Brief Description: Addressing public works procurement.
Sponsors: Senate Committee on Government Operations & Elections (originally sponsored by Senators Haugen and Keiser).
Brief Summary of Engrossed Substitute Bill |
|
|
|
|
|
Hearing Date: 2/28/08
Staff: Tracey Taylor (786-7196).
Background:
In 1911 the Legislature authorized the Port District Act allowing citizens to create port districts.
Today, there are 75 port districts in Washington.
General Powers and Authority of Port Districts
Port districts are authorized for the purpose of acquisition, construction, maintenance,
operation, development, and regulation of harbor improvements, rail or motor vehicle transfer
and terminal facilities, water and air transfer and terminal facilities, or any combination of these
facilities.
Among the general powers granted to ports are the following:
Governance of Port Districts
Port districts are governed by a board of commissioners consisting of either three or five
members in accordance with specified statutory criteria. Port commissioners are nominated
either by commissioner district or, under certain circumstances, at-large. In all districts, port
commissioners are elected at-large. Subject to voter approval, a port district with five
commissioners may be authorized to have two commissioners who are both nominated and
elected at-large.
Public Contracting Processes
Pubic entities, including port districts, must use the public works contracting provisions for all
work, construction, alteration, repair, or improvement other than ordinary maintenance, executed
at the cost of the state or municipality, or which is by law a lien or charge on any property
therein. A contract is awarded based on a formal decision by the state or municipality notifying
the responsible bidder with the lowest responsive bid of the state or municipality's acceptance of
the bid and intent to enter into a contract with the bidder. However, a public entity may use the
small works roster for construction, building, renovation, remodeling, alteration, repair, or
improvement of real property with an estimated cost of $200,000 or less. Under this process,
quotations are solicited from at least five small works roster contractors, unless the estimated
cost is between $100,000 and $200,000, in which case all qualified contractors on the roster must
be notified.
State agencies, local agencies, and special districts can use the procurement process under
Chapter 39.80 RCW for professional services rendered by any person, other than an employee of
the agency, contracting to perform activities within the professional practice in Chapters 18.08
(Architects), 18.43 (Engineers & Land Surveyors) or 18.96 (Landscape Architects) RCW. The
agency negotiates a contract with the most qualified firm for architectural and engineering
services at a price which the agency determines is fair and reasonable to the agency. In making
its determination, the agency must take into account the estimated value of the services to be
rendered as well as the scope, complexity, and professional nature thereof.
State agencies use competitive solicitation for personal service contracts including many
consultant services related to construction. Personal services include professional or technical
expertise provided by a consultant to accomplish a specific study, project, task, or other work
statement. It does not include architect and engineer services procured under Chapter 39.80
RCW. Competitive Solicitation is a documented formal process providing an equal and open
opportunity to qualified parties and culminating in selection based on criteria which may include
such factors as the consultant's fees or costs, ability, capacity, experience, reputation,
responsiveness to time limitations, responsiveness to solicitation requirements, quality of
previous performance, and compliance with statutes and rules relating to contracts or services.
2007 Performance Audit by the State Auditor's Office
Pursuant to Initiative 900, the State Auditor's Office, with the private firms of Cotton &
Company and CDR Consultants, audited the Port of Seattle. The audit scope included all
construction projects and related consulting agreements from January 2004 through March 2007.
The audit identified significant and widespread issues related to contracting and contract
management by the Port of Seattle and made 51 recommendations to address these conditions.
Among the 51 recommendations are several statutory changes the auditor's recommend to the
Legislature. Found in Appendix C of the Washington State Auditor's Performance Audit Report:
Port of Seattle Construction Management of December 20, 2007 (Report No. 100008), these
recommendation include:
Summary of Bill:
The current statutory competitive bid threshold of $200,000 for port districts is clarified to apply
to public works contracts.
Port districts utilizing the small works roster for a public works contract, the estimated cost of
which is more than $100,000 but less than $200,000, must notify the remaining contractors on
the appropriate small works roster that quotations are being sought.
The current statutory contracting procedures for architectural and engineering services is
expanded to include construction related services. As a result, a state agency, local agency or
special district can publicly announce and negotiate contracts for other construction-related
services on the basis of demonstrated competence and qualification for the type of professional
services required and at a fair and reasonable price. A cross-reference applying the amended
chapter for the procurement of architectural, engineering, and construction related services to
port district is added to the ports title.
"Other construction-related services" is defined as consultant services provided by any person,
other than an employee of the agency, in connection with and furtherance of any public work for
project management, construction supervision, or construction management. This does not
include architectural and engineering services, legal services, accounting or auditing services,
claims consultant services, or other similar services that may be required in connection to any
public work.
"Public work consultant services" is defined as architectural, engineering, and other
construction-related services provided by a consultant.
The definition of "consultant" is amended t o eliminate a reference to "professional services" and
to include only persons providing architectural, engineering or other construction related
consultant services, who are not employees of the agency for which the services are being
provided.
If a port district is procuring the planning services from a public work consultant relating to a
facility outside the port district's jurisdictional boundaries, after the district has purchased
property for the facility, the port district with the responsibility for the future property
development use must make available to the public in the affected area certain information. The
information that must be available includes: the type and scale of proposed uses on the site; the
type and scale of business and industrial activities the development is likely to later attract to the
site and the nearby area; the general character and scope of impacts on air quality, noise, water
resources and recreation; and the expected impacts on local and state transportation
infrastructure. This information must be made available throughout the planning and the design
phases and may be accomplished by the use of web pages, office inspection and copying,
property tours and public meetings.
A port commission must establish by resolution the policies to comply with the competitive bid
requirements for public works projects and set forth the conditions by which the competitive bid
requirements may be waived.
Appropriation: None.
Fiscal Note: Preliminary fiscal note available.
Effective Date: The bill takes effect 90 days after adjournment of session in which bill is passed.