E2SHB 1634 -
By Committee on Environment, Water & Energy
NOT ADOPTED 04/06/2011
Strike everything after the enacting clause and insert the following:
"Sec. 1 RCW 19.122.010 and 1984 c 144 s 1 are each amended to
read as follows:
((It is the intent of the legislature in enacting this chapter to
assign responsibilities for locating and keeping accurate records of
utility locations, protecting and repairing damage to existing
underground facilities, and protecting the public health and safety
from interruption in utility services caused by damage to existing
underground utility facilities.)) In this chapter, the underground
utility damage prevention act, the legislature intends to:
(1) Protect public health and safety and prevent disruption of
vital utility services by establishing a comprehensive damage
prevention program;
(2) Establish authority to enforce the act; and
(3) Assign responsibilities for locating underground facilities,
for providing accurate location records, and for repairing damage.
Sec. 2 RCW 19.122.020 and 2007 c 142 s 9 are each amended to read
as follows:
((Unless the context clearly requires otherwise,)) The definitions
in this section apply throughout this chapter((:)) unless the context
clearly requires otherwise.
(1) "Business day" means any day other than Saturday, Sunday, or a
legal local, state, or federal holiday.
(2) "Damage" includes the substantial weakening of structural or
lateral support of an underground facility, penetration, impairment, or
destruction of any underground protective coating, housing, or other
protective device, or the severance, partial or complete, of any
underground facility to the extent that the project owner or the
affected utility owner determines that repairs are required.
(3) "Emergency" means any condition constituting a clear and
present danger to life or property, or a customer service outage.
(4) "Excavation" and "excavate" means any operation including the
installation of signs, except for installation of official traffic
signs, in which earth, rock, or other material on or below the ground
is moved or otherwise displaced by any means((, except the tilling of
soil less than twelve inches in depth for agricultural purposes, or
road and ditch maintenance that does not change the original road grade
or ditch flowline)).
(5) "Excavation confirmation code" means a code or ticket issued by
the one-number locator service for the site where an excavation is
planned. The code must be accompanied by the date and time it was
issued.
(6) "Excavator" means any person who engages directly in
excavation.
(7) "Gas" means natural gas, flammable gas, or toxic or corrosive
gas.
(8) "Hazardous liquid" means:
(a) Petroleum, petroleum products, or anhydrous ammonia as those
terms are defined in 49 C.F.R. Part 195 as in effect on March 1, 1998;
((and))
(b) Carbon dioxide((. The utilities and transportation commission
may by rule incorporate by reference)); and
(c) Other substances designated as hazardous by the secretary of
transportation and incorporated by reference by the commission by rule.
(9) (("Identified facility" means any underground facility which is
indicated in the project plans as being located within the area of
proposed excavation.)) "Identified but unlocatable underground facility" means an
underground facility which has been identified but cannot be located
with reasonable accuracy.
(10)
(((11))) (10) "Locatable underground facility" means an underground
facility which can be field-marked with reasonable accuracy.
(((12))) (11) "Marking" means the use of stakes, paint, or other
clearly identifiable materials to show the field location of
underground facilities, in accordance with the current color code
standard of the American public works association. Markings shall
include identification letters indicating the specific type of the
underground facility.
(((13))) (12) "Notice" or "notify" means contact in person or by
telephone or other electronic methods that results in the receipt of a
valid excavation confirmation code.
(((14))) (13) "One-number locator service" means a service through
which a person can notify utilities and request field-marking of
underground facilities.
(((15) "Operator" means the individual conducting the excavation.)) (14) "Person" means an individual, partnership, franchise
holder, association, corporation, a state, a city, a county, or any
subdivision or instrumentality of a state, and its employees, agents,
or legal representatives.
(16)
(((17))) (15) "Pipeline" or "pipeline system" means all or parts of
a pipeline facility through which hazardous liquid or gas moves in
transportation, including, but not limited to, line pipe, valves, and
other appurtenances connected to line pipe, pumping units, fabricated
assemblies associated with pumping or compressor units, metering and
delivery stations and fabricated assemblies therein, and breakout
tanks. "Pipeline" or "pipeline system" does not include process or
transfer pipelines.
(((18))) (16) "Pipeline company" means a person or entity
constructing, owning, or operating a pipeline for transporting
hazardous liquid or gas. A pipeline company does not include: (a)
Distribution systems owned and operated under franchise for the sale,
delivery, or distribution of natural gas at retail; or (b) excavation
contractors or other contractors that contract with a pipeline company.
(((19))) (17) "Reasonable accuracy" means location within twenty-four inches of the outside dimensions of both sides of an underground
facility.
(((20))) (18) "Transfer pipeline" means a buried or aboveground
pipeline used to carry hazardous liquid between a tank vessel or
transmission pipeline and the first valve inside secondary containment
at the facility provided that any discharge on the facility side of
that first valve will not directly impact waters of the state. A
transfer pipeline includes valves, and other appurtenances connected to
the pipeline, pumping units, and fabricated assemblies associated with
pumping units. A transfer pipeline does not include process pipelines,
pipelines carrying ballast or bilge water, transmission pipelines, or
tank vessel or storage tanks.
(((21))) (19) "Transmission pipeline" means a pipeline that
transports hazardous liquid or gas within a storage field, or
transports hazardous liquid or gas from an interstate pipeline or
storage facility to a distribution main or a large volume hazardous
liquid or gas user, or operates at a hoop stress of twenty percent or
more of the specified minimum yield strength.
(((22))) (20) "Underground facility" means any item buried or
placed below ground for use in connection with the storage or
conveyance of water, sewage, electronic, telephonic or telegraphic
communications, cablevision, electric energy, petroleum products, gas,
gaseous vapors, hazardous liquids, or other substances and including
but not limited to pipes, sewers, conduits, cables, valves, lines,
wires, manholes, attachments, and those parts of poles or anchors below
ground. This definition does not include pipelines as defined in
subsection (((17))) (15) of this section, but does include distribution
systems owned and operated under franchise for the sale, delivery, or
distribution of natural gas at retail.
(21) "Bar hole" means a hole made in the soil or pavement with a
bar for the specific purpose of testing the subsurface atmosphere with
a combustible gas indicator.
(22) "Commission" means the utilities and transportation
commission.
(23) "Easement" or "utility easement" means a right held by a
facility operator to enter or cross with in-place assets, property
owned by another for the purpose of providing utility service, or
maintaining assets that provide utility service.
(24) "End user" means any utility customer or consumer of utility
services or commodities provided by a facility operator.
(25) "Equipment operator" means the individual conducting the
excavation.
(26) "Facility operator" means any person who owns underground
facilities or is in the business of supplying any utility service or
commodity for compensation. "Facility operator" does not include a
utility customer who owns a service lateral that terminates at a
facility operator's main utility line.
(27) "Large project" means a project that exceeds seven hundred
linear feet.
(28) "Service lateral" means an underground water, storm water, or
sewer facility located in a public right-of-way or utility easement
that connects an end user's building or property to a facility
operator's underground facility, and terminates beyond the public
right-of-way or utility easement.
(29) "Unlocatable underground facility" means, subject to the
provisions of RCW 19.122.030, an underground facility that cannot be
field-marked with reasonable accuracy using best available information
to designate the location of underground facilities. "Unlocatable
underground facility" includes, but is not limited to, service
laterals, storm drains, and nonconductive and nonmetallic underground
facilities that do not contain trace wires.
Sec. 3 RCW 19.122.027 and 2005 c 448 s 2 are each amended to read
as follows:
(1) The ((utilities and transportation commission shall cause to be
established)) commission must establish a single statewide toll-free
telephone number to be used for referring excavators to the appropriate
one-number locator service.
(2) The ((utilities and transportation)) commission, in
consultation with the Washington utilities coordinating council,
((shall)) must establish minimum standards and best management
practices for one-number locator services.
(3) One-number locator services ((shall)) must be operated by
nongovernmental agencies.
(4) All facility operators within a one-number locator service area
must subscribe to the service.
(5) Failure to subscribe to the one-number locator service
constitutes willful intent to avoid compliance with this chapter.
Sec. 4 RCW 19.122.030 and 2000 c 191 s 17 are each amended to
read as follows:
(1)(a) Unless exempted under section 5 of this act, before
commencing any excavation, ((excluding agriculture tilling less than
twelve inches in depth, the excavator shall)) an excavator must mark
the boundary of the excavation area with white paint applied on the
ground of the worksite, then provide notice of the scheduled
commencement of excavation to all ((owners of underground facilities))
facility operators through a one-number locator service.
(b) If boundary marking required by (a) of this subsection is
infeasible, an excavator must communicate directly with affected
facility operators to ensure that the boundary of the excavation area
is accurately identified.
(2) ((All owners of underground facilities within a one-number
locator service area shall subscribe to the service. One-number
locator service rates for cable television companies will be based on
the amount of their underground facilities. If no one-number locator
service is available, notice shall be provided individually to those
owners of underground facilities known to or suspected of having
underground facilities within the area of proposed excavation. The
notice shall be communicated to the owners of underground facilities))
An excavator must provide the notice required by subsection (1) of this
section to a one-number locator service not less than two business days
((or)) and not more than ten business days before the scheduled date
for commencement of excavation, unless otherwise agreed ((by the
parties)) to by the excavator and facility operators. If an excavator
intends to work at multiple sites or at a large project, the excavator
must take reasonable steps to confer with facility operators to enable
them to locate underground facilities reasonably in advance of the
start of excavation for each phase of the work.
(3) Upon receipt of the notice provided for in ((this section, the
owner of the underground facility shall)) subsection (1) of this
section, a facility operator must, with respect to:
(a) The operator's locatable underground facilities, provide the
excavator with reasonably accurate information ((as to its locatable
underground facilities by surface-marking the location of the
facilities. If there are)) by surface-marking their location;
(b) The operator's unlocatable or identified but unlocatable
underground facilities, ((the owner of such facilities shall)) provide
the excavator with ((the best)) available information as to their
((locations. The owner of the underground facility providing the
information shall respond)) location; and
(c) Service laterals, designate their presence or location, if the
service laterals:
(i) Connect end users to the facility operator's main utility line;
and
(ii) Are within a public right-of-way or utility easement and the
boundary of the excavation area identified under subsection (1) of this
section.
(4)(a) A facility operator must provide information to an excavator
pursuant to subsection (3) of this section no later than two business
days after the receipt of the notice or before the excavation time, at
the option of the ((owner)) facility operator, unless otherwise agreed
by the parties. ((Excavators shall not excavate until all known
facilities have been marked. Once marked by the owner of the
underground facility, the excavator is responsible for maintaining the
markings. Excavators shall have the right to receive compensation from
the owner of the underground facility for costs incurred if the owner
of the underground facility does not locate its facilities in
accordance with this section.))
(4) The owner of the underground facility shall have
(b) A facility operator may comply with subsection (3)(b) and (c)
of this section in a manner that includes, but is not limited to, any
one of the following methods:
(i) Placing within a proposed excavation area a triangular green
mark at the main utility line pointing at an address in question,
indicating the presence of an unlocatable or identified but unlocatable
underground facility, including a service lateral;
(ii) Arranging to meet an excavator at a worksite to provide
available information about the location of service laterals; or
(iii) Providing available information through other means if
agreeable to both the excavator and facility operator.
(c) A facility operator's good faith attempt to designate the
presence or location of a service lateral using available information:
(i) Is deemed to comply with the requirements of this section; and
(ii) Does not constitute any assertion of ownership or operation of
the service lateral by the facility operator.
(d) An end user is responsible for determining the location of
service laterals on their property or service laterals that they own.
Nothing in this section may be interpreted to require an end user to
subscribe to a one-number locator service or to locate a service
lateral within a right-of-way or easement.
(5) An excavator must not excavate until all known facility
operators have marked or provided information regarding underground
facilities as provided in this section.
(6)(a) Once marked by a facility operator, an excavator is
responsible for maintaining the accuracy of the facility operator's
markings of underground utilities for the lesser of:
(i) Forty-five calendar days from the date that the excavator
provided notice to the one-number locator service pursuant to
subsection (1) of this section; or
(ii) The duration of the project.
(b) An excavator that makes repeated requests for location of
underground utilities due to its failure to maintain the accuracy of a
facility operator's markings of underground facilities as required by
this subsection (6) may be charged for services provided.
(c) A facility operator's markings of underground utilities expire
forty-five calendar days from the date that the excavator provided
notice to the one-number locator service pursuant to subsection (1) of
this section. For excavation occurring after that date, an excavator
must provide additional notice to a one-number locator service pursuant
to subsection (1) of this section.
(7) An excavator has the right to receive compensation from a
facility operator for costs incurred if the facility operator does not
locate its underground facilities in accordance with the requirements
specified in this section.
(8) A facility operator has the right to receive compensation for
costs incurred in responding to excavation notices given less than two
business days prior to the excavation from the excavator.
(((5) An owner of underground facilities is not required to
indicate the presence of existing service laterals or appurtenances if
the presence of existing service laterals or appurtenances on the site
of the construction project can be determined from the presence of
other visible facilities, such as buildings, manholes, or meter and
junction boxes on or adjacent to the construction site.)) (9) Emergency excavations are exempt from the time
requirements for notification provided in this section. With respect
to creating bar holes twelve inches or more in depth during emergency
leak investigations, excavators must take reasonable measures to
eliminate electrical arc hazards.
(6)
(((7) If the excavator, while performing the contract,)) (10) If an
excavator discovers underground facilities ((which)) that are not
identified, the excavator ((shall)) must cease excavating in the
vicinity of the ((facility)) underground facilities and immediately
notify the ((owner or)) facility operator ((of such facilities,)) or
the one-number locator service. If an excavator discovers identified
but unlocatable underground facilities, the excavator must notify the
facility operator. Upon notification by the one-number locator service
or an excavator, a facility operator must allow for location of the
uncovered portion of an underground facility identified by the
excavator, and may accept location information from the excavator for
marking of the underground facility.
NEW SECTION. Sec. 5 A new section is added to chapter 19.122 RCW
to read as follows:
(1) The requirements specified in RCW 19.122.030 do not apply to
any of the following described activities:
(a) An excavation of less than twelve inches in depth on private
noncommercial property, if the excavation is performed by the person or
an employee of the person who owns or occupies the property on which
the excavation is being performed;
(b) The tilling of soil less than twenty inches in depth for
agricultural purposes;
(c) Road maintenance activities involving excavation less than six
inches in depth below the original road grade and ditch maintenance
activities involving excavation less than six inches in depth below the
original ditch flowline or alteration of the original ditch horizontal
alignment;
(d) The creation of bar holes with hand-operated equipment during
emergency leak investigations;
(e) The creation of bar holes less than twelve inches in depth; or
(f) Construction, operation, or maintenance activities by an
irrigation district on rights-of-way, easements, or facilities owned by
the federal bureau of reclamation in federal reclamation projects.
(2) Any activity described under subsection (1) of this section is
subject to the requirements specified in RCW 19.122.050.
Sec. 6 RCW 19.122.033 and 2000 c 191 s 18 are each amended to
read as follows:
(1) Before commencing any excavation, ((excluding agricultural
tilling less than twelve inches in depth,)) an excavator ((shall)) must
notify pipeline companies of the scheduled commencement of excavation
through a one-number locator service in the same manner as is required
for notifying ((owners of underground facilities)) facility operators
of excavation work under RCW 19.122.030. Pipeline companies ((shall))
have the same rights and responsibilities as ((owners of underground
facilities)) facility operators under RCW 19.122.030 regarding
excavation work. Excavators have the same rights and responsibilities
under this section as they have under RCW 19.122.030.
(2) Project owners, excavators, and pipeline companies have the
same rights and responsibilities relating to excavation near pipelines
that they have for excavation near underground facilities as provided
in RCW 19.122.040.
(3) The state or any of its political subdivisions undertaking or
permitting construction or excavation activity under chapter 19.27 RCW
within one hundred feet, or greater distance if defined by local
ordinance, of a right-of-way or easement that contains a transmission
pipeline must:
(a) Notify the transmission pipeline company of the proposed
construction activity before such a permit is approved; or
(b) Require consultation between the person proposing the
construction activity and the transmission pipeline company as a
condition of receiving the permit.
Sec. 7 RCW 19.122.035 and 2000 c 191 s 19 are each amended to
read as follows:
(1) After a pipeline company has been notified by an excavator
pursuant to RCW 19.122.033 that excavation work will uncover any
portion of the pipeline, the pipeline company shall ensure that the
pipeline section in the vicinity of the excavation is examined for
damage prior to being reburied.
(2) Immediately upon receiving information of third-party damage to
a hazardous liquid pipeline, the company that operates the pipeline
shall terminate the flow of hazardous liquid in that pipeline until it
has visually inspected the pipeline. After visual inspection, the
((operator of the hazardous liquid)) pipeline company shall determine
whether the damaged pipeline section should be replaced or repaired, or
whether it is safe to resume pipeline operation. Immediately upon
receiving information of third-party damage to a gas pipeline, the
((company that operates the)) pipeline company shall conduct a visual
inspection of the pipeline to determine whether the flow of gas through
that pipeline should be terminated, and whether the damaged pipeline
should be replaced or repaired. A record of the pipeline company's
inspection report and test results shall be provided to the ((utilities
and transportation)) commission consistent with reporting requirements
under 49 C.F.R. 195 Subpart B.
(3) Pipeline companies shall immediately notify local first
responders and the department of any reportable release of a hazardous
liquid from a pipeline. Pipeline companies shall immediately notify
local first responders and the commission of any blowing gas leak from
a gas pipeline that has ignited or represents a probable hazard to
persons or property. Pipeline companies shall take all appropriate
steps to ensure the public safety in the event of a release of
hazardous liquid or gas under this subsection.
(4) No damaged pipeline may be buried until it is repaired or
relocated. The pipeline company shall arrange for repairs or
relocation of a damaged pipeline as soon as is practical or may permit
the excavator to do necessary repairs or relocation at a mutually
acceptable price.
Sec. 8 RCW 19.122.040 and 1984 c 144 s 4 are each amended to read
as follows:
(1) Project owners shall indicate in bid or contract documents the
existence of underground facilities known by the project owner to be
located within the proposed area of excavation. The following ((shall
be)) are deemed changed or differing site conditions:
(a) An underground facility not identified as required by this
chapter or other provision of law; ((and)) or
(b) An underground facility not located, as required by this
chapter or other provision of law, by the project owner, facility
operator, or excavator if the project owner or excavator is also a
((utility)) facility operator.
(2) An excavator shall use reasonable care to avoid damaging
underground facilities. An excavator ((shall)) must:
(a) Determine the precise location of underground facilities which
have been marked;
(b) Plan the excavation to avoid damage to or minimize interference
with underground facilities in and near the excavation area; and
(c) Provide such support for underground facilities in and near the
construction area, including during backfill operations, as may be
reasonably necessary for the protection of such facilities.
(3) If an underground facility is damaged and such damage is the
consequence of the failure to fulfill an obligation under this chapter,
the party failing to perform that obligation ((shall be)) is liable for
any damages. Any clause in an excavation contract which attempts to
allocate liability, or requires indemnification to shift the economic
consequences of liability, different from the provisions of this
chapter is against public policy and unenforceable. Nothing in this
chapter prevents the parties to an excavation contract from contracting
with respect to the allocation of risk for changed or differing site
conditions.
(4) In any action brought under this section, the prevailing party
is entitled to reasonable attorneys' fees.
Sec. 9 RCW 19.122.050 and 1984 c 144 s 5 are each amended to read
as follows:
(1) An excavator who, in the course of excavation, contacts or
damages an underground facility shall notify the ((utility owning or
operating such)) facility operator and the one-number locator service,
and report the damage as required under section 20 of this act. If the
damage causes an emergency condition, the excavator causing the damage
shall also alert the appropriate local public safety agencies and take
all appropriate steps to ensure the public safety. No damaged
underground facility may be buried until it is repaired or relocated.
(2) ((The owner of the underground facilities damaged)) A facility
operator notified in accordance with subsection (1) of this section
shall arrange for repairs or relocation as soon as is practical or may
permit the excavator to do necessary repairs or relocation at a
mutually acceptable price.
Sec. 10 RCW 19.122.055 and 2005 c 448 s 3 are each amended to
read as follows:
(1)(a) Any excavator who fails to notify the one-number locator
service and causes damage to a hazardous liquid or gas pipeline is
subject to a civil penalty of not more than ten thousand dollars for
each violation.
(b) The civil penalty in this subsection may also be imposed on any
excavator who violates RCW 19.122.090.
(2) All civil penalties recovered under this section ((shall)) must
be deposited into the ((pipeline safety)) damage prevention account
created in ((RCW 81.88.050)) section 12 of this act.
Sec. 11 RCW 19.122.070 and 2005 c 448 s 4 are each amended to
read as follows:
(1) Any person who violates any provision of this chapter not
amounting to a violation of RCW 19.122.055((, and which violation
results in damage to underground facilities,)) is subject to a civil
penalty of not more than one thousand dollars for ((each violation.
All penalties recovered in such actions shall be deposited in the
general fund)) an initial violation, and not more than five thousand
dollars for each subsequent violation within a three-year period. All
penalties recovered in such actions must be used for education and
training of excavators and facility operators regarding best practices
and compliance with this chapter. All penalties recovered in such
actions must be deposited in the damage prevention account created in
section 12 of this act.
(2) Any excavator who willfully or maliciously damages a field-marked underground facility ((shall be)) is liable for treble the costs
incurred in repairing or relocating the facility. In those cases in
which an excavator fails to notify known underground facility
((owners)) operators or the one-number locator service, any damage to
the underground facility ((shall be)) is deemed willful and malicious
and ((shall be)) is subject to treble damages for costs incurred in
repairing or relocating the facility.
(3) This chapter does not affect any civil remedies for personal
injury or for property damage, including that to underground
facilities, nor does this chapter create any new civil remedies for
such damage.
NEW SECTION. Sec. 12 A new section is added to chapter 19.122
RCW to read as follows:
The damage prevention account is created in the custody of the
state treasurer. All receipts from moneys directed by law or the
commission to be deposited to the account must be deposited in the
account. Expenditures from the account may be used only for purposes
designated in section 13 of this act. Only the commission or the
commission's designee may authorize expenditures from the account. The
account is subject to allotment procedures under chapter 43.88 RCW.
NEW SECTION. Sec. 13 A new section is added to chapter 19.122
RCW to read as follows:
The commission may use money deposited in the damage prevention
account created in section 12 of this act to:
(1) Develop and disseminate educational programming designed to
improve worker and public safety relating to excavation and underground
facilities; and
(2) Provide grants to persons who have developed educational
programming that the commission and the safety committee created
pursuant to section 18 of this act deem appropriate for improving
worker and public safety relating to excavation and underground
facilities.
Sec. 14 RCW 19.122.075 and 2000 c 191 s 23 are each amended to
read as follows:
Any person who willfully damages or removes a permanent marking
used to identify an underground facility or pipeline, or a temporary
marking prior to its intended use, is subject to a civil penalty of not
more than one thousand dollars for ((each act)) an initial violation,
and not more than five thousand dollars for each subsequent violation
within a three-year period.
Sec. 15 RCW 19.122.080 and 1984 c 144 s 8 are each amended to
read as follows:
The notification and marking provisions of this chapter may be
waived for one or more designated persons by ((an underground)) a
facility ((owner)) operator with respect to all or part of that
((underground)) facility ((owner's)) operator's own underground
facilities.
Sec. 16 RCW 19.122.100 and 2005 c 448 s 6 are each amended to
read as follows:
If charged with a violation of RCW 19.122.090, an equipment
operator ((will be)) is deemed to have established an affirmative
defense to such charges if:
(1) The equipment operator was provided a valid excavation
confirmation code;
(2) The excavation was performed in an emergency situation;
(3) The equipment operator was provided a false confirmation code
by an identifiable third party; or
(4) Notice of the excavation was not required under this chapter.
Sec. 17 RCW 19.122.110 and 2005 c 448 s 7 are each amended to
read as follows:
Any person who intentionally provides an equipment operator with a
false excavation confirmation code is guilty of a misdemeanor.
NEW SECTION. Sec. 18 A new section is added to chapter 19.122
RCW to read as follows:
(1) The commission must contract with a statewide, nonprofit entity
whose purpose is to reduce damages to underground and above ground
facilities, promote safe excavation practices, and review complaints of
alleged violations of this chapter. The contract does not obligate
funding by the commission for activities performed by the nonprofit
entity or the safety committee under this section, and therefore is
exempt under RCW 39.29.040(1) from the requirements of chapter 39.29
RCW.
(2) The contracting entity must create a safety committee to:
(a) Advise the commission and other state agencies, the
legislature, and local government agencies and officials on best
practices and training to prevent damage to underground utilities, and
policies to enhance worker and public safety and protection of
underground facilities; and
(b) Review complaints alleging violations of this chapter involving
practices related to underground facilities.
(3) The safety committee consists of thirteen members, who must be
nominated by represented groups and appointed by the contracting entity
to staggered three-year terms. The safety committee must include
representatives of:
(a) Local governments;
(b) An investor-owned natural gas utility subject to regulation
under Titles 80 and 81 RCW;
(c) Contractors;
(d) Excavators;
(e) An investor-owned electric utility subject to regulation under
Title 80 RCW;
(f) A consumer-owned utility;
(g) A pipeline company;
(h) The insurance industry;
(i) The commission; and
(j) A telecommunications company.
(4) The safety committee must meet at least once every three
months.
(5) The safety committee may review complaints of alleged
violations of this chapter involving practices related to underground
facilities. Any person may bring a complaint to the safety committee
regarding an alleged violation.
(6) To review complaints of alleged violations, the safety
committee must appoint at least three and no more than five members as
a review committee. The review committee must represent a balance of
excavators, facility operators, and the insurance industry, and must
include at least one representative of a pipeline company or natural
gas distribution company.
(7) Before reviewing a complaint alleging a violation of this
chapter, the review committee must notify the person making the
complaint and the alleged violator of its review and the opportunity to
participate.
(8) The safety committee may provide written notification to the
commission, with supporting documentation, that a person has likely
committed a violation of this chapter, and recommend remedial action
that may include a penalty amount, training, or education to improve
public safety, or some combination of penalty, training, and education.
(9) This section expires December 31, 2020.
NEW SECTION. Sec. 19 A new section is added to chapter 19.122
RCW to read as follows:
(1) The commission may enforce the civil penalties authorized in
RCW 19.122.070 or 19.122.075 when it receives written notification from
the safety committee created under section 18 of this act indicating
that a violation of this chapter has likely been committed by a person
subject to regulation by the commission, or involving the underground
facilities of such a person.
(2) If the commission receives written notification from the safety
committee pursuant to section 18 of this act that a violation of this
chapter has likely been committed by a person who is not subject to
regulation by the commission, and in which the underground facility
involved is also not subject to regulation by the commission, the
commission may refer the matter to the attorney general for enforcement
of a civil penalty under RCW 19.122.070 or 19.122.075. The commission
must provide funding for such enforcement. However, any costs and fees
recovered by the attorney general pursuant to subsection (3) of this
section must be deposited by the commission in the fund that paid those
costs and fees.
(3) In a matter referred to it by the commission pursuant to
subsection (2) of this section, the attorney general may bring an
action to enforce the penalties authorized in RCW 19.122.070 or
19.122.075. In any action brought under this subsection, the court may
award the state all costs of investigation and trial, including a
reasonable attorneys' fee fixed by the court.
(4) This section expires December 31, 2020.
NEW SECTION. Sec. 20 A new section is added to chapter 19.122
RCW to read as follows:
(1) Facility operators and excavators who observe or cause damage
to an underground facility must report the event to the commission.
(2)(a) Facility operators and excavators who observe or cause
damage must report whenever the event results in scrapes, gouges,
cracks, dents, or other visible damage to a utility, pipeline, or cable
casing or other external protection of any underground facility.
(b) A nonpipeline facility operator conducting excavations, or a
subcontractor conducting excavations on the facility operator's behalf,
that strikes the facility operator's own underground facilities is not
required to report that damage event to the commission.
(3) Reports must be made to the commission's office of pipeline
safety within forty-five days of the event, or sooner if required by
law using the commission's virtual private damage information reporting
tool (DIRT) report form or other similar form if it reports:
(a) The name of the person submitting the report and whether the
person is an excavator, a representative of a one-number locator
service, or a facility operator;
(b) The date and time of the damage event;
(c) The address where the damage occurred;
(d) The type of right-of-way, where the damage occurred, including
but not limited to city street, state highway, or private easement;
(e) The type of underground facility damaged, including but not
limited to pipes, transmission pipelines, distribution lines, sewers,
conduits, cables, valves, lines, wires, manholes, attachments, or parts
of poles or anchors below ground;
(f) The type of utility service or commodity the underground
facility stores or conveys, including but not limited to electronic,
telephonic or telegraphic communications, water, sewage, cablevision,
electric energy, petroleum products, gas, gaseous vapors, hazardous
liquids, or other substances;
(g) The type of excavator, including but not limited to contractors
or facility operators;
(h) The excavation equipment used, including but not limited to
augers, bulldozers, backhoes, or hand tools;
(i) The type of work being performed, including but not limited to
drainage, grading, or landscaping;
(j) Whether a one-number locator service was notified before
excavation commenced, and, if so, the excavation confirmation code
provided by the one-number locator service;
(k) The person who located the underground facility, and their
employer;
(l) Whether underground facility marks were visible in the proposed
excavation area before excavation commenced;
(m) Whether underground facilities were marked correctly;
(n) Whether an excavator experienced interruption of work as a
result of the damage;
(o) A description of the damage; and
(p) Whether the damage caused an interruption of underground
facility service.
(4) The commission must use reported data to evaluate the
effectiveness of the damage prevention program.
NEW SECTION. Sec. 21 A new section is added to chapter 19.122
RCW to read as follows:
(1) The commission may investigate and enforce violations of RCW
19.122.055, 19.122.075, and 19.122.090 relating to pipeline facilities
without initial referral to the safety committee created under section
18 of this act.
(2) If the commission's investigation of notifications received
pursuant to section 19 of this act or subsection (1) of this section
substantiates violations of this chapter, the commission may impose
penalties authorized by RCW 19.122.055, 19.122.070, 19.122.075, and
19.122.090, and require training, education, or any combination of
these remedies.
(3) With respect to referrals from the safety committee, the
commission must consider any recommendation by the committee regarding
enforcement and remedial actions involving an alleged violator.
(4) In an action to impose penalties initiated by the commission
under subsection (1) or (2) of this section, the penalty is due and
payable when the person incurring the penalty receives a notice of
penalty in writing from the commission describing the violation and
advising the person that the penalty is due. The person incurring the
penalty has fifteen days from the date it receives the notice of
penalty to file with the commission a request for mitigation or a
request for a hearing, and the commission must include this time limit
information in the notice of penalty. After receiving a timely request
for mitigation or hearing, the commission must suspend collection of
the penalty until it issues a final order concerning the penalty or
mitigation of that penalty. A person aggrieved by the commission's
final order may seek judicial review, subject to provisions of the
administrative procedure act, chapter 34.05 RCW.
(5) If a penalty imposed by the commission is not paid, the
attorney general may, on the commission's behalf, file a civil action
in superior court to collect the penalty.
(6) This section expires December 31, 2020.
NEW SECTION. Sec. 22 A new section is added to chapter 19.122
RCW to read as follows:
All penalties collected pursuant to section 21 of this act must be
deposited in the damage prevention account created in section 12 of
this act.
NEW SECTION. Sec. 23 RCW 19.122.060 (Exemption from notice and
marking requirements for property owners) and 1984 c 144 s 6 are each
repealed.
NEW SECTION. Sec. 24 A new section is added to chapter 19.122
RCW to read as follows:
Nothing in this act may be construed to classify a consumer-owned
utility, as defined in RCW 19.27A.140, to be under the authority of the
commission.
NEW SECTION. Sec. 25 A new section is added to chapter 19.122
RCW to read as follows:
This act may be known and cited as the underground utility damage
prevention act.
NEW SECTION. Sec. 26 This act takes effect January 1, 2013."
E2SHB 1634 -
By Committee on Environment, Water & Energy
NOT ADOPTED 04/06/2011
On page 1, line 1 of the title, after "utilities;" strike the remainder of the title and insert "amending RCW 19.122.010, 19.122.020, 19.122.027, 19.122.030, 19.122.033, 19.122.035, 19.122.040, 19.122.050, 19.122.055, 19.122.070, 19.122.075, 19.122.080, 19.122.100, and 19.122.110; adding new sections to chapter 19.122 RCW; repealing RCW 19.122.060; prescribing penalties; providing an effective date; and providing expiration dates."
EFFECT: Several technical corrections and clarifications are
included, in addition to the following changes.
Intent (Section 1). The intent section is clarified, and provides
that the chapter is the "underground utility damage prevention act," as
further specified in Section 25.
Definitions (Section 2). The definition of "excavation" and
"excavate" is revised to provide that installation of official traffic
signs is excluded. Other existing and proposed new exceptions to the
definition of "excavation" and "excavate" are transferred to a new
section consolidating exemptions from excavator requirements (Section
5). An obsolete definition of "identified facility" is deleted. A
definition of "easement" or "utility easement" is added. Proposed
definitions of "end user," "facility operator," "service lateral," and
"unlocatable underground facility" are revised. Proposed definitions
of "sewer lateral," "sewer system owner or operator," and "utility
coordinating council" are deleted.
Duties of Excavators and Facility Operators (Section 4). Facility
operator duties are revised to provide that facility operators: (1)
Must provide "information" rather than "best available information"
regarding location of their facilities if they are unlocatable or
identified but unlocatable; (2) must designate service laterals only if
they connect end users to facility operators' main utility lines and
are within a right-of-way or utility easement and boundary of an
identified excavation area; and (3) may comply with the foregoing
requirements through several methods, including placing marks
indicating the presence of underground facilities, arranging to meet
excavators at worksites to provide information, or by providing
information through other means agreeable to both excavators and
utility operators.
Exemptions from Excavator Duties (Section 5). Exemptions from
excavator duties are consolidated in a new section. Existing
exemptions for: (1) Tilling of soil for agricultural purposes is
changed from less than 12 inches in depth to less than 20 inches in
depth; and (2) road and ditch maintenance activities not involving
excavation below original road grade or original ditch flowline or
alteration of original ditch horizontal alignment are changed to allow
excavation up to 6 inches. An exemption is added for certain
activities by an irrigation district on rights-of-way, easements, or
facilities owned by the federal bureau of reclamation in federal
reclamation projects. Activity exempted from excavator duties in this
section is nonetheless subject to a requirement that excavators report
damage they cause to underground facilities.
Damage Prevention Account (Section 10). Civil penalties on
excavators damaging hazardous liquid or gas pipelines will be deposited
in the new damage prevention account created by the legislation, rather
than the existing pipeline safety account.
Safety Committee (Section 18). Language is added providing that
the UTC's contract with a nonprofit entity creating the Safety
Committee does not obligate UTC funding, and therefore is exempt from
competitive contracting requirements. The process for selecting
members is clarified. The Safety Committee will include
representatives of investor-owned natural gas utilities and insurance
industry, in addition to other stakeholders. Before reviewing a
complaint, a review committee appointed by the Safety Committee must
notify the complainant and alleged violator of its review and the
opportunity to participate. The Safety Committee may provide written
notification to the UTC that a person has likely committed a violation,
and recommend remedial action.
Enforcement Authority (Sections 19 and 21). Provisions for
enforcement of alleged violations not involving UTC-regulated persons
or facilities are added; the Attorney General will provide such
enforcement. The UTC's authority to enforce violations involving
damage to UTC-regulated pipelines is clarified.
Repeal of Exemption (Section 23). A provision exempting excavation
less than 12 inches deep on private noncommercial property from
excavator duties if performed by the property owner or occupier, or an
employee, is repealed, and the exemption is incorporated in Section 5.
UTC Jurisdiction (Section 24). A provision is added clarifying
that nothing in the act may be construed to classify a consumer-owned
utility to be under the authority of the UTC.
Short Title (Section 25). A provision is added providing that the
act may be known and cited as the underground utility damage prevention
act.