FINAL BILL REPORT
SHB 2378
C 481 L 07
Synopsis as Enacted
Brief Description: Expediting new vessel construction for Washington state ferries.
Sponsors: By House Committee on Transportation (originally sponsored by Representatives Flannigan, Jarrett, Clibborn, Eddy, Seaquist and Roberts).
House Committee on Transportation
Senate Committee on EnterCommittee
Background:
The design-build ferry procurement process is divided into three phases. To begin the
process, the Department of Transportation (DOT) issues a notice of intent to submit a request
for proposal (RFP).
In phase one, the DOT evaluates and selects pre-qualified proposers to participate in
development of technical proposals. The DOT rules outline pre-qualification requirements,
which include both a technical and financial test. In phase two, qualified proposers prepare
technical proposals in consultation with the DOT, sufficient to generate a firm, fixed price
bid to the DOT. Phase three includes the submission and evaluation of bids, award of the
contract, and design and construction of the automobile ferries.
In order to be considered, bids must conform with the technical proposals submitted in phase
two and proposers must have qualified through phase two. The DOT may select the lowest
total bid price and award the contract or reject any or all of the bids, republish the RFP, or
revise or cancel the RFP. The DOT may provide an honorarium to reimburse each
unsuccessful phase three proposer for a portion of its technical proposal preparation costs.
Summary:
The Legislature finds that the Washington State Ferries has commenced a vessel procurement
process to replace older and outdated vessels and that this process must move forward with
all speed. The commencement of construction is determined to be important for safety
reasons as well as for sustaining the region's ship construction and preservation capacity.
The DOT is authorized to consider and accept or reject a single proposal jointly submitted by
the qualified proposers. The DOT is also authorized to make revisions to the RFP, and pay
an honorarium to a proposer or proposers with whom the DOT engages in unsuccessful
negotiations.
The qualified proposers are authorized to meet and confer regarding matters reasonably
related to submitting a single proposal and implementing a final contract. The proposers are
required to declare their intent to submit a proposal within 30 days of the effective date of
this act and provide any information required by the DOT. If at the end of the 30-day period
the proposers have not declared their intent and provided the required information or the
DOT has determined that the proposers' plan is unacceptable, no further discussions between
the proposers are allowed.
The provisions related to ferry vessel procurement through the design-build process are
modified to allow for the negotiation of a contract if there is only a single qualified proposer
or proposal. The DOT is also authorized to negotiate incentives and cost-sharing provisions
with the proposer.
The DOT is required to submit a copy of the contract, along with the negotiated price, to the
Office of Financial Management 10 days prior to the execution of the contract. If the
negotiated price is higher than the adopted expenditure plan for vessel construction, the DOT
may not execute the contract until the Legislature reviews the proposal and adjusts the
expenditure plan.
If the DOT and the proposer or joint proposers are not able to reach an agreement, the DOT
may republish, revise, or cancel the RFP process.
Votes on Final Passage:
House 91 6
Senate 45 0
Effective: May 14, 2007