Washington State House of Representatives Office of Program Research |
BILL ANALYSIS |
Technology, Energy & Communications Committee | |
HB 1061
This analysis was prepared by non-partisan legislative staff for the use of legislative members in
their deliberations. This analysis is not a part of the legislation nor does it constitute a
statement of legislative intent.
Brief Description: Changing provisions concerning the siting of energy facilities.
Sponsors: Representatives Hudgins, Linville and Morris.
Brief Summary of Bill |
|
|
Hearing Date: 1/10/07
Staff: Scott Richards (786-7156).
Background:
The Energy Facility Site Evaluation Council (EFSEC) was created in 1970 to provide one-stop
licensing for large energy projects. The EFSEC's membership includes mandatory representation
from five state agencies and discretionary representation from four additional state agencies. The
EFSEC's membership may include representatives from the particular city, county, or port district
where potential projects may be located.
The EFSEC's jurisdiction includes the siting of large intrastate natural gas and petroleum
pipelines, electric power plants above 350 megawatts, new oil refineries, large expansions of
existing facilities, and underground natural gas storage fields. For electric power plants, the
EFSEC's jurisdiction extends to those associated facilities that include new transmission lines
that operate in excess of 115 kilovolts and are necessary to connect the plant to the Northwest
power grid. The EFSEC's jurisdiction includes the siting of electrical transmission facilities in
excess of 115 kilovolts in National Interest Electric Transmission Corridors as designated by the
United States Department of Energy or the Federal Energy Regulatory Commission under
Section 1221 of the National Energy Policy Act. The EFSEC's may site energy facilities of any
size that exclusively use alternative energy resources, if the project applicant chooses to use the
EFSEC review and certification process.
EFSEC Site Evaluation Process
The EFSEC siting process generally involves six steps: (1) a potential site study followed by an
application; (2) State Environmental Policy Act review; (3) review for consistency with
applicable local land use laws and plans; (4) a formal adjudication on all issues related to the
project; (5) certain air and water pollution discharge permitting reviews as delegated by the U.S.
Environmental Protection Agency; and (6) a recommendation to the Governor who then decides
whether to accept, reject, or remand the application. A certification agreement approved by the
Governor preempts any other state or local regulation concerning the location, construction, and
operational conditions of an energy facility.
Under the EFSEC process, the applicant is required to pay the costs of the council in processing
under an application.
Summary of Bill:
EFSEC Jurisdiction
The EFSEC's jurisdiction is extended to site any thermal power plant with generating capacity
and its associated facilities.
"Energy generation area" means an area within which the effects of two or more generating
plants may accumulate so that the generating plants have effects of magnitude similar to a single
generating plant.
Developers of energy facilities may apply to EFSEC to certify two or more project under one
application, regardless of the size of the facility's generation capacity.
Appropriation: None.
Fiscal Note: Requested on January 9, 2007.
Effective Date: The bill takes effect 90 days after adjournment of session in which bill is passed.