlife account.

Appropriation:
     General Fund--Federal . . . . . . . . . . . . $2,830,000
     General Fund--Private/Local . . . . . . . . . . . . $3,500,000
     State Building Construction Account--State . . . . . . . . . . . . $500,000
     Wildlife Account--State . . . . . . . . . . . . $600,000
          Subtotal Appropriation . . . . . . . . . . . . $7,430,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $34,920,000
          TOTAL . . . . . . . . . . . . $42,350,000

NEW SECTION.  Sec. 172   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF FISH AND WILDLIFE
     Land Acquisition Pass-Thru Grants (06-4-018)

Appropriation:
     Wildlife Account--Federal . . . . . . . . . . . . $3,300,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $3,300,000

NEW SECTION.  Sec. 173   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF FISH AND WILDLIFE
     Department of Natural Resources - Department of Fish and Wildlife Land Exchange - Shrub Steppe (06-2-851)

     The appropriation in this section is subject to the following conditions and limitations: Funding is provided solely to appraise the value of lands for exchange with the department of natural resources. Forest lands transferred to the department of natural resources under this section shall be actively managed by the department under a cooperative agreement with surrounding public and private landowners to implement landscape scale restoration and other management objectives.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $500,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $500,000

NEW SECTION.  Sec. 174   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF FISH AND WILDLIFE
     Alternative Mitigation Exchange Service (06-2-852)

     The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for contract services with the association of Washington cities and the Washington state association of counties for the purpose of developing and demonstrating an alternative mitigation exchange service in Vancouver and Clark county. The purposes of the exchange are to improve the environmental value of permit decision-making and to accomplish permit streamlining objectives.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $200,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $200,000

NEW SECTION.  Sec. 175   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF FISH AND WILDLIFE
     Estuary and Salmon Restoration in Puget Sound (06-2-001)

     The appropriation in this section is subject to the following conditions and limitations:
     (1) The appropriation is provided solely for nearshore estuary and shoreline projects supporting salmon recovery in Puget Sound.
     (2) Project selection and funding decisions shall be submitted for approval to the executive committee of the Puget Sound nearshore partnership between the department and the United States army corps of engineers.
     (3) Funded projects require a nonstate match or in-kind contributions. The match requirements must be approved by the executive committee identified in subsection (2) of this section.
     (4) Project selection and funding decisions must be coordinated with the salmon recovery funding board to ensure that project funding and matching requirements are maximized to the greatest extent possible.
     (5) The department shall not utilize any amount of this appropriation to support administration or overhead. Funding to support the administration of the funds and the implementation of selected projects must be obtained from the department's operating budget.
     (6) Eligible projects must be within Puget Sound and identified in a current salmon recovery plan.
     (7) All funds must be obligated to a specific project or projects no later than October 15, 2006.
     (8) The department shall submit a report to the legislature and the office of financial management by November 1, 2006. The report must describe the status of all projects authorized for funding under this appropriation, including project location, implementation timeline, performance measures, funding structure, matching funds, and expected results.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $2,500,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $5,000,000
          TOTAL . . . . . . . . . . . . $7,500,000

Sec. 176   2005 c 488 s 443 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF NATURAL RESOURCES
     Land Bank (06-2-015)

     The appropriation in this section is subject to the following conditions and limitations: The department shall prepare an inventory of acquisitions, sales, transfers, or exchanges of water rights within the past ten years. This inventory shall be submitted in a report to the appropriate committees of the legislature by December 1, 2006. The report shall also estimate the cost of a study to inventory all water rights that are connected to existing state lands.

Appropriation:
     Resources Management Cost Account--State . . . . . . . . . . . . (($5,000,000))
       $43,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $10,462,000
     Future Biennia (Projected Costs) . . . . . . . . . . . . $40,000,000
          TOTAL . . . . . . . . . . . . (($55,462,000))
       $93,462,000

Sec. 177   2005 c 488 s 451 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF NATURAL RESOURCES
     Small Timber Landowner (FREP) (06-2-019)

     The appropriation in this section is subject to the following conditions and limitations:
     (1) In addition to the annual project progress reporting requirement of RCW 43.88.160(3), the department shall file quarterly project progress reports with the office of financial management.
     (2) The department may not expend more than (($200,000)) $300,000 of the appropriation for administrative or staff costs.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $8,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $7,750,000
     Future Biennia (Projected Costs) . . . . . . . . . . . . $40,000,000
          TOTAL . . . . . . . . . . . . $55,750,000

NEW SECTION.  Sec. 178   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF NATURAL RESOURCES
     Federal HCP Land Acquisition Grants (06-2-950)

Appropriation:
     General Fund--Federal . . . . . . . . . . . . $6,720,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $6,720,000

Sec. 179   2005 c 488 s 453 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF NATURAL RESOURCES
     Statewide Aquatic Restoration Projects (06-2-008)

     The appropriations in this section are subject to the following conditions and limitations: $2,000,000 of the state toxics control account--state appropriation is provided solely for costs related to removal of creosote logs and pilings in Puget Sound.

Appropriation:
     Aquatic Lands Enhancement Account--State . . . . . . . . . . . . $300,000
     State Toxics Control Account--State . . . . . . . . . . . . $2,000,000
     State Building Construction Account--State . . . . . . . . . . . . $150,000
          Subtotal Appropriation . . . . . . . . . . . . (($450,000))
       $2,450,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $200,000
     Future Biennia (Projected Costs) . . . . . . . . . . . . $1,200,000
          TOTAL . . . . . . . . . . . . (($1,850,000))
       $3,850,000

NEW SECTION.  Sec. 180   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE DEPARTMENT OF NATURAL RESOURCES
     Old Growth Forest Inventory (06-2-855)

     The appropriation in this section is subject to the following conditions and limitations:
     (1) The appropriation in this section is provided solely to conduct an inventory of old growth forests located on state lands east of the crest of Cascade mountains. The inventory is intended to be a continuation of the inventory conducted pursuant to section 905, chapter 277, Laws of 2004, and must be completed in two phases.
     (2) In conducting the inventory required by this section, the department of natural resources shall reconvene a scientific panel with membership consistent with the structure created in section 905, chapter 277, Laws of 2004, and direct the panel to review the best available applicable scientific information. The panel shall also develop a definition for old-growth trees and stands located east of the crest of the Cascade mountains using attributes measured in department of natural resources inventory plots.
     (3) The first phase of the inventory required by this section shall be completed by July 1, 2007. In the first phase, the panel shall identify reference stands for old-growth ponderosa pine, dry mixed conifer species, and pine-oak plant associations.
     (4) The second phase of the inventory required by this section shall be completed by December 15, 2007. In the second phase, the department of natural resources shall use the definition provided by the scientific panel under subsection (2) of this section to produce an inventory of old growth forests located on state lands east of the crest of Cascade mountains. The inventory must include:
     (a) Maps that illustrate the distribution of forest stands containing old-growth ponderosa pine, dry mixed-conifer species, and pine-oak plant associations, including sites with residual old-growth ponderosa pine trees; and
     (b) Tables describing the number of acres of old-growth stands in each county, forest type, and department of natural resources' administrative unit.
     (5) The department of natural resources shall report the information required by this section to the appropriate committees of the legislature.
     (6) Until the completion of the inventory required by this section, the department of natural resources may not cut or remove any Douglas fir, ponderosa pine, or larch trees from state lands located east of the crest of the Cascade mountains if the tree is one hundred sixty years in age or older and has a diameter of twenty-eight inches or more when measured at breast height, unless removal of the tree is determined by the department of natural resources to be necessary to prevent an imminent physical or ecological hazard or otherwise satisfy a safety concern.

Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $100,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $100,000

Sec. 181   2005 c 488 s 460 (uncodified) is amended to read as follows:
FOR THE DEPARTMENT OF AGRICULTURE
     Hop Initiative (06-1-951)

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . (($500,000))
       $1,000,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($500,000))
       $1,000,000

Sec. 182   2005 c 488 s 601 (uncodified) is amended to read as follows:
FOR THE STATE BOARD OF EDUCATION
     Common School Construction Account Deposits

     The appropriations in this section are subject to the following conditions and limitations:
     (1) (($15,000,000)) $33,766,000 in fiscal year 2006 and $15,000,000 in fiscal year 2007 of the education savings account appropriation shall be deposited in the common school construction account.
     (2) $99,737,000 of the education construction account appropriation shall be deposited in the common school construction account.

Appropriation:
     Education Savings Account--State . . . . . . . . . . . . (($30,000,000))
       $48,766,000
     Education Construction Account--State . . . . . . . . . . . . $99,737,000
          Subtotal Appropriation . . . . . . . . . . . . (($129,737,000))
       $148,503,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($129,737,000))
       $148,503,000

Sec. 183   2005 c 488 s 605 (uncodified) is amended to read as follows:
FOR THE STATE BOARD OF EDUCATION
     School Construction Assistance Program (06-4-100)

     The appropriations in this section are subject to the following conditions and limitations:
     (1) For state assistance grants for purposes of calculating square foot eligibility, kindergarten student headcount shall not be reduced by fifty percent.
     (2)(a) $14,439,000 from this appropriation is provided solely for projects at skills centers that are included on the prioritized list of capital items and major capital project list submitted by the state board of education ((and)).
     (b)
$150,000 from this appropriation is provided solely for a comprehensive feasibility study for the development of a skills center in Skagit county.
     (c) $400,000 from this appropriation is provided solely for comprehensive feasibility studies for the development of skills centers in the following targeted areas: Moses Lake, northeast King county, Pierce county, and Seattle. Skills centers shall submit a budget plan to the state board of education and the appropriate fiscal committees of the legislature for proposed expenditures and the proposed expenditures shall conform to state board of education rules and procedures for reimbursement of capital items. The state board of education shall develop a plan to include skills center capital requests within the state construction assistance program.
     (3) $156,155,000 of this appropriation is provided solely to increase the area cost allowance by $12.14 per square foot for grades K-12 for fiscal year 2006, an additional $12.27 per square foot for grades K-12 for fiscal year 2007, the student square footage allocation in fiscal year 2007 in accordance with the first step in the state board of education six-year plan, and the amount of state assistance provided for modernization and new in-lieu projects to one hundred percent of the area cost allowance.
     (4) The appropriation in this section includes the amounts deposited in the common school construction account under section 601 of this act.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $130,200,000
     Common School Construction Account--State . . . . . . . . . . . . (($474,853,000))
       $511,116,000
          Subtotal Appropriation . . . . . . . . . . . . (($605,053,000))
       $641,316,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $2,832,159,000
          TOTAL . . . . . . . . . . . . (($3,437,212,000))
       $3,473,475,000

Sec. 184   2005 c 488 s 606 (uncodified) is amended to read as follows:
     FOR THE STATE BOARD OF EDUCATION
     Environmental Learning Centers (06-2-951)

     The appropriation in this section is subject to the following conditions and limitations:
     (1) $1,950,000 from this appropriation is provided solely for capital projects at the Chewelah peak learning center. The Chewelah peak learning center shall submit a budget plan to the state board of education and the appropriate fiscal committees of the legislature for proposed expenditures.
     (2) $400,000 of this appropriation is provided solely for capital projects at Camp Waskowitz learning center. Camp Waskowitz shall submit a budget plan to the state board of education and the appropriate fiscal committees of the legislature for proposed expenditures.
     (3) $500,000 of this appropriation is provided solely for capital projects at IslandWood education center on Bainbridge island. IslandWood shall submit a budget plan to the state board of education and the appropriate fiscal committees of the legislature for proposed expenditures.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $2,350,000
     Common School Construction Account--State . . . . . . . . . . . . $500,000
          Subtotal Appropriation . . . . . . . . . . . . $2,850,000


     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($2,350,000))
       $2,850,000

Sec. 185   2005 c 488 s 607 (uncodified) is amended to read as follows:
FOR THE STATE BOARD OF EDUCATION
     Apple Award Construction Achievement Grants (06-4-850)

     The appropriation in this section is subject to the following conditions and limitations: Grants of $25,000 are provided to public elementary schools whose students have shown the greatest combined average increase in the percentage of students meeting the fourth grade reading, mathematics, and writing standards on the Washington assessment of student learning from school year 2003-04 as compared to school year 2004-05 and school year 2004-05 as compared to school year 2005-06 ((and 2006-07)). $250,000 shall be available for awards in ((2005-06)) fiscal year 2006 and $250,000 in ((2006-07)) fiscal year 2007. The program shall be administered by the state board of education which shall determine categories for selection that provides geographic and school district size representation.
     The grants shall be used for capital construction purposes as determined by the students in the schools and approved by the district's school directors. The funds may be used exclusively for capital construction projects on school property or on other public property in the community, city, or county in which the school is located.

Appropriation:
     Education Construction Account--State . . . . . . . . . . . . $500,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $500,000

Sec. 186   2005 c 488 s 609 (uncodified) is amended to read as follows:
((FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION)) FOR THE STATE BOARD OF EDUCATION
     High Performance Buildings (06-4-852)

     The appropriation in this section is subject to the following conditions and limitations: Additional funding will be provided to school districts constructing public schools to recognized standards for high performance public buildings for a transition period of three years. The districts building high performance public schools will be granted funding per school project for capital-related costs associated with the design and construction of public K-12 schools that meet or exceed comprehensive design, construction, and operating standards for high performance and sustainable school buildings. No more than $250,000 will be allotted for each elementary school built to high performance standards, no more than $350,000 will be allotted for each middle school built to high performance standards, and no more than $500,000 will be allotted to each high school built to high performance standards. These levels may be modified, in a limited manner, if specific project conditions warrant and as determined by the office of the superintendent of public instruction. The state board of education and the office of the superintendent of public instruction shall not expend more than $195,000 of the appropriation for administrative costs.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $6,500,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $13,000,000
          TOTAL . . . . . . . . . . . . $19,500,000

Sec. 187   2005 c 488 s 610 (uncodified) is amended to read as follows:
FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION
     State School Construction Assistance Program Administration (06-2-001)

     The appropriation in this section is subject to the following conditions and limitations: $76,000 of the common school construction account--state appropriation is provided solely to implement chapter ... (Substitute House Bill No. 3098), Laws of 2006 (state board of education). If the bill is not enacted by June 30, 2006, the appropriation shall lapse.

Appropriation:
     Common School Construction Account--State . . . . . . . . . . . . (($2,279,004))
       $2,355,004

     Prior Biennia (Expenditures) . . . . . . . . . . . . $3,969,379
     Future Biennia (Projected Costs) . . . . . . . . . . . . $10,554,882
          TOTAL . . . . . . . . . . . . (($16,803,265))
       $16,879,265

Sec. 188   2005 c 488 s 612 (uncodified) is amended to read as follows:
FOR THE STATE SCHOOL FOR THE BLIND
     Campus Preservation (06-1-003)

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . (($700,000))
       $900,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $2,800,000
          TOTAL . . . . . . . . . . . . (($3,500,000))
       $3,700,000

Sec. 189   2005 c 488 s 613 (uncodified) is amended to read as follows:
FOR THE STATE SCHOOL FOR THE DEAF
     Omnibus Minor Works - Preservation (06-1-002)

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . (($200,000))
       $400,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $775,000
          TOTAL . . . . . . . . . . . . (($975,000))
       $1,175,000

Sec. 190   2005 c 488 s 632 (uncodified) is amended to read as follows:
FOR THE UNIVERSITY OF WASHINGTON
     Guggenheim Hall Renovation (06-1-006)

     The appropriations in this section ((is)) are subject to the following conditions and limitations: No money from the appropriation in this section may be expended on surge space.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . (($24,500,000))
       $19,750,000
     Education Construction Account--State . . . . . . . . . . . . $4,750,000
          Subtotal Appropriation . . . . . . . . . . . . $24,500,000


     Prior Biennia (Expenditures) . . . . . . . . . . . . $1,812,000
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $26,312,000

Sec. 191   2005 c 488 s 650 (uncodified) is amended to read as follows:
FOR WASHINGTON STATE UNIVERSITY
     WSU Pullman - Biotechnology/Life Sciences 2 (04-2-085)

Reappropriation:
     Washington State University Building Account--State . . . . . . . . . . . . $1,400,000
Appropriation:
     Gardner-Evans Higher Education Construction
          Account--State . . . . . . . . . . . . $10,000,000


     Prior Biennia (Expenditures) . . . . . . . . . . . . $3,250,000
     Future Biennia (Projected Costs) . . . . . . . . . . . . (($45,000,000))
       $56,000,000
          TOTAL . . . . . . . . . . . . (($49,650,000))
       $70,650,000

Sec. 192   2005 c 488 s 659 (uncodified) is amended to read as follows:
FOR WASHINGTON STATE UNIVERSITY
     Minor Works - Facility Preservation (06-1-001)

     The appropriation in this section is subject to the following conditions and limitations: $50,000 of the appropriation from the Washington State University building account--state is provided solely for preliminary design, engineering, permitting, and cost estimate evaluations to modernize and expand the existing dairy facilities in Pullman.

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $25,000,000
     Washington State University Building Account--State . . . . . . . . . . . . (($5,500,000))
       $10,500,000
          Subtotal Appropriation . . . . . . . . . . . . (($30,500,000))
       $35,500,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $120,000,000
          TOTAL . . . . . . . . . . . . (($150,500,000))
       $155,500,000

NEW SECTION.  Sec. 193   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR EASTERN WASHINGTON UNIVERSITY
     Martin Williamson Renovation (06-1-706)

Appropriation:
     Gardner-Evans Higher Education Construction
          Account--State . . . . . . . . . . . . $200,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $24,238,000
          TOTAL . . . . . . . . . . . . $24,438,000

NEW SECTION.  Sec. 194   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR EASTERN WASHINGTON UNIVERSITY
     Patterson Hall Remodel (06-2-002)

Appropriation:
     Gardner-Evans Higher Education Construction
          Account--State . . . . . . . . . . . . $200,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $26,078,000
          TOTAL . . . . . . . . . . . . $26,278,000

NEW SECTION.  Sec. 195   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR CENTRAL WASHINGTON UNIVERSITY
     Replace Chiller (06-1-025)

Appropriation:
     Gardner-Evans Higher Education Construction
          Account--State . . . . . . . . . . . . $1,880,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $1,880,000

Sec. 196   2005 c 488 s 696 (uncodified) is amended to read as follows:
FOR THE EVERGREEN STATE COLLEGE
     Seminar Building Phase II - Construction (02-2-004)

     The reappropriation in this section is subject to the following conditions and limitations: The reappropriation shall not be used for
vehicles, laptop computers, small printers, disposable items, or other items with a useful life of less than one year.

Reappropriation:
     The Evergreen State College Capital Projects
          Account--State . . . . . . . . . . . . $700,000
Appropriation:
     Education Construction Account--State . . . . . . . . . . . . $4,250,000


     Prior Biennia (Expenditures) . . . . . . . . . . . . $42,550,000
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . (($43,250,000))
       $47,500,000

Sec. 197   2005 c 488 s 714 (uncodified) is amended to read as follows:
FOR WESTERN WASHINGTON UNIVERSITY
     Campus Roadway Development (04-2-073)

     The reappropriation in this section is subject to the following conditions and limitations:
     (1) The purpose of the reappropriation is to complete a predesign of potential south campus roadway options and general circulation issues that avoids significant impacts on adjacent neighborhoods and conforms to the city of Bellingham traffic plans.
     (2) The predesign shall also investigate options to achieve higher rates of alternative modes of transportation among faculty, staff, and students, minimize surface parking, and make improvements for traffic circulation, including public transit. Safe movement of pedestrians and bicyclists shall be a priority.
     (3) Allotment for predesign is contingent upon the completion of a communication and public involvement plan for this project that is consistent with the significant projects section of the Western Washington University institutional master plan and adjacent neighborhood plans adopted by the city of Bellingham, the city of Bellingham Western Washington University neighborhood plan, and the neighborhood meeting requirements contained in Bellingham municipal code 20.40.060. The communication and public involvement plan shall seek to maximize public input through coordination of the planning effort with established neighborhood advisory groups and boards recognized by the city of Bellingham.

Reappropriation:
     Western Washington University Capital Projects
          Account--State . . . . . . . . . . . . (($38,826))
       $36,466

     Prior Biennia (Expenditures) . . . . . . . . . . . . $290,174
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $326,640

Sec. 198   2005 c 488 s 795 (uncodified) is amended to read as follows:
FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM
     Skagit Valley College: Science Building Replacement (04-1-209)

Reappropriation:
     State Building Construction Account--State . . . . . . . . . . . . $14,664
Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $2,693,000
     Gardner-Evans Higher Education Construction
          Account--State . . . . . . . . . . . . $325,000
          Subtotal Appropriation . . . . . . . . . . . . $3,018,000


     Prior Biennia (Expenditures) . . . . . . . . . . . . $285,336
     Future Biennia (Projected Costs) . . . . . . . . . . . . (($24,268,049))
       $26,693,049
          TOTAL . . . . . . . . . . . . (($27,261,049))
       $30,011,049

Sec. 199   2005 c 488 s 777 (uncodified) is amended to read as follows:
FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM
     Everett Community College: Undergraduate Education Center (04-2-692)

Appropriation:
     State Building Construction Account--State . . . . . . . . . . . . $7,363,700
     Gardner-Evans Higher Education Construction
          Account--State . . . . . . . . . . . . $3,844,000
          Subtotal Appropriation . . . . . . . . . . . . $11,207,700


     Prior Biennia (Expenditures) . . . . . . . . . . . . $126,000
     Future Biennia (Projected Costs) . . . . . . . . . . . . (($27,407,540))
       $38,103,591
          TOTAL . . . . . . . . . . . . (($34,897,240))
       $49,437,291

NEW SECTION.  Sec. 200   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM
     Seattle Central Community College: Maritime Academy Repairs (06-1-502)

Appropriation:
     Gardner-Evans Higher Education Construction
          Account--State . . . . . . . . . . . . $268,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $1,588,000
          TOTAL . . . . . . . . . . . . $1,856,000

NEW SECTION.  Sec. 201   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM
     Green River College: Water System Replacement (06-1-501)

Appropriation:
     Gardner-Evans Higher Education Construction
          Account--State . . . . . . . . . . . . $1,951,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $1,951,000

NEW SECTION.  Sec. 202   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM
     Highline Community College: Primary Power Branch Replacement (06-1-503)

Appropriation:
     Gardner-Evans Higher Education Construction
          Account--State . . . . . . . . . . . . $1,717,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $1,717,000

NEW SECTION.  Sec. 203   A new section is added to 2005 c 488 (uncodified) to read as follows:
FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM
     Skagit Valley College: Campus Fire Loop Replacement (06-1-504)

Appropriation:
     Gardner-Evans Higher Education Construction
          Account--State . . . . . . . . . . . . $1,634,000

     Prior Biennia (Expenditures) . . . . . . . . . . . . $0
     Future Biennia (Projected Costs) . . . . . . . . . . . . $0
          TOTAL . . . . . . . . . . . . $1,634,000

Sec. 204   2005 c 488 s 905 (uncodified) is amended to read as follows:
     (1) To ensure that minor works appropriations are carried out in accordance with legislative intent, funds appropriated in this act shall not be allotted until project lists are on file at the office of financial management ((and the office of financial management has formally approved the lists. Proposed revisions)), the house of representatives capital budget committee, and the senate ways and means committee. All projects must meet the criteria included in subsection (2)(a) of this section. Revisions to the lists must be filed with ((and approved by)) the office of financial management, the house of representatives capital budget committee, and the senate ways and means committee and include an explanation of variances from the prior list before funds may be expended on the revisions.
     (2)(a) Minor works projects are single line appropriations that shall include multiple projects valued between $25,000 and $1,000,000 each that are of a similar nature and can ((generally)) be completed within two years of the appropriation with the funding provided. These projects cannot be combined with or be a part of an overall project, that if combined over a continuous period of time, would exceed $1,000,000. Minor works categories include (i) health, safety, and code requirements; (ii) facility preservation; (iii) infrastructure preservation; and (iv) program improvement or expansion. Improvements for accessibility in compliance with the Americans with disabilities act may be included in any of the above minor works categories.
     (b) Minor works appropriations shall not be used for, among other things: Studies, except for technical or engineering reviews or designs that lead directly to and support a project on the same minor works list; planning; design outside the scope of work on a minor works list; moveable, temporary, and traditionally funded operating equipment not in compliance with the equipment criteria established by the office of financial management; software not dedicated to control of a specialized system; moving expenses; land or facility acquisition; or to supplement funding for projects with funding shortfalls unless expressly authorized elsewhere in this act. The office of financial management may make an exception to the limitations described in this subsection (2)(b) for exigent circumstances after notifying the legislative fiscal committees and waiting ten days for comments by the legislature regarding the proposed exception.
     (3) The ((office of financial management)) agency shall ((forward)) provide copies of these project lists and revised lists to the office of financial management, the house of representatives capital budget committee, and the senate ways and means committee. No expenditure may be incurred or obligation entered into for minor works appropriations until the office of financial management has approved the allotment of the funds to be expended. The office of financial management shall encourage state agencies to incorporate accessibility planning and improvements into the normal and customary capital program.
     (4) It is generally not intended to make future appropriations for capital expenditures or for maintenance and operating expenses for an acquisition project or a significant expansion project that is initiated through the minor works process and therefore does not receive a policy and fiscal analysis by the legislature. Minor works projects are intended to be one-time expenditures that do not require future state resources to complete.

NEW SECTION.  Sec. 205   A new section is added to 2005 c 488 (uncodified) to read as follows:
     Executive Order No. 05-05, archaeological and cultural resources, was issued effective November 10, 2005. Agencies and higher education institutions shall comply with the requirements set forth in this executive order.

Sec. 206   2005 c 488 s 909 (uncodified) is amended to read as follows:
     ACQUISITION OF PROPERTIES AND FACILITIES THROUGH FINANCIAL CONTRACTS. The following agencies may enter into financial contracts, paid from any funds of an agency, appropriated or nonappropriated, for the purposes indicated and in not more than the principal amounts indicated, plus financing expenses and required reserves pursuant to chapter 39.94 RCW. When securing properties under this section, agencies shall use the most economical financial contract option available, including long-term leases, lease-purchase agreements, lease-development with option to purchase agreements or financial contracts using certificates of participation. Expenditures made by an agency for one of the indicated purposes before the issue date of the authorized financial contract and any certificates of participation therein are intended to be reimbursed from proceeds of the financial contract and any certificates of participation therein to the extent provided in the agency's financing plan approved by the state finance committee.
     State agencies may enter into agreements with the department of general administration and the state treasurer's office to develop requests to the legislature for acquisition of properties and facilities through financial contracts. The agreements may include charges for services rendered.
     Those noninstructional facilities of higher education institutions authorized in this section to enter into financial contracts are not eligible for state funded maintenance and operations. Instructional space that is available for regularly scheduled classes for academic transfer, basic skills, and workforce training programs may be eligible for state funded maintenance and operations.
     (1) Department of general administration:
     (a) Enter into a financing contract for up to $12,000,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct the fifth and final phase of the roof membrane replacement at the east plaza parking structure as well as safety improvements to the parking garage below the plaza.
     (b) Enter into a financing contract for up to $6,000,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW for the fourth phase of the office building-2 rehabilitation that will renew failing building systems, correct code deficiencies, and improve access.
     (c) Enter into a financing contract for up to $13,000,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW for the rehabilitation of the Cherberg building.
     (2) Liquor control board: Enter into a financing contract for up to $17,000,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct an extension to the liquor control board's distribution center to meet liquor sales growth through 2018.
     (3) Department of corrections:
     (a) Enter into a financing contract for up to $400,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct a waste transfer station and purchase a garbage truck at the McNeil Island corrections center.
     (b) Enter into a financing contract for up to $4,588,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct a transportation services warehouse and offices for correctional industries.
     (c) Enter into a financing contract for up to $4,536,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct additions to the food factory and warehouses at the Airway Heights corrections center for correctional industries.
     (4) Parks and recreation commission: Enter into a financing contract in an amount not to exceed $4,800,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to develop Cama Beach state park.
     (5) Community and technical colleges:
     (a) ((Enter into a financing contract on behalf of Bellevue Community College for up to $20,000,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to purchase the North Center building.
     (b)
)) Enter into a financing contract on behalf of Clark College for up to $9,100,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct a ((parking structure)) building for a training center.
     (((c))) (b) Enter into a financing contract on behalf of Clover Park Technical College for up to $14,000,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct a student center.
     (((d))) (c) Enter into a financing contract on behalf of Columbia Basin College for up to $1,500,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to renovate the Hawk Union building.
     (d) Enter into a financing contract on behalf of Edmonds Community College for up to $8,500,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct a bookstore and student center.
     (e) Enter into a financing contract on behalf of Edmonds Community College for up to $4,000,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct a black box theater as a part of the Instructional Lab building.
     (f) Enter into a financing contract on behalf of Green River Community College for up to $7,000,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to purchase Kent Station higher education center.
     (g) Enter into a financing contract on behalf of Olympic College for up to $3,600,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct an addition to the student center bookstore.
     (h) Enter into a financing contract on behalf of Shoreline Community College for up to $15,000,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct a student union building.
     (i) Enter into a financing contract on behalf of Skagit Valley Community College for up to $3,200,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to renovate existing space into a new student center.
     (j) Enter into a financing contract on behalf of Walla Walla Community College for up to $2,175,100 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to purchase land, make site improvements, and construct a building for ((the enology program)) professional-technical instruction.
     (k) Enter into a financing contract on behalf of Walla Walla Community College for up to $640,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct an addition to the health sciences building at the Clarkston center.
     (l) Enter into a financing contract on behalf of Seattle Central Community College for up to $3,000,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct a math and science building.
     (m) Enter into a financing contract on behalf of Pierce College/Puyallup for up to $8,000,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct a student gym and fitness center.
     (n) Enter into a financing contract on behalf of Pierce College/Ft. Steilacoom for up to $5,000,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct an addition to the college health and wellness center.
     (o) Enter into a financing contract on behalf of Columbia Basin College for up to $3,000,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct the Richland health sciences center.
     (p) The projects in (((a),)) (f), (((k),)) (j), (l), (m), and (n) of this subsection are reauthorizations of projects originally authorized in the 2003-2005 biennium. If the college enters into a financing contract before the effective date of this section, then the appropriate reauthorization contained in this section is null and void.
     (6) Washington State University: Enter into a financing contract for up to $11,650,000 plus financing expenses and required reserves pursuant to chapter 39.94 RCW to construct a bioproducts facility in the Tri-Cities.

Sec. 207   RCW 43.---.--- (section 8, chapter ---, Laws of 2006, (E3SHB No. 2939)) is amended to read as follows:
     The energy freedom account is created in the state treasury. All receipts from appropriations made to the account, proceeds from other lawful sources, and loan payments of principal and interest derived from loans made under this chapter must be deposited into the account. Moneys in the account may be spent only after appropriation. Expenditures from the account may be used only for loans and grants to political subdivisions for renewable energy and biofuel development projects and activities authorized under this chapter or otherwise authorized by the legislature.

NEW SECTION.  Sec. 208   A new section is added to 2005 c 488 (uncodified) to read as follows:
     OFFICE OF FINANCIAL MANAGEMENT. The legislature finds that the January 23, 2006, report on 63-20 capital projects financing submitted by the state treasurer raised significant issues that could benefit from additional exploration and analysis. The legislature further finds that financing costs are only one important dimension to consider when analyzing and comparing the use of conventional bonds with other capital project financing mechanisms in the development of major public facilities. Other factors that must be considered include total project and life-cycle costs, long-term costs of capital, scheduling, generally accepted accounting principles, transfer of risk, project management, project complexity, public works contracting procedures, and applicability of private sector strategies or practices in the development and ongoing maintenance of public facilities.
     The office of financial management and the department of general administration, in consultation with legislative staff from the appropriate policy and fiscal committees of the legislature shall:
     (1) Research models and best practices used by other governments and private industry to provide major facility and infrastructure information for budgeting purposes, including the updated joint legislative audit and review committee life-cycle cost model in section 102 of this act. The analysis must include total cost of capital and long-term forecasting information for facility preservation, major facility or system replacement, and new capacity to result in more effective investment decisions for major public facilities and infrastructure.
     (2) Develop recommendations that incorporate best practices in the state's capital budgeting process and public works contracting procedures, including lessons learned from 63-20 financing projects entered into by state agencies or local governments.
     (3) Develop recommendations for appropriate uses of alternative capital project financing instruments and a corresponding decision making process.
     (4) Develop a strategy to manage risk and reduce the potential for claims and litigation associated with state construction projects. This strategy must include the enumeration of best practices for the management of project risk and conflicts, in order to minimize future expenses related to construction claims.
     (5) Coordinate with the capital projects advisory review board created in chapter 377, Laws of 2005 to evaluate public capital project construction processes and policies related to alternative public works delivery methods.
     (6) Submit report findings and recommendations to the appropriate fiscal committees of the legislature by September 1, 2007.

Sec. 209   RCW 79.17.010 and 2003 1st sp.s. c 25 s 939 and 2003 c 334 s 452 are each reenacted and amended to read as follows:
     (1) The department, with the approval of the board, may exchange any state land and any timber thereon for any land of equal value in order to:
     (a) Facilitate the marketing of forest products of state lands;
     (b) Consolidate and block-up state lands;
     (c) Acquire lands having commercial recreational leasing potential;
     (d) Acquire county-owned lands;
     (e) Acquire urban property which has greater income potential or which could be more efficiently managed by the department in exchange for state urban lands as defined in RCW 79.19.100; or
     (f) Acquire any other lands when such exchange is determined by the board to be in the best interest of the trust for which the state land is held.
     (2) Land exchanged under this section shall not be used to reduce the publicly owned forest land base.
     (3) The board shall determine that each land exchange is in the best interest of the trust for which the land is held prior to authorizing the land exchange.
     (4) During the biennium ending June 30, ((2005)) 2007, the department, with approval of the board, may exchange any state land and any timber thereon for any land and proceeds of equal value. Proceeds may be in the form of cash or services in order to achieve the purposes established in this section. Any cash received as part of an exchange transaction shall be deposited in the resource management cost account to pay for administrative expenses incurred in carrying out an exchange transaction. The amount of proceeds received from the exchange partner may not exceed five percent of the total value of the exchange. The receipt of proceeds shall not change the character of the transaction from an exchange to a sale.

NEW SECTION.  Sec. 210   A new section is added to 2005 c 488 (uncodified) to read as follows:
     Eastern Washington University is authorized to sell its Spokane center. Proceeds from the sale must be deposited into the higher education construction account. Proceeds may be used to acquire or design a facility on or adjacent to the Riverpoint higher education campus for the university's Spokane-based program offerings. Eastern Washington University must report to the office of financial management and the appropriate fiscal committees of the legislature upon sale of the center as well as expenditure of the proceeds.

Sec. 211   RCW 43.99N.060 and 2000 c 137 s 1 are each amended to read as follows:
     (1) The stadium and exhibition center account is created in the custody of the state treasurer. All receipts from the taxes imposed under RCW 82.14.0494 and distributions under RCW 67.70.240(5) shall be deposited into the account. Only the director of the office of financial management or the director's designee may authorize expenditures from the account. The account is subject to allotment procedures under chapter 43.88 RCW. An appropriation is not required for expenditures from this account.
     (2) Until bonds are issued under RCW 43.99N.020, up to five million dollars per year beginning January 1, 1999, shall be used for the purposes of subsection (3)(b) of this section, all remaining moneys in the account shall be transferred to the public stadium authority, created under RCW 36.102.020, to be used for public stadium authority operations and development of the stadium and exhibition center.
     (3) After bonds are issued under RCW 43.99N.020, all moneys in the stadium and exhibition center account shall be used exclusively for the following purposes in the following priority:
     (a) On or before June 30th of each year, the office of financial management shall accumulate in the stadium and exhibition center account an amount at least equal to the amount required in the next succeeding twelve months for the payment of principal of and interest on the bonds issued under RCW 43.99N.020;
     (b) An additional reserve amount not in excess of the expected average annual principal and interest requirements of bonds issued under RCW 43.99N.020 shall be accumulated and maintained in the account, subject to withdrawal by the state treasurer at any time if necessary to meet the requirements of (a) of this subsection, and, following any withdrawal, reaccumulated from the first tax revenues and other amounts deposited in the account after meeting the requirements of (a) of this subsection; and
     (c) The balance, if any, shall be transferred to the youth athletic facility account under subsection (4) of this section.
     Any revenues derived from the taxes authorized by RCW 36.38.010(5) and 36.38.040 or other amounts that if used as provided under (a) and (b) of this subsection would cause the loss of any tax exemption under federal law for interest on bonds issued under RCW 43.99N.020 shall be deposited in and used exclusively for the purposes of the youth athletic facility account and shall not be used, directly or indirectly, as a source of payment of principal of or interest on bonds issued under RCW 43.99N.020, or to replace or reimburse other funds used for that purpose.
     (4) Any moneys in the stadium and exhibition center account not required or permitted to be used for the purposes described in subsection (3)(a) and (b) of this section shall be deposited in the youth athletic facility account hereby created in the state treasury. Expenditures from the account may be used only for purposes of grants or loans to cities, counties, and qualified nonprofit organizations for community outdoor athletic facilities. For the 2005-2007 biennium, moneys in the account may also be used for the recreation level of service study for local and regional active recreation facilities identified in section 168 of this act. Only the director of the interagency committee for outdoor recreation or the director's designee may authorize expenditures from the account. The account is subject to allotment procedures under chapter 43.88 RCW, but an appropriation is not required for expenditures. The athletic facility grants or loans may be used for acquiring, developing, equipping, maintaining, and improving community outdoor athletic facilities. Funds shall be divided equally between the development of new community outdoor athletic facilities, the improvement of existing community outdoor athletic facilities, and the maintenance of existing community outdoor athletic facilities. Cities, counties, and qualified nonprofit organizations must submit proposals for grants or loans from the account. To the extent that funds are available, cities, counties, and qualified nonprofit organizations must meet eligibility criteria as established by the director of the interagency committee for outdoor recreation. The grants and loans shall be awarded on a competitive application process and the amount of the grant or loan shall be in proportion to the population of the city or county for where the community outdoor athletic facility is located. Grants or loans awarded in any one year need not be distributed in that year. The director of the interagency committee for outdoor recreation may expend up to one and one-half percent of the moneys deposited in the account created in this subsection for administrative purposes.

Sec. 212   2005 c 488 s 927 (uncodified) is amended to read as follows:
FOR THE STATE TREASURER--TRANSFERS
     Local Toxics Control Account: For transfer
to the state toxics control account . . . . . . . . . . . . $13,900,000
     State Drought Preparedness Account: For
transfer to the charitable, education, penal
and reformatory institutions account . . . . . . . . . . . . $970,000

NEW SECTION.  Sec. 213   Part headings in this act are not any part of the law.

NEW SECTION.  Sec. 214   If any provision of this act or its application to any person or circumstance is held invalid, the remainder of the act or the application of the provision to other persons or circumstances is not affected.

NEW SECTION.  Sec. 215   This act is necessary for the immediate preservation of the public peace, health, or safety, or support of the state government and its existing public institutions, and takes effect immediately.


     INDEX       PAGE #


CENTRAL WASHINGTON UNIVERSITY . . . . . . . . . . . . 63
CRIMINAL JUSTICE TRAINING COMMISSION . . . . . . . . . . . . 19
DEPARTMENT OF AGRICULTURE . . . . . . . . . . . . 55
DEPARTMENT OF COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT . . . . . . . . . . . . 3
DEPARTMENT OF CORRECTIONS . . . . . . . . . . . . 22
DEPARTMENT OF ECOLOGY . . . . . . . . . . . . 25
DEPARTMENT OF FISH AND WILDLIFE . . . . . . . . . . . . 49
DEPARTMENT OF GENERAL ADMINISTRATION . . . . . . . . . . . . 15
DEPARTMENT OF NATURAL RESOURCES . . . . . . . . . . . . 52
DEPARTMENT OF SOCIAL AND HEALTH SERVICES . . . . . . . . . . . . 20
DEPARTMENT OF VETERANS AFFAIRS . . . . . . . . . . . . 21
EASTERN WASHINGTON UNIVERSITY . . . . . . . . . . . . 63
EMPLOYMENT SECURITY DEPARTMENT . . . . . . . . . . . . 24
INTERAGENCY COMMITTEE FOR OUTDOOR RECREATION . . . . . . . . . . . . 39
JOINT LEGISLATIVE AUDIT AND REVIEW COMMITTEE . . . . . . . . . . . . 2
OFFICE OF FINANCIAL MANAGEMENT . . . . . . . . . . . . 1, 73
STATE BOARD OF EDUCATION . . . . . . . . . . . . 56, 59
STATE PARKS AND RECREATION COMMISSION . . . . . . . . . . . . 35
STATE SCHOOL FOR THE BLIND . . . . . . . . . . . . 60
THE EVERGREEN STATE COLLEGE . . . . . . . . . . . . 64
UNIVERSITY OF WASHINGTON . . . . . . . . . . . . 61
WESTERN WASHINGTON UNIVERSITY . . . . . . . . . . . . 64

ESSB 6384  - H COMM AMD
     By Committee on Capital Budget

ADOPTED AS AMENDED 02/28/2006

     On page 1, line 2 of the title, after "improvements;" strike the remainder of the title and insert "amending RCW 43.99N.060; amending RCW 43.---.--- (section 8, chapter ---, Laws of 2006, (E3SHB No. 2939)); amending 2006 c --- s 2 (E2SHB No. 2393) (uncodified); amending 2005 c 488 ss 109, 112, 125, 131, 138, 142, 143, 152, 156, 201, 206, 238, 252, 255, 264, 287, 323, 324, 325, 327, 329, 340, 341, 342, 346, 360, 365, 368, 369, 370, 372, 376, 382, 385, 386, 387, 390, 391, 392, 398, 401, 402, 395, 414, 425, 427, 443, 451, 453, 460, 601, 605, 606, 607, 609, 610, 612, 613, 632, 650, 659, 696, 714, 795, 777, 905, 909, and 927 (uncodified); reenacting and amending RCW 79.17.010; adding new sections to 2005 c 488 (uncodified); creating new sections; and declaring an emergency."

--- END ---