BILL REQ. #: S-3289.1
State of Washington | 62nd Legislature | 2012 Regular Session |
Read first time 01/19/12. Referred to Committee on Energy, Natural Resources & Marine Waters.
AN ACT Relating to modifying the definition of "lowest reasonable cost" for the purposes of chapter 19.280 RCW, electric utility resource plans; and amending RCW 19.280.020.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF WASHINGTON:
Sec. 1 RCW 19.280.020 and 2009 c 565 s 19 are each amended to
read as follows:
The definitions in this section apply throughout this chapter
unless the context clearly requires otherwise.
(1) "Commission" means the utilities and transportation commission.
(2) "Conservation and efficiency resources" means any reduction in
electric power consumption that results from increases in the
efficiency of energy use, production, transmission, or distribution.
(3) "Consumer-owned utility" includes a municipal electric utility
formed under Title 35 RCW, a public utility district formed under Title
54 RCW, an irrigation district formed under chapter 87.03 RCW, a
cooperative formed under chapter 23.86 RCW, a mutual corporation or
association formed under chapter 24.06 RCW, a port district formed
under Title 53 RCW, or a water-sewer district formed under Title 57
RCW, that is engaged in the business of distributing electricity to one
or more retail electric customers in the state.
(4) "Department" means the department of commerce.
(5) "Electric utility" means a consumer-owned or investor-owned
utility.
(6) "Full requirements customer" means an electric utility that
relies on the Bonneville power administration for all power needed to
supply its total load requirement other than that served by
nondispatchable generating resources totaling no more than six
megawatts or renewable resources.
(7) "Governing body" means the elected board of directors, city
council, commissioners, or board of any consumer-owned utility.
(8) "High efficiency cogeneration" means the sequential production
of electricity and useful thermal energy from a common fuel source,
where, under normal operating conditions, the facility has a useful
thermal energy output of no less than thirty-three percent of the total
energy output.
(9) "Integrated resource plan" means an analysis describing the mix
of generating resources and conservation and efficiency resources that
will meet current and projected needs at the lowest reasonable cost to
the utility and its ratepayers and that complies with the requirements
specified in RCW 19.280.030(1).
(10) "Investor-owned utility" means a corporation owned by
investors that meets the definition in RCW 80.04.010 and is engaged in
distributing electricity to more than one retail electric customer in
the state.
(11) "Lowest reasonable cost" means the lowest cost mix of
generating resources and conservation and efficiency resources
determined through a detailed and consistent analysis of a wide range
of commercially available resources. At a minimum, this analysis must
consider the following: (a) Resource cost((,)); (b) market-volatility
risks((,)); (c) demand-side resource uncertainties((,)); (d) resource
dispatchability((,)); (e) resource effect on system operation((,)); (f)
the risks imposed on the utility and its ratepayers((,)); (g) public
policies regarding resource preference adopted by Washington state or
the federal government((, and)); (h) the cost of risks associated with
environmental effects including emissions of carbon dioxide; and (i)
the economic benefits of locally sited generation that accrue to the
utility's ratepayers based on an assessment using the version of the
office of financial management's "Washington state input-output model"
identified by the office of financial management by rule, consistent
with the purpose of this subsection.
(12) "Plan" means either an "integrated resource plan" or a
"resource plan."
(13) "Renewable resources" means electricity generation facilities
fueled by: (a) Water; (b) wind; (c) solar energy; (d) geothermal
energy; (e) landfill gas; (f) biomass energy utilizing animal waste,
solid organic fuels from wood, forest, or field residues or dedicated
energy crops that do not include wood pieces that have been treated
with chemical preservatives such as creosote, pentachlorophenol, or
copper-chrome-arsenic; (g) by-products of pulping or wood manufacturing
processes, including but not limited to bark, wood chips, sawdust, and
lignin in spent pulping liquors; (h) ocean thermal, wave, or tidal
power; or (i) gas from sewage treatment facilities.
(14) "Resource plan" means an assessment that estimates electricity
loads and resources over a defined period of time and complies with the
requirements in RCW 19.280.030(2).