EHB 2469 -
By Committee on Environment
ADOPTED 02/29/2012
Strike everything after the enacting clause and insert the following:
"Sec. 1 RCW 90.58.355 and 1994 c 257 s 20 are each amended to
read as follows:
((The procedural requirements of this chapter)) Requirements to
obtain a substantial development permit, conditional use permit, or
variance shall not apply to any person:
(1) Conducting a remedial action at a facility pursuant to a
consent decree, order, or agreed order issued pursuant to chapter
70.105D RCW, or to the department of ecology when it conducts a
remedial action under chapter 70.105D RCW. The department ((of ecology
shall)) must ensure compliance with the substantive requirements of
this chapter through the consent decree, order, or agreed order issued
pursuant to chapter 70.105D RCW, or during the department-conducted
remedial action, through the procedures developed by the department
pursuant to RCW 70.105D.090; or
(2) Installing site improvements for storm water treatment in an
existing boatyard facility to meet requirements of a national pollutant
discharge elimination system storm water general permit. The
department must ensure compliance with the substantive requirements of
this chapter through the review of engineering reports, site plans, and
other documents related to the installation of boatyard storm water
treatment facilities."
EHB 2469 -
By Committee on Environment
ADOPTED 02/29/2012
On page 1, line 1 of the title, after "systems;" strike the remainder of the title and insert "and amending RCW 90.58.355."
EFFECT: Amends language in existing law regarding exemption from "procedural requirements of this chapter" to refer to the permits defined in the shoreline management act, including substantial development, conditional use, and variance permits.