CERTIFICATION OF ENROLLMENT

SENATE BILL 5798

Chapter 152, Laws of 2007

60th Legislature
2007 Regular Session



DESIGN-BUILD CONSTRUCTION--TRANSPORTATION



EFFECTIVE DATE: 07/22/07

Passed by the Senate March 12, 2007
  YEAS 49   NAYS 0

BRAD OWEN
________________________________________    
President of the Senate
Passed by the House April 6, 2007
  YEAS 96   NAYS 0

FRANK CHOPP
________________________________________    
Speaker of the House of Representatives


 
CERTIFICATE

I, Thomas Hoemann, Secretary of the Senate of the State of Washington, do hereby certify that the attached is SENATE BILL 5798 as passed by the Senate and the House of Representatives on the dates hereon set forth.

THOMAS HOEMANN
________________________________________    
Secretary
Approved April 20, 2007, 2:52 p.m.








CHRISTINE GREGOIRE
________________________________________    
Governor of the State of Washington
 
FILED
April 20, 2007







Secretary of State
State of Washington


_____________________________________________ 

SENATE BILL 5798
_____________________________________________

Passed Legislature - 2007 Regular Session
State of Washington60th Legislature2007 Regular Session

By Senators Swecker and Haugen

Read first time 02/01/2007.   Referred to Committee on Transportation.



     AN ACT Relating to design-build construction for transportation projects; and amending RCW 47.20.780.

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF WASHINGTON:

Sec. 1   RCW 47.20.780 and 2001 c 226 s 2 are each amended to read as follows:
     The department of transportation shall develop a process for awarding competitively bid highway construction contracts for projects over ten million dollars that may be constructed using a design-build procedure. As used in this section and RCW 47.20.785, "design-build procedure" means a method of contracting under which the department of transportation contracts with another party for the party to both design and build the structures, facilities, and other items specified in the contract.
     The process developed by the department must, at a minimum, include the scope of services required under the design-build procedure, contractor prequalification requirements, criteria for evaluating technical information and project costs, contractor selection criteria, and issue resolution procedures.
     ((This section expires April 30, 2008.))


         Passed by the Senate March 12, 2007.
         Passed by the House April 6, 2007.
         Approved by the Governor April 20, 2007.