FINAL BILL REPORT

SHB 1422

This analysis was prepared by non-partisan legislative staff for the use of legislative members in their deliberations. This analysis is not a part of the legislation nor does it constitute a statement of legislative intent.

C 217 L 11

Synopsis as Enacted

Brief Description: Authorizing a forest biomass to aviation fuel demonstration project.

Sponsors: House Committee on Technology, Energy & Communications (originally sponsored by Representatives Stanford, Orcutt, Chandler, Warnick, Van De Wege, Green, Smith, Jacks, Blake, Sullivan, McCoy, Kretz, Tharinger, Ryu, Short, Sells, Lytton, Liias, Frockt, Moscoso, Billig, Probst, Rolfes, Dunshee, Maxwell, Upthegrove and Kenney; by request of Commissioner of Public Lands).

House Committee on Technology, Energy & Communications

Senate Committee on Natural Resources & Marine Waters

Background:

State Trust Lands.

The Department of Natural Resources (DNR) manages 5.6 million acres of forest, range, agricultural, aquatic, and commercial lands for the people of Washington. The DNR manages approximately 2.3 million acres of forested state trust lands.

Under a mix of authorities, including state law, the state Constitution, and the state's federal Enabling Act, these state trust lands are held by the state for specified trust beneficiaries. In total, there are 18 trust beneficiaries that derive some level of economic benefit from the management of these trust lands. The beneficiaries include common schools, the state universities, community colleges, counties, and the state's capital budget.

Biomass Energy Pilot Projects.

In 2009 legislation was enacted authorizing the DNR to implement biomass energy pilot projects in eastern and western Washington. The purpose of the pilot projects is to demonstrate that removing biomass feedstock in ecologically sustainable ways to produce energy (liquid fuels or heat and electricity) may provide income for forest landowners while improving forest health, creating rural jobs, reducing wildfires and greenhouse gas emissions, and aiding in the production of renewable energy.

In January 2010 the following four biomass projects were selected:

Long-term Biomass Supply Contracts.

In 2010 the DNR was authorized by statute to enter into long-term contracts to supply forest biomass from DNR-managed lands. Under this authorization, the DNR may: (1) conduct separate sales within valuable materials contracts; (2) enter into long-term competitive contracts of five years which may be renewed up to three times; (3) carry out direct sales contracts without public auction; (4) offer 15-year contracts for entities making a qualifying capital investment of $50 million; and (5) lease state lands for the purpose of integrated biomass supply area and facility siting.

Forest Biomass Supply Assessment.

Before entering into long-term contracts for forest biomass from state-managed lands, the DNR must first assess the available supply of biomass in the contract area. In 2010 the DNR received a grant from the United States Forest Service to perform a statewide forest biomass supply assessment. The DNR selected the University of Washington's School of Forestry to conduct the assessment.

The Forest Biomass Supply Assessment will assess forest biomass availability and sustainability throughout Washington on all forest land ownerships, including state‑owned lands. The Forest Biomass Supply Assessment is scheduled for completion by August 2011.

For these purposes, "forest biomass" means the by-products of prescribed or permitted forest management practices; forest protection treatments; or forest health treatments. "Forest biomass" does not include wood pieces that have been treated with chemical preservatives such as: creosote, pentachlorophenol, or copper-chrome-arsenic; wood from old growth forests, except wood removed for forest health treatments; or municipal solid waste.

Summary:

The Department of Natural Resources (DNR) and the Department of Commerce are directed to cooperate and consult with the University of Washington (UW) and Washington State University in their development of forest biomass to aviation fuel by:

The DNR must report to the Governor and the Legislature:

A percentage of the income, proportionate to the percent of state resources, derived from the investment of state resources in the development of patents, copyrights, proprietary processes, or licenses developed by the forest biomass to aviation fuel demonstration project must be deposited in the State General Fund.

Votes on Final Passage:

House

93

1

Senate

47

0

(Senate amended)

House

96

0

(House concurred)

Effective:

July 22, 2011