State of Washington | 60th Legislature | 2008 Regular Session |
READ FIRST TIME 02/28/08.
AN ACT Relating to generating electricity from tidal and wave energy; adding a new section to chapter 43.31 RCW; adding a new section to chapter 82.08 RCW; adding a new section to chapter 82.12 RCW; adding a new section to chapter 82.16 RCW; and providing expiration dates.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF WASHINGTON:
NEW SECTION. Sec. 1 A new section is added to chapter 43.31 RCW
to read as follows:
(1) The department of ecology must establish a wave and tidal
energy work group consisting of, but not limited to, representatives
from:
(a) The energy facility site evaluation council;
(b) The department of natural resources;
(c) The department of ecology;
(d) The department of fish and wildlife;
(e) The utilities and transportation commission;
(f) A wave energy company or tidal energy company, or both;
(g) A wave energy industry association or tidal energy industry
association, or both;
(h) Either a state or private university researching wave energy or
a state or private university researching tidal energy, or both;
(i) The Northwest Indian fisheries commission;
(j) An electrical utility; and
(k) A local government.
(2) The work group must organize and facilitate a stakeholder
review of issues relating to the siting and operation of tidal and wave
energy projects. Included within the review should be each state
agency with regulatory or proprietary jurisdiction over the projects or
sites on which projects are located, federal agencies with such
jurisdiction, tribes, project sponsors, utilities purchasing power from
or sponsoring such projects, nongovernmental organizations concerned
with responsible stewardship of the marine environment, citizens, and
local governments. The review must consider and build on the efforts
of the interagency work group that has been examining these issues over
the past year.
(3) The work group must organize the review to address at a minimum
the following:
(a) Applicable state and federal regulatory and aquatic land
proprietary management requirements, and ways to improve coordination
and the timeline of reviews and approvals;
(b) Determining the scope of an appropriate programmatic
environmental analysis of tidal and wave energy technologies to develop
a foundation for state review of proposed projects; and
(c) Current state policies regarding such projects and the need, if
any, for a comprehensive state policy.
(4) The work group must provide a report from the stakeholders and
agencies, together with any recommendations for environmental analysis
and administrative or legislative changes, to the governor and
appropriate committees of the senate and house of representatives by
December 31, 2008.
NEW SECTION. Sec. 2 A new section is added to chapter 82.08 RCW
to read as follows:
(1) The tax levied by RCW 82.08.020 does not apply to sales of
machinery and equipment used directly in generating tidal or wave
energy, or to sales of or charges made for labor and services rendered
in respect to installing such machinery and equipment, but only if the
purchaser develops with such machinery, equipment, and labor a facility
capable of generating not less than five kilowatts of electricity and
provides the seller with an exemption certificate in a form and manner
prescribed by the department. The seller shall retain a copy of the
certificate for the seller's files.
(2) For purposes of this section and section 3 of this act:
(a) "Machinery and equipment" has the same meaning as provided in
RCW 82.08.02567.
(b) Machinery and equipment is "used directly" in generating
electricity with tidal or wave energy if it provides any part of the
process that captures the energy of the tidal or wave energy.
(3) This section expires June 30, 2018.
NEW SECTION. Sec. 3 A new section is added to chapter 82.12 RCW
to read as follows:
(1) The provisions of this chapter do not apply with respect to
machinery and equipment used directly in generating not less than five
kilowatts of electricity using tidal or wave energy as the principal
source of power, or to the use of labor and services rendered in
respect to installing such machinery and equipment.
(2) The definitions in section 2 of this act apply to this section.
(3) This section expires June 30, 2018.
NEW SECTION. Sec. 4 A new section is added to chapter 82.16 RCW
to read as follows:
(1) In computing tax under this chapter, an amount equal to the
cost of production at the plant for consumption within the state of
Washington of electrical energy produced or generated from tidal or
wave energy is deducted from gross income.
(2) This section applies only to new facilities for the production
or generation of energy from tidal or wave energy on which construction
or installation is begun after January 1, 2008, and before January 1,
2018.
(3) Deductions under subsection (1) of this section are allowed for
a period not to exceed thirty years after the project is placed in
operation.
(4) The department of revenue, after consultation with the
utilities and transportation commission in the case of investor-owned
utilities and the governing bodies of locally regulated utilities, must
determine the eligibility of individual projects and measures for
deductions under this section.