HOUSE BILL REPORT
ESHB 1020
As Passed Legislature
Title: An act relating to siting electrical transmission under the energy facility site evaluation council.
Brief Description: Regarding electrical transmission.
Sponsors: By House Committee on Technology, Energy & Communications (originally sponsored by Representatives Morris and B. Sullivan).
Brief History:
Technology, Energy & Communications: 1/14/05, 1/27/05 [DPS].
Floor Activity:
Passed House: 2/28/05, 93-2.
Senate Amended.
Passed Senate: 4/15/05, 46-0.
Floor Activity:
Passed House: 1/27/06, 98-0.
Senate Amended.
Passed Senate: 2/28/06, 48-0.
House Concurred.
Passed House: 3/4/06, 96-0.
Passed Legislature.
Brief Summary of Engrossed Substitute Bill |
|
|
|
HOUSE COMMITTEE ON TECHNOLOGY, ENERGY & COMMUNICATIONS
Majority Report: The substitute bill be substituted therefor and the substitute bill do pass. Signed by 11 members: Representatives Morris, Chair; Kilmer, Vice Chair; Crouse, Ranking Minority Member; Ericks, Haler, Hudgins, Nixon, P. Sullivan, Sump, Takko and Wallace.
Staff: Scott Richards (786-7156).
Background:
National Energy Policy Act of 2005
The National Energy Policy Act of 2005 (Act) was signed into law August 2005. Section
1221 of the Act authorizes the U.S. Secretary of Energy (Secretary) to conduct a study within
one year of passage, and triennially thereafter, of electric transmission congestion. The
Secretary will issue a report based on the study, which may designate any geographic area
experiencing electric energy transmission capacity constraints or congestion that adversely
affects consumers as a national interest energy electric transmission corridor.
In determining whether to designate a particular area as a national interest electric
transmission corridor, the Secretary may consider the following:
whether the economic vitality and development of the corridor, or the end markets served by
the corridor, may be constrained by lack of adequate or reasonably priced electricity;whether
economic growth in the corridor, or the end markets served by the corridor, may be
jeopardized by reliance on limited sources of energy; and a diversification of supply is
warranted;whether the energy independence of the United States would be served by the
designation;whether the designation would be in the interest of national energy policy; and
whether the designation would enhance national defense and homeland security.
FERC's Backstop Authority
The Act authorizes the Federal Energy Regulatory Commission to issue permits for
construction or modification of electric transmission in a national interest transmission
corridor if:
EFSEC Licensing
The Energy Facility Site Evaluation Council (EFSEC) was created in 1970 to provide
one-stop licensing for large energy projects. The EFSEC's membership includes mandatory
representation from five state agencies and discretionary representation from four additional
state agencies. The EFSEC's membership may include representatives from the particular
city, county, or port district where potential projects may be located.
The EFSEC's jurisdiction includes the siting of large intrastate natural gas and petroleum
pipelines, electric power plants above 350 megawatts, new oil refineries, large expansions of
existing facilities, and underground natural gas storage fields. For electric power plants, the
EFSEC's jurisdiction extends to those associated facilities that include new transmission lines
that operate in excess of 200 kilovolts and are necessary to connect the plant to the Northwest
power grid. Developers of energy facilities that exclusively use alternative energy resources,
regardless of the size of the facility's generation capacity, may choose to use the EFSEC
process to site the facility.
The EFSEC siting process generally involves six steps: (1) a potential site study followed by
an application; (2) State Environmental Policy Act review; (3) review for consistency with
applicable local land use laws and plans; (4) a formal adjudication on all issues related to the
project; (5) certain air and water pollution discharge permitting reviews as delegated by the
U.S. Environmental Protection Agency; and (6) a recommendation to the Governor who then
decides whether to accept, reject, or remand the application. A certification agreement
approved by the Governor preempts any other state or local regulation concerning the
location, construction, and operational conditions of an energy facility. Under the EFSEC
process, the applicant is required to pay the costs of the EFSEC in processing an application.
County and City Growth Management
Under the Growth Management Act, certain counties and cities must develop comprehensive
land use plans outlining the coordinated land use policy of the county or city. The
comprehensive land use planning process includes adopting development regulations, such as
zoning ordinances, critical areas ordinances, and binding site plan ordinances.
Summary of Engrossed Substitute Bill:
A person or entity developing new transmission lines or expanding or reconstructing existing
transmission lines that operate in excess of 115 kilovolts may use the EFSEC process to
obtain siting approval for the transmission lines. Facilities that generate electricity using
alternative energy resources as the source of power may use the EFSEC facility siting
process.
The definition of "transmission facility" is amended to include electrical transmission
facilities in excess of 115,000 volts in national interest electric transmission corridors as
designated by the United States Secretary of the Department of Energy or the Federal Energy
Regulatory Commission in accordance with Section 1221 of the national Energy Policy Act
of 2005.
The Legislature finds that the siting of electrical transmission facilities at or under 115,000
volts has historically been regulated by local government.
The EFSEC is designated as the state authority for purposes of siting transmission facilities
under the national Energy Policy Act of 2005. The EFSEC's authority regarding transmission
facilities is limited to those transmission facilities that are subject to Section 1221 of the
national Energy Policy Act of 2005. When EFSEC develops recommendations for any
application for the construction or modification of transmission facilities, the fuel source of
the electricity carried by the transmission facilities shall not be considered. The EFSEC must
convey to the United States Secretary of Energy the views of interested parties in the state
concerning the appropriate limits on federal authority over transmission siting in the state.
When siting transmission facilities are subject to Section 1221, EFSEC may consider
interstate benefits of the facilities in the state.
A person or entity apply for energy facility site certification must pay reasonable costs
incurred by members of the EFSEC in processing the application which may include but are
not limited to council member's wages and employee benefits.
The public hearing process for site certification has been updated to include city land use and
zoning ordinances in accordance with the Growth Management Act.
Appropriation: None.
Fiscal Note: Not requested.
Effective Date: The bill takes effect 90 days after adjournment of session in which bill is passed.
Testimony For: (In support of original bill) The issue of availability of new transmission
and siting of that transmission is a growing issue. The availability of new transmission is a
problem in the Western United States and in Washington. The need for new transmission is
growing and transmission is integral to delivering generation where it is needed. In addition,
those that are building most of the transmission now have eminent domain authority. In the
future, there will be more merchant development of transmission that is privately financed
and will not have eminent domain authority. The bill will facilitate siting of merchant built
lines. Giving the EFSEC this jurisdiction is a tool for entities working to accommodate
growth in the state.
The intent of the bill is also to give local jurisdictions time and the option to site new
transmission corridors within their jurisdiction and, if the local jurisdictions do not do so by
July 1, 2007, then the EFSEC would have jurisdiction.
There is concern regarding clarifying when and where the EFSEC has jurisdiction and the
relationship of that jurisdiction to the requirements of the Growth Management Act.
Testimony Against: (With concerns to original bill) There are concerns about the impact this might have on local jurisdictions that might site transmission. First, the bill requires cities and counties to amend their comprehensive plans and not all cities and counties are required to do a comprehensive land use plan. In addition, there is cost associated with amendment comprehensive plans. There is also concern that it is an expensive and lengthy process for counties and cities to go through the siting process on their own. The bill would force cities and counties to either accept a developer's application or to go through the expensive and lengthy process on their own.
Persons Testifying: (In support of original bill) Representative Morris, prime sponsor.
(With concerns to original bill) Kathleen Collins, PacifiCorp; Scott Merriman, Association of
Counties; Victoria Lincoln, Association of Washington Cities; and Mike Tracey, Puget
Sound Energy.