Washington State
House of Representatives
Office of Program Research
BILL
ANALYSIS

State Government & Tribal Affairs Committee

HB 1506


This analysis was prepared by non-partisan legislative staff for the use of legislative members in their deliberations. This analysis is not a part of the legislation nor does it constitute a statement of legislative intent.

Brief Description: Changing alternative works provisions.

Sponsors: Representatives Haigh, Armstrong, Hunt and Ormsby.

Brief Summary of Bill
  • Expands the use of the design-build and general contractor/construction manager contracting procedures;
  • Establishes a project review committee to approve the use of design-build and general contractor/construction manager contracting procedures; and
  • Requires data collection for evaluation of alternative contracting procedures.

Hearing Date: 2/2/07

Staff: Marsha Reilly (786-7135).

Background:

Alternative forms of public works were first used on a very limited basis and then adopted in statute in 1994 for certain pilot projects. These alternative procedures included a design-build process and a general contractor/construction manager (GC/CM) process and may be used on projects costing in excess of $10 million.

The design-build procedure is a multi-step competitive process to award a contract to a single firm that agrees to both design and build a public facility that meets specific criteria. It may be used on projects valued over $10 million where:

The contract is awarded following a public request of proposals for design-build services. Following extensive evaluation of the proposals, the contract is awarded to the firm that submits the best and final proposal with the lowest price.

The GC/CM method employs the services of a project management firm that bears significant responsibility and risk in the contracting process. The government agency contracts with an architectural and engineering firm to design the facility and, early in the project, also contracts with a GC/CM firm to assist in the design of the facility, manage the construction of the facility, act as the general contractor, and guarantee that the facility will be built within budget. When the plans and specifications for a project phase are complete, the GC/CM firm subcontracts with construction firms to construct that phase. Initial selection of GC/CM finalists is based on the qualifications and experience of the firm.

In 2003, job order contracting was authorized as an alternative public works contracting procedure. Under a job order contract, a contractor agrees to perform an indefinite quantity of public works jobs, defined by individual work orders, over a fixed period of time. A public entity may not have more than two job order contracts in effect at any one time. The maximum total dollar amount that is awarded under a job order contract may not exceed $3 million in the first year, $5 million over the first two years, or $8 million over a three-year period if the contract is renewed or extended.

With some restrictions, the use of alternative public works contracting procedures are authorized to a limited number of public entities:

In 2005, the Capital Projects Advisory Review Committee was established to monitor and evaluate the use of traditional and alternative public works contracting procedures and evaluate potential future use of other alternative contracting procedures. The committee will also provide a forum in which best practices and concerns about alternative public works contracting can be discussed.

The authorization to use alternative public works procedures expires June 30, 2007.

Summary of Bill:

The use of alternative public works contracting procedures is extended to 2014.

Project Review Committee.
A Project Review Committee (Committee) is created to approve the use of the design-build, GC/CM, or both procedures, through a certification process or through approval on a project by project basis. Members of the Committee are appointed by the Capital Projects Advisory Review Board (Board), and appointments must represent a balance among the industries and public owners represented on the Board. All meetings of the Committee are public and the committee must allow for public comment.

Certification Process.
A public body may apply to the Committee for a three-year certification to use design-build, GC/CM, or both procedures. The public body must submit an application to the Committee that includes a description of its qualifications, its capital plan for the certification period, its intended use of the alternative contracting procedures, and any other information requested by the committee.

To certify a public body, the Committee must determine that the public body has:

Once a public body has been certified to use design-build, GC/CM, or both procedures, it may use the procedure without seeking approval by the Committee on a project by project basis. However, a public body certified to use GC/CM must seek additional approval to use that procedure for projects estimated to cost less than $10 million.

Project by Project Approval.
A public body may seek certification for one additional three-year period by submitting updated information on its capital plan to the Committee. The Committee may revoke any public body's certification upon a finding that its use of the alternative contracting procedure no longer serves the public interest.

Public bodies that are not certified to use design-build or GC/CM may seek approval to use the procedure on a project by project basis by submitting an application that includes its qualifications, a description of the proposed project, and which alternative contracting procedure it plans to use.

To approve a proposed project, the Committee must determine that:

Appeal of Committee Determinations.
A determination by the Committee may be appealed to the Board within seven days of the Committee's decision. The Board must resolve an appeal within 30 days, and the Board's decision is final.

Design-Build.
Several policy changes are made relating to the use of the design-build procedure.

Criteria for evaluating proposals for design-bid contracts are added and include the proposer's technical qualifications, its capability to perform, and its past performance. Additional factors are considered for analyzing finalists' proposals, including:

If all proposals are rejected, the public body must provide its reasons to the proposers in writing.

General Contractor/Construction Manager.

The major policy changes related to the use of GC/CM include:

Numerous other procedural changes are made to the contracting procedure.

Contract management responsibilities are expanded. The public body must provide contract documents that obligate the public owner to accept or reject a request for equitable adjustment, change order, or claim within 60 days. If the public owner does not respond in writing, the request is deemed denied.

Incentive clauses for early completion, cost savings, or other performance goals must be included in the request for proposals. Incentives may not be paid from any contingency fund established for coordination of the construction documents or coordination of the work. The public body must issue a change order within 30 days on change orders agreed to, in writing, by the GC/CM. If the public body fails to issue the change order, interest at a rate of one percent per month shall accrue on the dollar amount of the additional work satisfactorily completed.

The maximum allowable contract cost (MACC) may only be negotiated when the design is at least 90 percent complete and major subcontractor bid packages may be bid prior to agreement of the MACC. The public body may authorize the GC/CM to bid and award bid packages before receipt of complete plans and specifications; however, any contracts awarded must be incorporated in the negotiated MACC.

Bidder eligibility criteria for subcontractors currently listed in statute is removed and responsibility is determined based on specific objective criteria that must be listed in the bid documents.

A GC/CM may only bid on subcontract work or for the supply of equipment or materials if that work is customarily performed or supplied by the GC/CM, if the bid opening is managed by the public body, and if notification of the GC/CM's intent to bid is included in the solicitation of bids. The GC/CM is prohibited from purchasing equipment and materials for assignment to subcontract bid package bidders for installation or warranty. The GC/CM may not perform subcontract work in excess of 30 percent of the negotiated MACC.

Prebid determination of subcontractor eligibility must be preceded by a public hearing to receive comments and determine if establishing bidder eligibility in advance of seeking bids is in the best interests of the project.

Subcontract agreements must not delegate or assign the GC/CM's implied duty not to hinder or delay a subcontractor or delegate or assign the GC/CM's authority to resolve subcontractor conflicts; restrict a subcontractor's right to damages; require a subcontractor to bear the cost of trade damage repair; or require the subcontractor to execute progress payment applications that waive claims for additional time or compensation or bond or retainage rights as a condition of receipt of progress payment.

Job Order Contracting.

The authority to use the job order contracting procedure is limited to the same public bodies and has not been expanded. The maximum total dollar amount awarded under a job order contract is increased from $3 million to $4 million in the first year and from $8 million to $12 million over the three years of the contract. The Department of General Administration is authorized to have four job order contracts in effect at any one time. The amount of work that must be subcontracted on a job order contract is changed from 80 percent to 90 percent. The maximum dollar amount of a work order is increased from $300,000 to $350,000.

Data Collection.

All contracting procedures require public owners, as well as contractors and subcontractors, to report data required by the board. The Board must develop questionnaires designed to provide quantitative and qualitative data on alternative public works contracting procedures.

The act contains a sunset provision and requires an evaluation by the Joint Legislative Audit and Review Committee by June 30, 2013.

Creation of the Project Review Committee takes effect immediately. All other provisions of the act take effect June 30, 2007.

Appropriation: None.

Fiscal Note: Available.

Effective Date: The bill takes effect 90 days after adjournment of session in which bill is passed.