AN ACT Relating to the capital budget; making appropriations and authorizing expenditures for capital improvements; amending 2009 c 497 ss 1005, 1013, 1023, 1029, 1031, 1034, 1035, 1039, 1040, 1048, 1054, 1055, 1060, 1061, 1063, 1064, 1068, 1073, 1086, 1087, 2001, 2002, 2034, 2037, 2038, 3007, 3020, 3085, 3168, 4008, 5008, 5002, 5014, 5024, 5025, 5027, 5028, 5030, 5035, 5039, 5040, 5041, 5042, 5055, 5056, 5057, 5061, 5065, 5070, 5078, 5079, 5081, 5083, 5092, 5097, 5104, 5109, 5110, 5111, 5146, 5147, 5148, 5149, 5170, 5171, 5172, 5173, 5177, 5178, 5191, 5192, 5196, 5210, 5211, 5212, 5213, 5223, 5224, and 6009 (uncodified); adding new sections to 2009 c 497 (uncodified); creating a new section; and declaring an emergency.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF WASHINGTON:
NEW SECTION. Sec. 1 A supplemental capital budget is hereby
adopted and, subject to the provisions set forth in this act, the
several dollar amounts hereinafter specified, or so much thereof as
shall be sufficient to accomplish the purposes designated, are hereby
appropriated and authorized to be incurred for capital projects during
the period beginning with the effective date of this act and ending
June 30, 2011, out of the several funds specified in this act.
Sec. 1001 2009 c 497 s 1005 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF ((COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT))
COMMERCE
Local and Community Projects (20064008)
The reappropriation in this section is subject to the following
conditions and limitations: (1) $64,319 of the remaining
reappropriation for El Centro de la raza may be used for building
infrastructure. (2) $10,000 of the remaining reappropriation for
miracle league handicapped baseball may be used for pre-grading and
resurfacing construction. (3) $1,394,107 of the remaining
reappropriation for MOBIUS/inland northwest science and technology
center may be used for design and construction.
Reappropriation:
State Building Construction Account--State . . . . . . . . . . . . (($10,658,000))
$10,508,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $37,141,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . (($47,799,000))
$47,649,000
Sec. 1002 2009 c 497 s 1013 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF ((COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT))
COMMERCE
Job and Economic Development Grants (20064950)
The ((re))appropriation in this section is subject to the following
conditions and limitations:
(1) The ((re))appropriation is subject to the provisions of section
107, chapter 371, Laws of 2006.
(2) The ((re))appropriation is subject to the project list in
section 107, chapter 371, Laws of 2006.
(3) Up to $1,000,000 of the ((re))appropriation for the Pacific
Northwest national labs campus infrastructure project is provided
solely for giga-pop infrastructure.
(4) Up to $2,200,000 of the ((re))appropriation is provided solely
for military communities infrastructure projects. Military communities
infrastructure projects shall include:
(a) Grants to counties and cities for the purchase of development
easements and the purchase of real property in fee simple to restrict
the use of accident potential zones and clear zones. The office of
financial management shall establish a competitive process for
selecting projects to receive the grants. Final allocation of these
grants shall be at the discretion and with the approval of the director
of the office of financial management.
The grants are subject to the following conditions:
(i) The county or city must be subject to and in compliance with
RCW 36.70A.530;
(ii) The grants may not be used to remove encroachments into these
zones allowed by county or city zoning or permitting actions;
(iii) The county or city must have an encroachment prevention plan
preventing future encroachment into these zones; and
(iv) The grant provided by the state must not exceed one-third of
the project cost with funds from local and federal sources providing
the balance of the funds.
(b) Up to $481,000 of the ((re))appropriation is provided solely
for improvements to a military department site on Fairchild air force
base.
((Reappropriation:))
Public Works Assistance Account--State . . . . . . . . . . . . $14,172,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $12,439,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($35,828,000))
$37,561,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $50,000,000
Sec. 1003 2009 c 497 s 1023 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF ((COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT))
COMMERCE
Job Development Fund Grants (20074010)
The ((re))appropriation in this section is subject to the following
conditions and limitations: The ((re))appropriation is subject to the
provisions of section 1032, chapter 520, Laws of 2007.
The appropriation in this section is subject to the following
conditions and limitations: ((The)) $3,000,000 of the appropriation is
provided solely for a grant to the port of Grays Harbor for the bulk
liquid facility project.
((Reappropriation:))
Job Development Account--State . . . . . . . . . . . . $22,228,000
Appropriation:
((Job Development Account--State . . . . . . . . . . . . $3,000,000))
State Building Construction Account--State . . . . . . . . . . . . $20,930,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($24,702,000))
$29,000,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $49,930,000
Sec. 1004 2009 c 497 s 1029 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF ((COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT))
COMMERCE
Local and Community Projects (20084001)
The reappropriation in this section is subject to the following
conditions and limitations:
(1) The projects must comply with RCW 43.63A.125 and other
requirements for community projects administered by the department.
(2) The reappropriation is subject to the provisions of section
1008, chapter 328, Laws of 2008.
(3) $1,000,000 of the remaining reappropriation for the Evergreen
school district health and biosciences academy may be used for land
acquisition. If the facility is not constructed by June 30, 2015, the
school district shall reimburse the state an amount equal to $1,000,000
increased by the average percentage appreciation in property values for
undeveloped land in the surrounding area between the date the school
district acquired the property and June 30, 2015 or the date the school
district disposes of the property.
(4) $600,000 of the remaining reappropriation for the institute for
community leadership may be used for land acquisition.
(5) $250,000 of the remaining reappropriation for the Pacific
Northwest ilocandia association may be used for acquisition and
renovation.
(6) $200,000 of the remaining reappropriation for the library
connection at Greenbridge may be used for construction and equipment.
(7) $1,000,000 of the remaining reappropriation for the Evergreen
school district health and biosciences academy may be used for land
acquisition.
Reappropriation:
State Building Construction Account--State . . . . . . . . . . . . (($61,200,000))
$59,000,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $71,694,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . (($132,894,000))
$130,694,000
Sec. 1005 2009 c 497 s 1031 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF ((COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT))
COMMERCE
Belfair Sewer Improvements (20084852)
Reappropriation:
State Building Construction Account--State . . . . . . . . . . . . $5,500,000
((Public Works Assistance Account--State . . . . . . . . . . . . $4,800,000))
Subtotal Reappropriation . . . . . . . . . . . . $10,300,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $4,800,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $10,300,000
Sec. 1006 2009 c 497 s 1034 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF ((COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT))
COMMERCE
Quillayute Valley Wood-Fire Boiler (20084858)
((Reappropriation:))
Energy Freedom Account--State . . . . . . . . . . . . $1,000,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $980,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($0))
$20,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $1,000,000
Sec. 1007 2009 c 497 s 1035 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF ((COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT))
COMMERCE
Snohomish County Biodiesel (20084859)
((Reappropriation:))
Energy Freedom Account--State . . . . . . . . . . . . $500,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $81,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($0))
$419,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $500,000
Sec. 1008 2009 c 497 s 1039 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF ((COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT))
COMMERCE
Drinking Water State Revolving Fund Loan Program (30000005)
Appropriation:
Drinking Water Assistance Account--State . . . . . . . . . . . . (($8,000,000))
$10,930,000
Drinking Water Assistance Repayment Account--State . . . . . . . . . . . . $31,201,000
Subtotal Appropriation . . . . . . . . . . . . (($39,201,000))
$42,131,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $215,974,000
TOTAL . . . . . . . . . . . . (($255,175,000))
$258,105,000
Sec. 1009 2009 c 497 s 1040 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF ((COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT))
COMMERCE
Building for the Arts Grants (30000006)
The appropriation in this section is subject to the following
conditions and limitations:
(1) Projects must be selected based on their readiness to proceed.
(2) The appropriation is provided solely for the following list of
projects:
Admiral Theatre-No Theatre Left Behind | $140,000 |
(( | |
$250,000 | |
Campus Consolidation (Cornish) | $375,000 |
$500,000 | |
$20,000 | |
Downstairs at the 5th | $800,000 |
Federal Way Performing Arts Center | $325,000 |
$150,000 | |
$150,000 | |
Langston Hughes Performing Arts Center | $475,000 |
$200,000 | |
Modular Classrooms for Dance (Gladish) | $30,000 |
Mt. Baker Theatre | $1,000,000 |
Museum Expansion (Maryhill) | $1,500,000 |
$1,000,000 | |
Reconstruction of First Stage (Issaquah) | $400,000 |
Seattle Opera Center | $650,000 |
Stage Two (Whidbey) | $450,000 |
Vashon Arts Center | $1,115,000 |
$1,000,000 | |
$70,000 | |
Total | (( |
Sec. 1010 2009 c 497 s 1048 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF ((COMMUNITY, TRADE, AND ECONOMIC DEVELOPMENT))
COMMERCE
Local and Community Projects (30000019)
The appropriation in this section is subject to the following
conditions and limitations:
(1) Prior to receiving funds, project recipients must demonstrate
that the project site is under control for a minimum of ten years,
either through ownership or a long-term lease. This requirement does
not apply to appropriations for preconstruction activities or
appropriations whose sole purpose is to purchase real property that
does not include a construction or renovation component.
(3) Projects funded in this section may be required to comply with
Washington's high performance building standards as required by chapter
39.35D RCW.
(4) Project funds are available on a reimbursement basis only, and
shall not be advanced under any circumstances.
(5) Projects funded in this section must be held by the recipient
for a minimum of ten years and used for the same purpose or purposes
intended by the legislature as required in RCW 43.63A.125(2)(c).
(6) Projects funded in this section, including those that are owned
and operated by nonprofit organizations, are generally required to pay
state prevailing wages.
(7) The appropriation is provided solely for the following list of
projects:
Local Community Projects | |
7th St. Theater | $330,000 |
Arc of Tri-Cities | $900,000 |
Bellevue Clinic--Seattle Children's Hospital | $2,000,000 |
Blessed Sacrament Food and Emergency Facilities Renovation | $200,000 |
Children's Village Expansion Project | $500,000 |
Clark County Food Distribution Facility | $1,500,000 |
Coal Creek YMCA (Newcastle) | $800,000 |
Dawson Place Child Advocacy Center | $1,000,000 |
Federal Way National Little League Field Lighting Project and Monument Entry Sign | $177,000 |
Harlequin Theater | $235,000 |
Home Dialysis Center and Professional Workforce Training | $250,000 |
Kirkland Park Place Redevelopment | $2,000,000 |
Livingston Baker Fire and Life Safety | $750,000 |
Marshland Diking District | $500,000 |
Marysville Boys & Girls Club | $500,000 |
McClure Middle School Energy Saving Performance Contract Demonstration Project | $1,000,000 |
Mountains to Sound Greenway | $100,000 |
Mukilteo Boys & Girls Club | $150,000 |
Neighborcare Health Clinic and Rainier Beach Medical Clinic | $1,000,000 |
Parkland at Japanese Gulch | $1,000,000 |
Petrovitsky Park Upgrade | $750,000 |
Phoenix House | $200,000 |
Poulsbo Marine Center | $500,000 |
Public Broadcasting Frequency Expansion | $223,000 |
(( | |
Renovations to Mill Creek City Annex Building | $30,000 |
Snohomish County Emergency Center | $1,000,000 |
South Tacoma Community Center | $1,000,000 |
Whatcom Hospice House | $700,000 |
Zina Linnik | $950,000 |
NEW SECTION. Sec. 1011 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE DEPARTMENT OF COMMERCE
2010 Local and Community Projects (30000082)
The appropriation in this section is subject to the following
conditions and limitations:
(1) Prior to receiving funds, project recipients must demonstrate
that the project site is under control for a minimum of ten years,
either through ownership or a long-term lease. This requirement does
not apply to appropriations for preconstruction activities or
appropriations whose sole purpose is to purchase real property that
does not include a construction or renovation component.
(2) Projects funded in this section may be required to comply with
Washington's high performance building standards as required by chapter
39.35D RCW.
(3) Project funds are available on a reimbursement basis only, and
shall not be advanced under any circumstances.
(4) Projects funded in this section must be held by the recipient
for a minimum of ten years and used for the same purpose or purposes
intended by the legislature as required in RCW 43.63A.125(6).
(5) Projects funded in this section, including those that are owned
and operated by nonprofit organizations, are generally required to pay
state prevailing wages.
(6) The appropriation is provided solely for the following list of
projects:
Local Community Projects | |
Aviation High School | $3,000,000 |
Catholic Charities Spokane Family Service Center | $1,265,000 |
Chambers Bay US Amateur and US Open Preparations | $511,000 |
Junior Achievement (Statewide JA World Initiative) | $1,700,000 |
Museum of Flight Space Gallery | $3,000,000 |
Rainier Beach Medical & Dental Clinic (Neighborcare Health) | $1,000,000 |
Salishan Phase III | $1,000,000 |
Skagit Valley Hospital Inpatient Behavior Health Center | $750,000 |
Urban League Village at Colman School and Northwest African American Museum | $300,000 |
YMCA - Haselwood Family YMCA, Central Kitsap Community Campus | $500,000 |
Navos Mental Health and Wellness Center | $1,500,000 |
NEW SECTION. Sec. 1012 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE DEPARTMENT OF COMMERCE
Tulalip Water Pipeline (30000093)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $3,000,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $3,000,000
Sec. 1013 2009 c 497 s 1054 (uncodified) is amended to read as
follows:
FOR THE OFFICE OF FINANCIAL MANAGEMENT
Cowlitz River Dredging (20082856)
Reappropriation:
State Building Construction Account--State . . . . . . . . . . . . $313,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $500,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $687,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . (($1,000,000))
$1,500,000
NEW SECTION. Sec. 1014 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE OFFICE OF FINANCIAL MANAGEMENT
Port Angeles Economic Development Agreement (30000024)
The appropriation in this section is subject to the following
conditions and limitations:
The appropriation is provided solely to carry out paragraph 2.C. of
the economic development agreement associated with the case of Lower
Elwha Klallam Tribe et al v. State et al, Thurston county superior
court, cause No. 05-2-01595-8. The state has already provided $250,000
to carry out that paragraph. After disbursement of the appropriation
in this section, the state will provide no further funding under the
economic development agreement.
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $250,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $250,000
Sec. 1015 2009 c 497 s 1055 (uncodified) is amended to read as
follows:
FOR THE OFFICE OF FINANCIAL MANAGEMENT
Catastrophic Flood Relief (20084850)
The reappropriation in this section is subject to the following
conditions and limitations: Up to $4,803,000 of the total
appropriation is provided solely for the Chehalis basin flood control
authority or other authorized local government groups to develop or
participate in the development of flood hazard mitigation measures
throughout the basin.
Reappropriation:
State Building Construction Account--State . . . . . . . . . . . . $47,351,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $2,649,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $50,000,000
Sec. 1016 2009 c 497 s 1060 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF GENERAL ADMINISTRATION
Transportation Building Preservation (20021008)
((Reappropriation:))
Thurston County Capital Facilities Account--State . . . . . . . . . . . . $2,500,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $2,105,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($7,116,000))
$7,511,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $22,706,000
TOTAL . . . . . . . . . . . . $32,322,000
Sec. 1017 2009 c 497 s 1061 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF GENERAL ADMINISTRATION
Highway-License Building Repair and Renewal (20061013)
((Reappropriation:))
Thurston County Capital Facilities Account--State . . . . . . . . . . . . $100,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $24,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($3,423,000))
$3,499,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $3,523,000
Sec. 1018 2009 c 497 s 1063 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF GENERAL ADMINISTRATION
Natural Resources Building Repairs and Renewal (20061014)
Reappropriation:
State Vehicle Parking Account--State . . . . . . . . . . . . $30,000
((Thurston County Capital Facilities Account--State . . . . . . . . . . . . $100,000))
Subtotal Reappropriation . . . . . . . . . . . . $130,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $78,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($2,853,000))
$2,875,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $4,520,000
TOTAL . . . . . . . . . . . . $7,503,000
Sec. 1019 2009 c 497 s 1064 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF GENERAL ADMINISTRATION
Minor Works - Infrastructure Preservation (20081004)
Reappropriation:
((Thurston County Capital Facilities Account--State . . . . . . . . . . . . $136,000))
State Building Construction Account--State . . . . . . . . . . . . (($584,000))
$572,000
((Subtotal Reappropriation . . . . . . . . . . . . $720,000))
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $172,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($4,401,000))
$4,377,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $5,121,000
Sec. 1020 2009 c 497 s 1068 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF GENERAL ADMINISTRATION
Minor Works - Facility Preservation (20081015)
Reappropriation:
State Building Construction Account--State . . . . . . . . . . . . (($380,000))
$167,000
((Thurston County Capital Facilities Account--State . . . . . . . . . . . . $723,000))
Subtotal Reappropriation . . . . . . . . . . . . $1,103,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $1,150,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($5,583,000))
$5,369,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $6,686,000
Sec. 1021 2009 c 497 s 1073 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF GENERAL ADMINISTRATION
Minor Works Preservation (30000012)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . (($2,800,000))
$3,400,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . (($34,109,000))
$34,709,000
TOTAL . . . . . . . . . . . . (($36,909,000))
$38,109,000
NEW SECTION. Sec. 1022 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE DEPARTMENT OF GENERAL ADMINISTRATION
Capitol Campus Heating System Improvements (30000486)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $200,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $1,800,000
TOTAL . . . . . . . . . . . . $2,000,000
NEW SECTION. Sec. 1023 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE MILITARY DEPARTMENT
Camp Murray New Primary Gate Entrance (30000482)
Appropriation:
General Fund--Federal . . . . . . . . . . . . $67,500
Military Department Capital Account--State . . . . . . . . . . . . $157,500
Subtotal Appropriation . . . . . . . . . . . . $225,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $3,100,000
TOTAL . . . . . . . . . . . . $3,325,000
Sec. 1024 2009 c 497 s 1086 (uncodified) is amended to read as
follows:
FOR THE MILITARY DEPARTMENT
Minor Works Preservation (30000002)
Appropriation:
General Fund--Federal . . . . . . . . . . . . (($3,069,000))
$8,672,000
State Building Construction Account--State . . . . . . . . . . . . $1,709,000
Subtotal Appropriation . . . . . . . . . . . . (($4,778,000))
$10,381,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $18,700,000
TOTAL . . . . . . . . . . . . (($23,478,000))
$29,081,000
Sec. 1025 2009 c 497 s 1087 (uncodified) is amended to read as
follows:
FOR THE MILITARY DEPARTMENT
Minor Works Program (30000003)
Appropriation:
General Fund--Federal . . . . . . . . . . . . (($679,000))
$3,139,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $10,229,000
TOTAL . . . . . . . . . . . . (($10,908,000))
$13,368,000
NEW SECTION. Sec. 1026 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE MILITARY DEPARTMENT
Combined Support Maintenance Shop (20082006)
Appropriation:
General Fund--Federal . . . . . . . . . . . . $4,736,000
Subtotal Appropriation . . . . . . . . . . . . $4,736,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $22,164,000
TOTAL . . . . . . . . . . . . $26,900,000
Sec. 2001 2009 c 497 s 2001 (uncodified) is amended to read as
follows:
FOR THE CRIMINAL JUSTICE TRAINING COMMISSION
Replace Hawthorne Hall Dormitory (20082001)
((The appropriation in this section is subject to the following
conditions and limitations: The office of financial management shall
allot funds for the dormitory construction at the criminal justice
training commission only after the recommendation of the steering
committee participating in the analysis in section 1057 of this act has
been provided to the legislative fiscal committees and submitted to the
office of financial management for review.))
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . (($16,745,000))
$0
Reappropriation:
State Building Construction Account--State . . . . . . . . . . . . $632,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($1,293,000))
$1,104,000
Future Biennia (Projected Costs) . . . . . . . . . . . . (($0))
$16,934,000
TOTAL . . . . . . . . . . . . $18,670,000
Sec. 2002 2009 c 497 s 2002 (uncodified) is amended to read as
follows:
FOR THE CRIMINAL JUSTICE TRAINING COMMISSION
School Mapping (30000011)
The appropriation in this section is subject to the following
conditions and limitations: The legislature intends to complete ((half
of)) the remaining community and technical college mapping with this
appropriation ((and to appropriate funding for the remaining half of
unmapped square feet in community and technical colleges in the 2011-13
biennium)).
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . (($500,000))
$1,100,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . (($546,000))
$0
TOTAL . . . . . . . . . . . . (($1,046,000))
$1,100,000
NEW SECTION. Sec. 2003 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE DEPARTMENT OF LABOR AND INDUSTRIES
Central Office Roof Replacement and Fall Restraint Upgrade
(30000012)
Appropriation:
Accident Account--State . . . . . . . . . . . . $1,250,000
Medical Aid Account--State . . . . . . . . . . . . $1,250,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $2,500,000
NEW SECTION. Sec. 2004 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES
Juvenile Rehabilitation Administration: Community Facilities
(30000993)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $300,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $300,000
Sec. 2005 2009 c 497 s 2034 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF HEALTH
Drinking Water Assistance Program (30000013)
The appropriation in this section is subject to the following
conditions and limitations: $38,462,000 is provided from the American
recovery and reinvestment act of 2009.
Appropriation:
Drinking Water Assistance Account--Federal . . . . . . . . . . . . (($24,348,000))
$38,348,000
Drinking Water Assistance Account--Federal
American Recovery and Reinvestment Act . . . . . . . . . . . . $38,462,000
Subtotal Appropriation . . . . . . . . . . . . (($62,810,000))
$76,810,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . (($62,810,000))
$76,810,000
Sec. 2006 2009 c 497 s 2037 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF VETERANS AFFAIRS
State Veterans Cemetery (20082004)
Reappropriation:
General Fund--Federal . . . . . . . . . . . . $6,815,000
Appropriation:
General Fund--Federal . . . . . . . . . . . . $1,909,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $1,010,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . (($7,825,000))
$9,734,000
Sec. 2007 2009 c 497 s 2038 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF VETERANS AFFAIRS
Minor Works - Facilities Preservation (30000003)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . (($500,000))
$775,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $6,585,000
TOTAL . . . . . . . . . . . . (($7,085,000))
$7,360,000
NEW SECTION. Sec. 2008 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE DEPARTMENT OF CORRECTIONS
Washington State Penitentiary: Housing Units, Kitchen, and Site
Work (30000482)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $6,819,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $44,000,000
TOTAL . . . . . . . . . . . . $50,819,000
Sec. 3001 2009 c 497 s 3007 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF ECOLOGY
Sunnyside Valley Irrigation District Water Conservation (20052851)
Reappropriation:
State Building Construction Account--State . . . . . . . . . . . . $2,800,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . (($2,850,000))
$8,650,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $4,147,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $4,000,000
TOTAL . . . . . . . . . . . . (($13,797,000))
$19,597,000
Sec. 3002 2009 c 497 s 3020 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF ECOLOGY
Breazeale Interpretive Center (20082856)
Reappropriation:
General Fund--Federal . . . . . . . . . . . . (($270,000))
$419,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($225,000))
$76,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $495,000
NEW SECTION. Sec. 3003 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
Settlement Funding to Clean Up Toxic Sites (30000145)
Appropriation:
Cleanup Settlement Account--State . . . . . . . . . . . . $3,180,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $3,180,000
NEW SECTION. Sec. 3004 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
Clean Up Toxic Sites - Puget Sound (30000144)
Appropriation:
Cleanup Settlement Account--State . . . . . . . . . . . . $800,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $800,000
NEW SECTION. Sec. 3005 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
Reducing Diesel Particle Emissions in Tacoma (30000139)
Appropriation:
Air Pollution Control Account--State . . . . . . . . . . . . $1,000,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $1,000,000
NEW SECTION. Sec. 3006 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
Reducing Wood Smoke Particle Emissions in Tacoma (30000140)
Appropriation:
Air Pollution Control Account--State . . . . . . . . . . . . $600,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $600,000
NEW SECTION. Sec. 3007 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE DEPARTMENT OF ECOLOGY
Water Pollution Control Revolving Fund Program (30000142)
Appropriation:
Water Pollution Control Account--State . . . . . . . . . . . . $25,000,000
Water Pollution Control Account--Federal . . . . . . . . . . . . $17,000,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $42,000,000
Sec. 3008 2009 c 497 s 3085 (uncodified) is amended to read as
follows:
FOR THE STATE PARKS AND RECREATION COMMISSION
Federal Grant Authority (30000006)
Appropriation:
General Fund--Federal . . . . . . . . . . . . (($990,000))
$1,990,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $4,000,000
TOTAL . . . . . . . . . . . . (($4,990,000))
$5,990,000
NEW SECTION. Sec. 3009 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE STATE PARKS AND RECREATION COMMISSION
Deception Pass State Park - Wastewater System (30000483)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $300,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $2,600,000
TOTAL . . . . . . . . . . . . $2,900,000
NEW SECTION. Sec. 3010 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE DEPARTMENT OF FISH AND WILDLIFE
Wooten Wildlife Area - Spring Lake Dam Renovation (30000191)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $220,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $1,423,000
TOTAL . . . . . . . . . . . . $1,643,000
Sec. 3011 2009 c 497 s 3168 (uncodified) is amended to read as
follows:
FOR THE DEPARTMENT OF FISH AND WILDLIFE
Mitigation Projects and Dedicated Funding (20082048)
The reappropriation and the appropriation in this section ((is))
are subject to the following conditions and limitations: Up to
$2,300,000 of the reappropriation ((is)) and the appropriation are
provided solely for capital projects and engineering to pay the total
cost of labor and materials provided by the department of fish and
wildlife.
Reappropriation:
General Fund--Federal . . . . . . . . . . . . $9,000,000
Appropriation:
General Fund--Private/Local . . . . . . . . . . . . $2,500,000
Game Special Wildlife Account--Federal . . . . . . . . . . . . $600,000
Game Special Wildlife Account--Private/Local . . . . . . . . . . . . $900,000
General Fund--Federal . . . . . . . . . . . . (($25,000,000))
$31,000,000
Subtotal Appropriation . . . . . . . . . . . . (($29,000,000))
$35,000,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $19,125,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $114,800,000
TOTAL . . . . . . . . . . . . (($171,925,000))
$177,925,000
NEW SECTION. Sec. 3012 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE PUGET SOUND PARTNERSHIP
Puget Sound Aquatic Cleanup and Restoration (30000004)
The appropriation is this section is subject to the following
conditions and limitations:
(1) Projects must be selected based on their readiness to proceed.
(2) The appropriation is provided solely for the following list of
projects. However, if additional federal funding is made available,
the Puget Sound partnership may remove projects from this list that
receive federal funding, or use only that portion of the appropriation
necessary to match federal funds, and add projects for state funding
from OFM document 30000004.
$746,508 | |
$1,030,000 | |
Carpenter Creek estuary restoration | $2,783,597 |
Dungeness River engineered logjams | $1,030,000 |
$185,400 | |
$381,100 | |
$1,030,000 | |
Venema natural drainage system | $824,000 |
$1,342,559 | |
Toxics cleanup and remedial actions | $646.836 |
Total | $10,000,000 |
Sec. 4001 2009 c 497 s 4008 (uncodified) is amended to read as
follows:
FOR THE WASHINGTON STATE DEPARTMENT OF TRANSPORTATION
Commute Trip Reduction for Thurston County State Agencies
(92000001)
The appropriation in this section is subject to the following
conditions and limitations: The appropriation is provided solely for
implementation of chapter 427, Laws of 2009 (Substitute Senate Bill No.
6088 (commute trip reduction)).
Appropriation:
State Vehicle Parking Account--State . . . . . . . . . . . . (($734,000))
$650,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . (($734,000))
$650,000
Sec. 5001 2009 c 497 s 5008 (uncodified) is amended to read as
follows:
FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION
Northeast King County Skills Center (20084855)
Appropriation:
School Construction/Skills Center Building
Account--State . . . . . . . . . . . . (($9,049,000))
$7,649,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $550,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . (($9,599,000))
$8,199,000
Sec. 5002 2009 c 497 s 5002 (uncodified) is amended to read as
follows:
FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION
School Construction Assistance Grants (20084200)
The appropriation and the reappropriation in this section are
subject to the following conditions and limitations:
For school construction projects funded through the school
construction assistance grant program, the superintendent of public
instruction shall require mapping the design of new facilities and
remapping the design of facilities to be remodeled.
Reappropriation:
Common School Construction Account--State . . . . . . . . . . . . $176,922,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $137,267,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $477,570,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $791,759,000
Sec. 5003 2009 c 497 s 5014 (uncodified) is amended to read as
follows:
FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION
2009-11 School Construction Assistance Grant Program (30000031)
The appropriation in this section is subject to the following
conditions and limitations:
(1) The office of the superintendent of public instruction shall
develop a tracking system to increase accuracy in predicting the timing
of school district claims for reimbursement for school construction
assistance grants. The office of the superintendent of public
instruction shall also improve its communication with school districts
regarding the status of grant projects and create requirements
regarding the timing of reimbursement claims. The office of the
superintendent of public instruction shall submit a report on the
progress of the new tracking and communication system to the
appropriate committees of the legislature by November 15, 2009. The
report must include a list of school district capital projects
receiving state funding and each project's anticipated final
reimbursement date.
(2) In calculating square foot eligibility for state assistance
grants, kindergarten student headcount shall not be reduced by fifty
percent.
(3) For school construction projects funded through the school
construction assistance grant program, the superintendent of public
instruction shall require mapping the design of new facilities and
remapping the design of facilities to be remodeled.
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . (($369,920,000))
$282,620,000
Common School Construction Account--State . . . . . . . . . . . . $259,029,000
Common School Construction Account--Federal . . . . . . . . . . . . $2,500,000
School Construction and Skill Centers Building
Account--Bond--State . . . . . . . . . . . . (($58,284,000))
$59,684,000
Subtotal Appropriation . . . . . . . . . . . . (($689,733,000))
$603,833,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $3,921,000,000
TOTAL . . . . . . . . . . . . (($4,610,733,000))
$4,524,833,000
NEW SECTION. Sec. 5004 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION
Distressed Communities School Grants (30000042)
The appropriation in this section is subject to the following
conditions and limitations: The office of the superintendent of public
instruction shall develop a competitive grant program for school
districts demonstrating the most need to renovate or replace major
building systems. Grants may not exceed $500,000. A school district
must show a school facility need that directly affects the health and
safety of students. School districts will receive priority based on,
but not limited to, the following criteria: (1) The financial
resources of the school district, (2) the inability to pass a capital
bond measure, and (3) the condition of current facilities and the
district's ability to maintain them.
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $5,000,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $5,000,000
NEW SECTION. Sec. 5005 A new section is added to 2009 c 497
(uncodified) to read as follows:
FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION--WASHINGTON STATE CENTER
FOR CHILDHOOD DEAFNESS AND HEARING LOSS
Lloyd Auditorium Emergency Repairs (30000012)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $2,500,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $2,500,000
Sec. 5006 2009 c 497 s 5024 (uncodified) is amended to read as
follows:
FOR THE UNIVERSITY OF WASHINGTON
Clark Hall Renovation (20061007)
((Reappropriation:))
Education Construction Account--State . . . . . . . . . . . . $2,000,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $1,033,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($16,054,000))
$17,021,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $18,054,000
Sec. 5007 2009 c 497 s 5025 (uncodified) is amended to read as
follows:
FOR THE UNIVERSITY OF WASHINGTON
Minor Works - Facility Preservation (20081001)
Reappropriation:
University of Washington Building
Account--State . . . . . . . . . . . . (($16,000,000))
$8,728,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $5,671,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($7,000,000))
$8,601,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $23,000,000
Sec. 5008 2009 c 497 s 5027 (uncodified) is amended to read as
follows:
FOR THE UNIVERSITY OF WASHINGTON
Balmer Hall Reconstruction (20081004)
In conjunction with the appropriation in this section, University
of Washington is authorized to issue a bond or bonds in an amount not
to exceed $42,800,000 in value for construction of the facility
identified in this section. The bond must be financed from building
fee and trust land revenue deposited into the university's bond
retirement account in accordance with RCW 28B.20.700 through
28B.20.740.
Reappropriation:
State Building Construction Account--State . . . . . . . . . . . . (($3,000,000))
$2,913,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($1,000,000))
$1,087,000
Future Biennia (Projected Costs) . . . . . . . . . . . . (($38,600,000))
$0
TOTAL . . . . . . . . . . . . (($42,600,000))
$4,000,000
Sec. 5009 2009 c 497 s 5028 (uncodified) is amended to read as
follows:
FOR THE UNIVERSITY OF WASHINGTON
Intermediate Student Service and Classroom Improvements (20081005)
((Reappropriation:))
Education Construction Account--State . . . . . . . . . . . . $7,245,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $6,934,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($6,036,000))
$6,347,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $13,281,000
Sec. 5010 2009 c 497 s 5030 (uncodified) is amended to read as
follows:
FOR THE UNIVERSITY OF WASHINGTON
UW Tacoma (20082005)
In conjunction with the appropriation and the reappropriation in
this section, University of Washington is authorized to issue a bond or
bonds in an amount not to exceed $7,450,000 for construction of the
facility identified in this section. The bond must be financed from
building fee and trust land revenue deposited into the university's
bond retirement account in accordance with RCW 28B.20.700 through
28B.20.740.
Reappropriation:
State Building Construction Account--State . . . . . . . . . . . . (($4,000,000))
$3,543,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $34,000,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($2,150,000))
$2,607,000
Future Biennia (Projected Costs) . . . . . . . . . . . . (($17,044,000))
$0
TOTAL . . . . . . . . . . . . (($57,194,000))
$40,150,000
Sec. 5011 2009 c 497 s 5035 (uncodified) is amended to read as
follows:
FOR THE UNIVERSITY OF WASHINGTON
UW Tacoma - Land Acquisition (20092003)
In conjunction with the appropriation in this section, University
of Washington is authorized to issue a bond or bonds in an amount not
to exceed $2,000,000 for the purchase of the land identified in this
section. The bond must be financed from building fee and trust land
revenue deposited into the university's bond retirement account in
accordance with RCW 28B.20.700 through 28B.20.740.
((Reappropriation:))
Education Construction Account--State . . . . . . . . . . . . $469,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $469,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $1,531,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $2,000,000
Sec. 5012 2009 c 497 s 5039 (uncodified) is amended to read as
follows:
FOR THE UNIVERSITY OF WASHINGTON
Minor Works - Facility Preservation (30000027)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . (($26,000,000))
$34,175,000
((University of Washington Building Account--State . . . . . . . . . . . . $8,175,000))
Subtotal Appropriation . . . . . . . . . . . . $34,175,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $146,000,000
TOTAL . . . . . . . . . . . . $180,175,000
Sec. 5013 2009 c 497 s 5040 (uncodified) is amended to read as
follows:
FOR THE UNIVERSITY OF WASHINGTON
Minor Works - Program (30000110)
Appropriation:
((University of Washington Building Account--State . . . . . . . . . . . . $5,000,000))
State Building Construction Account--State . . . . . . . . . . . . $5,000,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $20,000,000
TOTAL . . . . . . . . . . . . $25,000,000
Sec. 5014 2009 c 497 s 5041 (uncodified) is amended to read as
follows:
FOR THE UNIVERSITY OF WASHINGTON
Preventative Facility Maintenance and Building System Repairs
(30000287)
Appropriation:
University of Washington Building
Account--State . . . . . . . . . . . . (($25,825,000))
$52,671,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $103,300,000
TOTAL . . . . . . . . . . . . (($129,125,000))
$155,971,000
Sec. 5015 2009 c 497 s 5042 (uncodified) is amended to read as
follows:
FOR THE UNIVERSITY OF WASHINGTON
Safe Campus (30000022)
Appropriation:
((University of Washington Building Account--State))
State Building Construction Account--State . . . . . . . . . . . . $8,000,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $8,000,000
Sec. 5016 2009 c 497 s 5055 (uncodified) is amended to read as
follows:
FOR THE WASHINGTON STATE UNIVERSITY
Minor Works - Preservation (30000065)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . (($16,128,000))
$24,516,000
Washington State University Building Account--
State . . . . . . . . . . . . (($10,000,000))
$1,612,000
Subtotal Appropriation . . . . . . . . . . . . $26,128,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $26,128,000
Sec. 5017 2009 c 497 s 5056 (uncodified) is amended to read as
follows:
FOR THE WASHINGTON STATE UNIVERSITY
Minor Works - Program (30000066)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . (($7,042,000))
$17,527,000
((Washington State University Building Account--))
State . . . . . . . . . . . . $10,485,000
Subtotal Appropriation . . . . . . . . . . . . $17,527,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $3,073,000
TOTAL . . . . . . . . . . . . $20,600,000
Sec. 5018 2009 c 497 s 5057 (uncodified) is amended to read as
follows:
FOR THE WASHINGTON STATE UNIVERSITY
Preventative Facility Maintenance and Building System Repairs
(30000287)
Appropriation:
Washington State University Building Account--
State . . . . . . . . . . . . (($10,115,000))
$28,988,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $40,460,000
TOTAL . . . . . . . . . . . . (($50,575,000))
$69,448,000
Sec. 5019 2009 c 497 s 5061 (uncodified) is amended to read as
follows:
FOR THE EASTERN WASHINGTON UNIVERSITY
Minor Works - Health, Safety, and Code Requirements (20081002)
((Reappropriation:))
Education Construction Account--State . . . . . . . . . . . . $1,500,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $1,343,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($2,500,000))
$2,657,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $4,000,000
Sec. 5020 2009 c 497 s 5065 (uncodified) is amended to read as
follows:
FOR THE EASTERN WASHINGTON UNIVERSITY
Preventive Maintenance and Building System Repairs (30000044)
Appropriation:
Eastern Washington University Capital Projects
Account--State . . . . . . . . . . . . (($2,217,000))
$4,960,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $8,868,000
TOTAL . . . . . . . . . . . . (($11,085,000))
$13,828,000
Sec. 5021 2009 c 497 s 5070 (uncodified) is amended to read as
follows:
FOR THE EASTERN WASHINGTON UNIVERSITY
Minor Works - Program (30000056)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $2,743,000
Eastern Washington University Capital Projects
Account--State . . . . . . . . . . . . (($3,306,000))
$563,000
Subtotal Appropriation . . . . . . . . . . . . $3,306,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $27,200,000
TOTAL . . . . . . . . . . . . $30,506,000
Sec. 5022 2009 c 497 s 5078 (uncodified) is amended to read as
follows:
FOR THE CENTRAL WASHINGTON UNIVERSITY
Minor Works - Health Safety and Code Requirements (30000002)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . (($950,000))
$1,642,000
Central Washington University Capital Projects
Account--State . . . . . . . . . . . . (($700,000))
$8,000
Subtotal Appropriation . . . . . . . . . . . . $1,650,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $12,000,000
TOTAL . . . . . . . . . . . . $13,650,000
Sec. 5023 2009 c 497 s 5079 (uncodified) is amended to read as
follows:
FOR THE CENTRAL WASHINGTON UNIVERSITY
Minor Works - Infrastructure Preservation (30000009)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . (($690,000))
$2,740,000
((Central Washington University Capital Projects))
Account--State . . . . . . . . . . . . $2,050,000
Subtotal Appropriation . . . . . . . . . . . . $2,740,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $12,000,000
TOTAL . . . . . . . . . . . . $14,740,000
Sec. 5024 2009 c 497 s 5081 (uncodified) is amended to read as
follows:
FOR THE CENTRAL WASHINGTON UNIVERSITY
Minor Works - Program (30000025)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . (($2,000,000))
$3,181,000
((Central Washington University Capital Projects))
Account--State . . . . . . . . . . . . $1,181,000
Subtotal Appropriation . . . . . . . . . . . . $3,181,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $28,000,000
TOTAL . . . . . . . . . . . . $31,181,000
Sec. 5025 2009 c 497 s 5083 (uncodified) is amended to read as
follows:
FOR THE CENTRAL WASHINGTON UNIVERSITY
Preventative Facility Maintenance and Building System Repairs
(30000287)
Appropriation:
Central Washington University Capital
Project Account--State . . . . . . . . . . . . (($2,422,000))
$6,345,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $9,688,000
TOTAL . . . . . . . . . . . . (($12,110,000))
$16,033,000
Sec. 5026 2009 c 497 s 5092 (uncodified) is amended to read as
follows:
FOR THE EVERGREEN STATE COLLEGE
Minor Works - Preservation (30000003)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . (($760,000))
$3,650,000
The Evergreen State College Capital Projects
Account--State . . . . . . . . . . . . (($3,765,000))
$875,000
Subtotal Appropriation . . . . . . . . . . . . $4,525,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $4,525,000
Sec. 5027 2009 c 497 s 5097 (uncodified) is amended to read as
follows:
FOR THE EVERGREEN STATE COLLEGE
Preventative Facility Maintenance and Building System Repairs
(30000287)
Appropriation:
The Evergreen State College Capital Projects
Account--State . . . . . . . . . . . . (($760,000))
$3,650,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . (($760,000))
$3,650,000
Sec. 5028 2009 c 497 s 5104 (uncodified) is amended to read as
follows:
FOR THE WESTERN WASHINGTON UNIVERSITY
Minor Works - Program (20082093)
Reappropriation:
State Building Construction Account--State . . . . . . . . . . . . $1,500,000
Western Washington University Capital Projects
Account--State . . . . . . . . . . . . (($2,500,000))
$1,163,000
Subtotal Reappropriation . . . . . . . . . . . . (($4,000,000))
$2,663,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $1,337,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $6,000,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $10,000,000
Sec. 5029 2009 c 497 s 5109 (uncodified) is amended to read as
follows:
FOR THE WESTERN WASHINGTON UNIVERSITY
Minor Works - Program (30000007)
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . (($5,248,000))
$8,248,000
((Western Washington University Capital Projects))
Account--State . . . . . . . . . . . . $3,000,000
Subtotal Appropriation . . . . . . . . . . . . $8,248,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $36,000,000
TOTAL . . . . . . . . . . . . $44,248,000
Sec. 5030 2009 c 497 s 5110 (uncodified) is amended to read as
follows:
FOR THE WESTERN WASHINGTON UNIVERSITY
Network Infrastructure/Switches (30000011)
Appropriation:
((Western Washington University Capital Projects))
Account--State . . . . . . . . . . . . $4,616,000
State Building Construction Account--State . . . . . . . . . . . . $4,616,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $4,616,000
Sec. 5031 2009 c 497 s 5111 (uncodified) is amended to read as
follows:
FOR THE WESTERN WASHINGTON UNIVERSITY
Preventative Facility Maintenance and Building System Repairs
(30000287)
Appropriation:
Western Washington University Capital Projects
Account--State . . . . . . . . . . . . (($3,614,000))
$12,567,000
Prior Biennia (Expenditures) . . . . . . . . . . . . $0
Future Biennia (Projected Costs) . . . . . . . . . . . . $14,456,000
TOTAL . . . . . . . . . . . . (($18,070,000))
$27,023,000
Sec. 5032 2009 c 497 s 5146 (uncodified) is amended to read as
follows:
FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM
Minor Works Preservation (Repairs and Minor Improvements)
(20061001)
((Reappropriation:))
Community/Technical College Capital Projects
Account--State . . . . . . . . . . . . $474,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $22,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($13,526,000))
$13,978,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $14,000,000
Sec. 5033 2009 c 497 s 5147 (uncodified) is amended to read as
follows:
FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM
Roof Repairs (20061010)
((Reappropriation:))
Community/Technical College Capital Projects
Account--State . . . . . . . . . . . . $500,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $208,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($8,340,000))
$8,632,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $8,840,000
Sec. 5034 2009 c 497 s 5148 (uncodified) is amended to read as
follows:
FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM
Facility Repairs (20061050)
((Reappropriation:))
Community and Technical College Capital Projects
Account--State . . . . . . . . . . . . $2,500,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $584,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($19,827,000))
$21,743,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $22,327,000
Sec. 5035 2009 c 497 s 5149 (uncodified) is amended to read as
follows:
FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM
Site Repairs (20061090)
((Reappropriation:))
Community and Technical College Capital Projects
Account--State . . . . . . . . . . . . $800,000
Appropriation:
State Building Construction Account--State . . . . . . . . . . . . $163,000
Prior Biennia (Expenditures) . . . . . . . . . . . . (($3,037,000))
$3,674,000
Future Biennia (Projected Costs) . . . . . . . . . . . . $0
TOTAL . . . . . . . . . . . . $3,837,000
Sec. 5036 2009 c 497 s 5170 (uncodified) is amended to read as
follows:
FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM
Minor Works - Preservation - Repairs and Minor Improvements
(20081001)
((Reappropriation:
Community/Technical College Capital Projects
Accou