Washington State
House of Representatives
Office of Program Research
BILL
ANALYSIS

Local Government Committee

HB 3202


This analysis was prepared by non-partisan legislative staff for the use of legislative members in their deliberations. This analysis is not a part of the legislation nor does it constitute a statement of legislative intent.

Brief Description: Changing Washington's vesting laws.

Sponsors: Representatives Simpson, Sells and Nelson.

Brief Summary of Bill
  • Revises vesting-related provisions with respect to various state laws pertaining to land use and property development.

Hearing Date: 1/29/08

Staff: Thamas Osborn (786-7129).

Background:

The "Vested Rights Doctrine" in the State of Washington
In the context of land use law, the concept of "vesting" is used to determine the point in time at which the laws and regulations controlling the division, use, or development of real property become fixed with respect to the development of a specific property, thus preventing such use or development from being subject to subsequent regulatory changes. Over the years, the determination of when a property owner's development rights become vested has been a key issue for the Washington courts, resulting in the courts' development of what is known as the "vested rights doctrine."

In the case of Noble Manor v. Pierce County, 133 Wn.2d 269 (1997), the Washington Supreme Court (Court) summarized the "vested rights doctrine" as it had been developed by the courts under the common law:

   "In Washington, "vesting" refers generally to the notion that a land use application, under the proper conditions, will be considered only under the land use statutes and ordinances in effect at the time of the application's submission.
          . . . .
   At common law, this state's doctrine of vested rights entitled developers to have a land development proposal processed under the regulations in effect at the time that a complete building permit application was filed."

The Court went on to quote from a legislative report issued in 1987 in order to explain how the common law vesting doctrine operates in the context of a property owner's application for a building permit:

   "The doctrine provides that a party filing a timely and sufficiently complete building permit application obtains a vested right to have that application processed according to zoning, land use and building ordinances in effect at the time of the application. The doctrine is applicable if the permit application is sufficiently complete, complies with existing zoning ordinances, and building codes, and filed during the period the zoning ordinances under which the developer seeks to develop are in effect. If a developer complies with these requirements, a project cannot be obstructed by enacting new zoning ordinances or building codes."

This common law vesting doctrine has been codified by the legislature, in various forms, in several chapters of the Revised Code of Washington pertaining to land use, property development, and construction permitting.

Many other states have adopted vesting doctrines which are much more restrictive than those codified in the state of Washington. Specifically, in many states vesting occurs only at such time as the local government authority gives final approval to an application for a land use, development project, or building permit.

Vesting of "Subdivisions" and "Short Subdivisions"
A property owner must have a proposed division of land reviewed and approved by the county, city, or town in which the land is located. Such divisions of land are generally categorized as either "subdivisions" or "short subdivisions." Subdivisions are defined as land divisions resulting in five or more lots, tracts, or parcels. Short subdivisions are defined as land divisions resulting in four or fewer lots, tracts, or parcels. However, a city, town, or Growth Management Act planning county may adopt a local ordinance increasing to a maximum of nine the number of lots, tracts, or parcels that may be contained within a short subdivision.

State law distinguishes between subdivisions and short subdivisions with respect to the vesting of development rights. For a period of five years following approval by the local planning authority of the final plat, the development of a subdivision is governed by the pertinent laws and regulations in effect at the time of such approval. In other words, subdivision development rights are vested for a period of five years following approval of the final plat. If the property is not developed within this five-year period, the property is divested and the subdivision may be subject to development regulations enacted subsequent to final plat approval. In addition, a local government may make changes to the applicable development regulations prior to the expiration of this five-year period in response to a change of conditions that creates a serious threat to public health or safety.

Short subdivisions, on the other hand, are not subject to the five-year vesting limitation applicable to subdivisions. Development rights with respect to short subdivisions become fully vested at the time that a complete application for short plat approval is submitted to the local planning authority and, therefore, are not subject to subsequent changes in land use or development regulations.

Local governments are required to adopt an ordinance defining when an application for subdivision approval shall be deemed complete.

Each preliminary plat submitted for final approval of the legislative body shall be accompanied by the following agencies' recommendations for approval or disapproval:

Vesting During the Pendency of a Petition for Review Before a Growth Management Hearings Board
The Growth Management Act (GMA) establishes three regional Growth Management Hearings Boards (Boards). Each Board consists of three members satisfying residency requirements and qualified by experience or training in matters pertaining to land use planning.

Boards have limited jurisdiction and may only hear and determine petitions alleging:

A petition with a Board may be filed only by:

For the purposes of filing a petition with a Board, "person" is defined to any individual, partnership, corporation, association, state agency, governmental subdivision or unit thereof, or public or private organization or entity of any character.

Final decisions of the Boards may be appealed to the Superior Court. Additionally, if all parties agree, the Superior Court may directly review a petition filed with a Board.


Periodic Local Government Review of Comprehensive Plan and Development Regulations
Under the Growth Management Act, comprehensive plans and development regulations are subject to continuing review and evaluation by the adopting county or city. Generally, a county or city is required to take legislative action to review and, if needed, revise its comprehensive land use plan and development regulations to ensure that they comply with the requirements of the GMA. This review and evaluation process must include consideration of critical areas ordinances and, in some instances, an analysis of the population allocated to a city or county from the most recent 10-year population forecast by the Office of Financial Management.

Washington State Building Code: Building Permits and the Vesting Doctrine
The Washington State Building Code (Code) consists of a series of national model codes and standards that regulate the construction of residential, commercial, and industrial buildings and structures. The general purpose of the Code is to create minimum performance standards and requirements for construction and construction materials, consistent with accepted standards for engineering and safety. Counties and cities are authorized to create local amendments to the Code, provided such amendments are consistent with the Code's objectives and minimum performance standards.

The Code does not contain regulatory provisions pertaining to land use, property division, zoning, or site development. Rather, the Code explicitly states that such regulations are "reserved to local jurisdictions". However, the Code does contain vesting provisions pertaining to applications for building permits. Under these provisions, a land owner's development rights vest at the time a building permit application is submitted to the local building authority and, thereafter, the land owner is subject to only those permitting, zoning, or land use ordinances in effect at the time of the submission of the application.

GMA Planning for Projects Developed Outside of Urban Growth Areas
As part of its comprehensive land use plan, a county fully planning under the GMA must designate urban growth areas (UGAs) or areas within which urban growth must be encouraged and outside of which growth can occur only if it is not urban in nature. The GMA does, however, permit the authorization of certain development activity outside of UGAs in fully planning counties. Some of these development application approvals are, however, considered an amendment to the jurisdiction's comprehensive plan.

Among the developments permitted outside of UGAs, but which have infrastructure/facilities needs and other characteristics which are urban in nature, are the following: 1) fully contained communities; 2) industrial land banks; and 3) master planned resorts. The GMA contains extensive planning requirements governing the creation of these categories of development so as to minimize their impact on the rural environment.

Summary of Bill:

Introduction
The act revises certain vesting-related provisions in state law by amending statutes in various chapters of the Revised Code of Washington, as well as adding a new statute to the GMA. The act has the general effect of revising the "vested rights doctrine" as it has been codified by the Legislature in the pertinent statutes.

Vesting under the GMA During the Pendency of a Petition for Review Before a Board
During the pendency of an appeal before a Board, or during the 60-day period following the publication of a comprehensive plan or development regulation adopted by a local government, whichever occurs later, the submission of an application for a development project will not result in the vesting of any development rights that may be subject to the plan or regulations in question. Under such circumstances, vesting may occur only after the Board's final decision or after the 60-day period, whichever occurs later, and such vesting will be in accordance with the pertinent laws and regulations in effect at that time.

Vesting in Relation to Local Government Review of the Comprehensive Plan and Development Regulations under the GMA
During the pendency of a local government's review and evaluation of its comprehensive plan and development regulations conducted pursuant to the requirements of the GMA, the submission of land use or development-related applications will not result in the vesting of any land use or development rights at the time of such submission. Rather, vesting will occur only at such time that the local government takes final action on the application, following the completion of the review and evaluation process. Vesting will then be in accordance with the pertinent zoning, permitting, and other land use control ordinances in effect at that time.

Land use development applications filed after the submission or filing of a proposed amendment to a comprehensive plan or development regulation shall not vest until the time the local government takes final action on the application and following the completion of all administrative appeals pertaining to the amendment.

Vesting of Short Subdivisions
Beginning on July 1, 2008, any lots in a final plat filed for record are a valid land use for a period of five years from the date of filing, or once substantial construction has begun, whichever occurs earlier. Accordingly, such lots are not subject to changes in zoning laws during this period. In addition, the development of a subdivision shall be governed by the terms of the approval of the final plat and the statutes, ordinances, and regulations in effect at the time the final plat is approved by both the local health department or designated water/sewer provider and the city or county engineer, and such vesting shall last for a period of five years following such approval. However, these vesting provisions may not be applicable if the legislative body finds that a change of conditions creates a serious threat to the public health or safety.

An application for preliminary plat approval is subject to GMA vesting provisions, as set forth in Section 2 of this act, pertaining to how vesting occurs in relation to a Board's review process and the 60-day period following the publication of a comprehensive plan or development regulation by a local government. Specifically, an application for preliminary plat approval that is submitted during the pendency of an appeal before a Board, or during the 60-day period following the publication of a comprehensive plan or development regulation adopted by a local government, whichever occurs later, will not result in the vesting of any development rights that may be subject to the plan or regulations in question. Under such circumstances, vesting may occur only after the Board's final decision or after the 60-day period, whichever occurs later, and such vesting will be in accordance with the pertinent laws and regulations in effect at that time.

An application for preliminary plat approval is subject to additional GMA vesting provisions, as set forth in Section 3 of this act, pertaining to how vesting occurs during the pendency of a local government's review and evaluation of its comprehensive plan and development regulations conducted pursuant to the requirements of the GMA. Specifically, the act of submitting an application for preliminary plat approval that is submitted during the pendency of this local government review and evaluation process will not result in the vesting of any development rights that may be subject to the plan or regulations in question. Rather, vesting will occur only at such time that the local government takes final action on the application, following the completion of the review and evaluation process. Vesting will then be in accordance with the pertinent zoning, permitting, and other land use control ordinances in effect at that time.

Development rights for specified categories of large development projects vest at the time the permit application is approved or denied by the local government. Such projects include:

If a local government fails to adopt an ordinance defining when a subdivision application shall be deemed complete, then vesting shall occur only when the local government takes final action on the application.

Washington State Building Code: Building Permits and the Vesting Doctrine
The permitting statutes of the Washington State Building Code are amended to create exceptions to the general rule that a land owner's development rights with respect to building permits vest at the time a permit application is submitted to the local building authority. The substance of these amendments is described in the sections below.

An application for a building permit is subject to GMA vesting provisions, as set forth in Section 2 of this act, pertaining to how vesting occurs during a Board's review process and the 60-day period following the publication of a comprehensive plan or development regulation by a local government. Specifically, an application for a building permit that is submitted during the pendency of an appeal before a Board, or during the 60-day period following the publication of a comprehensive plan or development regulation adopted by a local government, whichever occurs later, will not result in the vesting of any permitting or development rights that may be subject to the plan or regulations in question. Under such circumstances, vesting may occur only after the Board's final decision or after the 60-day period, whichever occurs later, and such vesting will be in accordance with the pertinent laws and regulations in effect at that time.

An application for a building permit is subject to additional GMA vesting provisions, as set forth in Section 3 of this act, pertaining to how vesting occurs during the pendency of a local government's review and evaluation of its comprehensive plan and development regulations conducted pursuant to the requirements of the GMA. Specifically, the act of submitting an application for a building permit that is submitted during the pendency of this local government review and evaluation process will not result in the vesting of any development rights that may be subject to the plan or regulations in question. Rather, vesting will occur only at such time that the local building authority takes final action on the application, following the completion of the review and evaluation process. The vesting of permitting rights will then be in accordance with the pertinent development-related regulations in effect at that time.

Development rights for specified categories of large development projects vest at the time the building permit application is approved or denied by the local building authority. Such projects include:

If a local government fails to adopt an ordinance defining when a building permit application shall be deemed complete, then vesting shall occur only when the local building authority takes final action on the application.

GMA Vesting Rules Regarding Specified Categories of Development Projects
The act creates a new statutory section within the GMA that creates general rules pertaining to the vesting of specified categories of large development projects. Specifically, the vesting of any land use or development rights for specified categories of large development projects shall be in accordance with the pertinent ordinances that are in effect that on the date the permit application is approved or denied. Such projects include:

Appropriation: None.

Fiscal Note: Not requested.

Effective Date: The bill takes effect 90 days after adjournment of session in which bill is passed.