HOUSE BILL REPORT
HB 1765
This analysis was prepared by non-partisan legislative staff for the use of legislative members in
their deliberations. This analysis is not a part of the legislation nor does it constitute a
statement of legislative intent.
As Reported by House Committee On:
Judiciary
Title: An act relating to claims under a construction contract.
Brief Description: Changing provisions concerning limitation of claims under a construction contract.
Sponsors: Representatives Lantz, Springer, Williams, Rodne and Moeller.
Brief History:
Judiciary: 2/9/07, 2/26/07 [DPS].
Brief Summary of Substitute Bill |
|
HOUSE COMMITTEE ON JUDICIARY
Majority Report: The substitute bill be substituted therefor and the substitute bill do pass. Signed by 7 members: Representatives Lantz, Chair; Goodman, Vice Chair; Rodne, Ranking Minority Member; Ahern, Moeller, Ross and Williams.
Minority Report: Do not pass. Signed by 2 members: Representatives Kirby and Pedersen.
Staff: Bill Perry (786-7123).
Background:
Construction contracts sometimes contain various provisions, including mandatory protest
and claim clauses, covering unanticipated situations that may arise during the course of
construction. Such protest and claim clauses generally require the contractor to follow
specific notice requirements when seeking additional payment for extra work done and
increased expenses incurred. Such clauses may be found in public works contracts as well as
private contracts.
In a five-to-four 2003 decision, Mike M. Johnson, Inc. v. Spokane County, 150 Wn.2d 375,
the Washington Supreme Court construed such a protest and claim clause to require strict
adherence to a notice requirement. In Mike M. Johnson, a contract for sewer construction
authorized the project owner, Spokane County, to order work changes within the general
scope of the contract. The contract also provided that the contractor bore all risks associated
with any mistakes in the location of utilities as shown on the construction project plans. The
county submitted revised design plans and change orders, including proposed increases in the
contractor's compensation and extensions of the construction deadlines. The contractor did
not object to these changes. When the contractor began work under the change order,
however, it encountered buried phone lines that caused delay. The contract contained
specific and detailed procedures for the contractor to follow in making a claim for additional
compensation for the delay caused by the underground phone lines. The contractor did not
provide the required written notice and documentation, although it did send a letter stating
that the phone lines were causing the contractor to incur additional expenses. The county
notified the contractor that the letter did not satisfy the contract's notice requirements. The
county's attorney informed the contractor that the county did not intend to waive any defense
it might have against a claim by the contractor. The contractor never complied with the
formal requirements of the contract for making a claim.
The Court noted that as a general matter of contract law, procedural contract requirements
must be enforced absent either a waiver by the benefitting party or an agreement between the
parties to modify the contract. The Court held that as a matter of summary judgment, the
contractor did not meet the requirement of the contract for making a claim for additional
payment. It likewise held that actual notice of the claim did not satisfy the contract, and the
county's actions did not constitute a waiver of the county's right to assert the contractor's
non-compliance as a defense to the claim.
The dissent in Mike M. Johnson agreed that actual notice is not an exception to contract
compliance. However, the dissent asserted that the real issue is whether the county's actual
notice plus its direction to the contractor to proceed amounted to compliance with the
contract by the contractor or waiver of the notice requirement by the county. The dissent
would have ruled that when an owner directs a contractor to do work outside the original
contract, and then observes the work being done, the owner cannot then rely solely on
technical non-compliance with a claim provision to deny reasonable compensation, especially
when the owner has not been prejudiced by the non-compliance.
Standard form contracts used by some public agencies contain protest and claim provisions
that may allow a contractor to pursue a claim even though the contractor has failed to make
the required notice. These provisions state that failure to give the required notice constitutes
a waiver of the contractor's rights unless the contractor can prove the owner's interest was not
prejudiced in any way by the contractor's failure.
Summary of Substitute Bill:
A contractor may enforce a claim right under a construction contract, even if the contractor
has failed to submit the claim to the project owner in the form or within the time required by
the contract, if the contractor can show:
Any claim under the act must be submitted in writing within 30 days after substantial completion of the project.
Substitute Bill Compared to Original Bill:
The substitute bill adds a provision requiring that claims under the act must be submitted in
writing within 30 days after substantial completion of the construction project.
Appropriation: None.
Fiscal Note: Not requested.
Effective Date of Substitute Bill: The bill takes effect 90 days after adjournment of session in which bill is passed.
Staff Summary of Public Testimony:
(In support) This issue has festered since the Mike M. Johnson decision. That decision gives
no incentive for project owners to modify their contracts. The dissent in the case rightly
points out the injustice of allowing summary judgment when there has been a failure to
comply strictly with hyper-technical requirements in a contract. The bill will allow disputes
to be resolved on the merits.
Public works contracts are basically take-it-or-leave-it contracts. The Mike M. Johnson
decision takes equity out of the claims process despite the fact that the construction process is
fluid and dynamic and adjustments need to be made along the way. The bill will remove
these onerous clauses from contracts, and bids will be reduced and taxpayers will save
money. Since Mike M. Johnson, contractors are tending to avoid public works contracts.
Dealing with the strict contract clauses results in a mountain of paperwork because
contractors feel obligated to give notice on every little thing for fear of losing a claim right.
(With concerns) The bill reduces predictability and does not meet the need for timely notice
with sufficient documentation to resolve construction claims.
(Opposed) The bill interferes with the freedom of contract.
The bill will make the claims process unworkable. Claims provisions are important because
they provide early notice and a way to resolve problems. The current law gives predictability
to the process. The bill will reward those contractors who are the worst at giving timely
notice. It will prevent public agencies from managing public funds in a responsible manner.
There has to be a way to resolve claims quickly and efficiently in order to stay within a
budget.
The bill is not needed. The Mike M. Johnson case did not change what has been the
established and settled law for 60 years. The bill is ambiguous with respect to what
constitutes "consent" and with respect to who, in a complex building project, must give it.
Persons Testifying: (In support) Representative Lantz, prime sponsor; Michael Transue,
Paul Cressman, and Douglas Roach, Associated General Contractors; and John Ahlers,
Utility Contractors Association of Washington.
(With concerns) Pete Wall, Tacoma School District; and Bob Bourg, Department of General
Administration.
(Opposed) Chris Hirst, Puget Sound School Coalition; John Hurley, Finance and
Administration, The Evergreen State College; Richard Prentke, Perkins Coie LLP, and
Washington State School Construction Alliance; Mitch Denning, Alliance of Educational
Association; and Scott Bicklund, Port of Tacoma.