Washington State

House of Representatives

Office of Program Research

BILL

ANALYSIS

Local Government Committee

HB 1660

This analysis was prepared by non-partisan legislative staff for the use of legislative members in their deliberations. This analysis is not a part of the legislation nor does it constitute a statement of legislative intent.

Brief Description: Authorizing multijurisdiction flood control zones.

Sponsors: Representatives Takko, Hunt and Tharinger.

Brief Summary of Bill

  • Authorizes the creation of multijurisdiction flood control zone districts (multijurisdiction zones) to exercise the same powers as flood control zone districts over watersheds spanning two or more counties or reservations of federally-recognized Indian tribes.

  • Provides for the formation, governance and operations of a multijurisdiction zone.

Hearing Date: 2/8/11

Staff: Heather Emery (786-7136).

Background:

Flood Control Zone District.

A flood control zone district (zone) is a special purpose district designed to undertake, operate, or maintain flood control projects or storm water control projects that are of special benefit to specified areas of a county. A zone must be located in a single county and may include any area within a county that is not included in another zone. Alternatively, a zone may be countywide and incorporate the boundaries of any and all watersheds not specifically organized into flood control zone districts. Countywide zones may be divided into subzones, each of which operates like a zone.

Formation of a Zone.

A zone may be formed by action of the legislative body of the county, or by petition by 25 percent of voters in a zone. If the zone is formed by petition, the county legislative body must incorporate the terms of the petition in a resolution within 40 days of receipt of the petition.

Governance and Operations of Zones.

Members of the board of county commissioners are ex officio supervisors of zones. If a zone has more than 2,000 inhabitants, an election to elect three zone supervisors other than county commissioners may be held.

Because each zone is located in a single county, existing county officials may handle zone administration. The county engineer, who is charged with administering the affairs of a zone, is authorized to appoint deputies, engage employees, and organize the zone into administrative departments. The county engineer is also authorized to approve all plans for specific projects and to supervise work whenever certain state grant funds are used in a flood control maintenance project. The county treasurer, who serves as zone treasurer, is responsible for establishing a zone flood control fund into which revenues available to a zone are deposited. Zone supervisors adopt a zone budget at the same time the county budget is prepared.

Powers and Duties of a Zone.

The powers and authority of zones are far-reaching. Among other functions, zones may:

Zone Finances.

A flood control zone district is an independent taxing authority subject to the 1 percent levy lid. A zone may receive funding from a variety of sources, including property tax receipts; rates, charges, and assessments; and debt proceeds.

A zone may impose annual, nonvoter-approved regular property tax levies of up to 50 cents per $1,000 of assessed value. With 60 percent voter approval, a zone may also impose excess levies for general purposes and to retire general obligation bonds issued for capital purposes.

A zone may issue three kinds of bonds: nonvoter approved general obligation bonds, voter approved general obligation bonds, and revenue bonds. Without voter approval, a zone may incur general indebtedness and issue general obligation bonds of up to three-eighths of 1 percent of the value of taxable property in the zone. With voter approval, a zone may authorize the issuance of general obligation bonds not to exceed an amount, together with any outstanding general obligation indebtedness, equal to three-fourths of 1 percent of the value of taxable property within the zone or participating zones. A zone may also issue a variety of revenue bonds that are payable from a specified fund.

Summary of Bill:

When a watershed spans territory in two or more counties or reservations of federally recognized Indian tribes, formation of a multijurisdiction zone vested with the same powers and immunities as a flood control zone district is authorized.

Formation of a Multijurisdiction Flood Control Zone District.

Unlike a flood control zone district, creation of a multijurisdiction zone may not be initiated by petition. The legislative authorities of participating counties and tribes may create a multijurisdiction zone by execution of a formation agreement, which must specify:

Additionally, the formation agreement may specify:

A multijursidiction zones is formed if the legislative authority of each participating county, after holding a public hearing, approves the formation agreement, and if participating tribes take appropriate tribal action to approve the agreement.

Governance and Operations of a Multijurisdiction Zone.

The roles and responsibilities of the multijurisdiction zone's supervisors, treasurer and engineer are set forth in the formation agreement.

Powers and Duties of a Multijurisdiction Zone.

A multijurisdiction zone is authorized to exercise the same powers and duties as a zone. Additionally, a multijurisdiction zone or zone may contract with any government entity with which it is authorized to cooperate, including federally-recognized Indian tribes, and it may convey property, with or without compensation, to the state, another local government entity, or a federally recognized Indian tribe.

Multijurisdiction Zone Finances.

A multijurisdiction zone is authorized to impose the taxes and levies and to incur indebtedness to the same extent as a zone. However, if the boundaries of a multijurisdiction zone overlap with the boundaries of a zone, the combined ad valorum property tax may not exceed 50 cents per $1,000 of assessed value of land, unless other impacted taxing districts agree to release their share of the authorized levy.

Boundary Review Boards.

While flood control zone districts are subject to the jurisdiction of a Boundary Review Board, a multijurisdiction zone is not.

Appropriation: None.

Fiscal Note: Not requested.

Effective Date: The bill takes effect 90 days after adjournment of the session in which the bill is passed.