FINAL BILL REPORT
ESHB 1830
C 377 L 05
Synopsis as Enacted
Brief Description: Establishing the capital projects review board.
Sponsors: By House Committee on State Government Operations & Accountability (originally sponsored by Representatives Hunt, Jarrett, Morrell, McDonald, Pettigrew, Hasegawa, Eickmeyer, Clibborn, Simpson and Ericks).
House Committee on State Government Operations & Accountability
House Committee on Capital Budget
Senate Committee on Government Operations & Elections
Senate Committee on Ways & Means
Background:
Most public works projects are completed using the design-bid-build procedure, in which the
architectural design phase of a project is separate from the construction phase. Under this
process, an architectural firm is retained to design the facility and prepare construction
documents. After the detailed design and construction documents are complete, the
construction phase of the project is put out for competitive bid. A construction contract is
then awarded to the lowest responsible bidder.
Alternative procedures for public works projects were first used on a very limited basis and
then adopted in statute in 1994 for certain pilot projects. These alternative procedures
included a design-build process and a general contractor/construction manager (GC/CM)
process could be used on projects costing in excess of $10 million.
The design-build procedure is a multi-step competitive process to award a contract to a single
firm that agrees to both design and build a public facility that meets specific criteria. The
contract is awarded following a public request of proposals for design-build services.
Following extensive evaluation of the proposals, the contract is awarded to the firm that
submits the best and final proposal with the lowest price.
The GC/CM method employs the services of a project management firm that bears significant
responsibility and risk in the contracting process. The government agency contracts with an
architectural and engineering firm to design the facility and, early in the project, also
contracts with a GC/CM firm to assist in the design of the facility, manage the construction of
the facility, act as the general contractor, and guarantee that the facility will be built within
budget. When the plans and specifications for a project phase are complete, the GC/CM firm
subcontracts with construction firms to construct that phase. Initial selection of GC/CM
finalists is based on the qualifications and experience of the firm.
Under the 1994 legislation, a temporary independent oversight committee was created to
review the utilization of design-build and GC/CM. The committee was composed of
representatives from state and local agencies, the construction and design industries, labor
organizations, and four members of the Legislature, one from each caucus. The committee
report, issued on January 21, 1997, recommended that the authorization to use the alternative
methods on a pilot basis be extended to June 30, 2001, and that certain modifications be
made to the alternative contracting procedures to increase the efficiency and effectiveness of
the methods. Those recommendations were adopted in 1997 and, also that year, the
committee was eliminated. In 2001, the authorization to use alternative public works
procedures again was extended to June 30, 2007.
The 2003-05 Capital Budget directed the Joint Legislative Audit and Review Committee
(JLARC) to study the use of GC/CM contracting procedures in major public works projects.
The study consists of a review of past and current projects constructed using GC/CM
contracting procedures to determine the feasibility of assessing the public benefits and costs.
The final report will be presented in June 2005.
Summary:
The Capital Projects Advisory Review Board (Review Board) is established to evaluate
public capital projects construction processes and to advise the Legislature on policies related
to alternative public works delivery methods.
Review Board membership includes the following members appointed by the governor: one
representative from construction general contracting; one representative from the design
industries; two representatives from construction specialty subcontracting; one representative
from a construction trades labor organization; one representative from the Office of Minority
and Women's Business Enterprises; one representative from a higher education institution;
one representative from the Department of General Administration; and one representative of
a domestic insurer authorized to write surety bonds for contractors in Washington. All
appointed members must be actively engaged in or authorized to use alternative public works
contracting procedures.
Two at-large members will represent local public owners and will serve terms on a rotating
basis. These members are appointed by the Association of Washington Cities, the
Washington State Association of Counties, and the Washington Public Ports Association. A
member of the Public Hospital District Project Review Board and a member of the School
District Project Review Board also will be included on the Review Board as non-voting
members.
Legislative members of the Review Board include two members of the House of
Representatives, one from each major caucus appointed by the Speaker of the House of
Representatives, and two members from the Senate, one from each major caucus appointed
by the President of the Senate. Legislative members shall be non-voting.
The Review Board will convene as soon as practical after July 1, 2005, and will meet as often
as necessary. The Department of General Administration must provide staff to support the
Review Board.
The Review Board must develop and recommend to the Legislature: (1) criteria that may be
used to determine effective and feasible use of alternative contracting procedures; (2)
qualification standards for general contractors bidding on alternative public works projects;
and (3) policies to further enhance the quality, efficiency, and accountability of capital
construction projects through the use of traditional and alternative delivery methods and
recommendations on expansion, continuation, elimination, or modification of alternative
public works contracting methods. The Review Board must also evaluate future use of other
alternative contracting procedures, including competitive negotiation contracts.
One demonstration project using the GC/CM or design-build alternative public works
contracting procedures is authorized for any city that is located in a county authorized to use
alternative public works or in a county that is a member of the Puget Sound Regional
Council, has revenues that exceed $60 million, and has a population greater than 25,000 but
less than 45,000. The demonstration project must be valued over $10 million and contracts
for the demonstration project must be entered into before March 1, 2006.
Votes on Final Passage:
House 97 0
Senate 47 0 (Senate amended)
House 98 0 (House concurred)
Effective: July 24, 2005