6932-S AMH ROLF BERN 057
SSB 6932 - H AMD 1398
By Representative Rolfes
ADOPTED 3/05/2008
On page 4, after line 29, insert the following:
"NEW SECTION. Sec.6. RCW 47.60.385 and 2007 c 512 s 14 are each amended to read as follows:
(1) Terminal improvement project funding requests must adhere to the capital plan.
(2) Requests for terminal improvement design and construction funding must be submitted with a predesign study that:
(a) Includes all elements required by the office of financial management;
(b) Separately identifies basic terminal elements essential for operation and their costs;
(c) Separately identifies additional elements to provide ancillary revenue and customer comfort and their costs;
(d) Includes construction phasing options that are consistent with forecasted ridership increases;
(e) Separately identifies additional elements requested by local governments and the cost and proposed funding source of those elements;
(f) Separately identifies multimodal elements and the cost and proposed funding source of those elements; and
(g) Identifies all contingency amounts.
(h) When planning for new vessel acquisitions, the department must evaluate the long-term vessel operating costs related to fuel efficiency and staffing."
Correct the title.
EFFECT: Requires Washington State Ferries to evaluate long-term operating costs related to fuel efficiency and staffing when planning for new vessel acquisitions