BILL REQ. #: H-1701.1
State of Washington | 63rd Legislature | 2013 Regular Session |
Read first time 03/06/13. Referred to Committee on Transportation.
AN ACT Relating to permitting certain transportation projects; adding a new chapter to Title 47 RCW; and declaring an emergency.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF WASHINGTON:
NEW SECTION. Sec. 1 It is the intent of the legislature to
achieve transportation permit reform that expedites the delivery of
transportation projects through a streamlined approach to environmental
permit decision making. To optimize the limited resources available
for transportation system improvements and environmental protection,
state regulatory and natural resources agencies, public and private
sector interests, Indian tribes, and the department of transportation
should work cooperatively to establish common goals, minimize project
delays, develop consistency in the application of environmental
standards, maximize environmental benefits through coordinated
investment strategies, and eliminate duplicative processes through
assigned responsibilities of selected permit drafting and compliance
activities between state and federal agencies. Therefore, a
streamlined permitting process is created for large transportation
projects.
NEW SECTION. Sec. 2 The department must use the following
permitting process for any transportation project of at least five
million dollars:
(1) Step 1: Conceptual description. The department must identify
project purposes, the approximate project location or alternative
locations, and the federal, state, and local agencies that might have
the authority to review and approve the project or portions of it at
any such locations, and must compile a preliminary interagency
communication list identifying agencies that may be interested in the
proposed project and, where known, contact persons in such agencies.
If the department is going to proceed with step 2 or to abandon the
project, it must complete step 1 by: (a) Providing a summary of the
outcome to all agencies on the list; and (b) making the summary
available to the public.
(2) Step 2: Early involvement of other agencies. (a) At any time
after completing step 1, the department must provide notice to all
agencies on the interagency communication list and the public. Within
thirty days, or a longer time if specified by the department, each
state, local, and federal agency must be encouraged to identify:
(i) A primary contact person to coordinate future communications
with the department and other interested agencies regarding the
project, or indicate that the agency has no interest in the project and
need not remain on the interagency communication list;
(ii) The agency's role with respect to the proposed project;
(iii) Additional alternative locations the department should
consider and the roles the agency would expect to have with the project
at those locations;
(iv) Other agencies the agency believes should be added to the list
for the project; and
(v) Other information the agency requests the department to
consider.
(b) After all state and local agencies on the interagency
communication list have responded, or at least ten days after
expiration of the specified response time, the department must complete
step 2 by: (i) Proposing one or more conceptual designs for the
project at a proposed location and any alternative locations then being
considered; (ii) providing a summary of the results of step 2,
including a statement that the department considers step 2 to be
complete or complete except for specified issues remaining to be
resolved with specified agencies, to all agencies on the interagency
communication list; and (iii) making the summary available to the
public.
(3) Step 3: Identify environmental reviews, permits, and other
approvals, application procedures, and decision standards. (a) At any
time after completing step 2, the department must initiate step 3 by
providing notice to all agencies on the interagency communication list
and the public. This notice may include a threshold determination on
whether an environmental impact statement or supplemental environmental
impact statement will be prepared or an environmental checklist and a
request for comments on what steps should be taken to comply with
chapter 43.21C RCW. Within thirty days, or a longer time if specified
by the department, each state, local, and federal agency must be
encouraged to identify:
(i) The procedures under which the agency expects environmental
reviews of the project to occur;
(ii) All permits and other approvals the agency might require for
the project at each alternative location and conceptual design;
(iii) What is needed for the department to file a complete
application for each permit or other approval;
(iv) The laws, rules, regulations, ordinances, and policies the
agency would administer with respect to the project at each alternative
location and conceptual design; and
(v) Other information the agency requests the department to
consider in deciding whether, when, where, or how to proceed with the
project.
(b) After all state and local agencies on the interagency
communication list have responded, or at least ten days after
expiration of the specified response time, the department must complete
step 3 by:
(i) Compiling a list of all environmental reviews, permits, and
other approvals it believes are needed for the project under each
alternative being considered;
(ii) Providing all agencies on the interagency communication list
a copy of the list compiled under (b)(i) of this subsection and a
summary of the other results of step 3, including a statement that the
department considers step 3 to be complete or complete except for
specified issues remaining to be resolved with specified agencies; and
(iii) Making the list compiled under (b)(i) of this subsection and
summary available to the public.
(c) The list compiled under (b)(i) of this subsection and summary
provided under (b)(ii) of this subsection are presumed to accurately
identify all environmental reviews, permits, and other approvals needed
for each alternative described, what is required for applications to be
considered complete, and the standards under which applications will be
reviewed and approved, unless an aggrieved agency or person files
objections within thirty days after the list and summary are
distributed.
(4) Step 4: Tentative selection of preferred alternative. (a) At
any time after completing step 3, the department must initiate step 4
by providing notice to all agencies on the interagency communication
list and the public. This notice may be accompanied by a scoping
notice for an environmental impact statement or supplemental
environmental impact statement or, if available, a draft environmental
impact statement or supplemental environmental impact statement. This
notice also may be accompanied by the department's preliminary analysis
of the advantages and disadvantages of each identified alternative, or
other information that may be helpful to other interested agencies and
the public in identifying advantages and disadvantages. Within
fourteen days, or a longer time if specified by the department, each
state, local, and federal agency must be encouraged to identify:
(i) For each identified alternative, the specific features the
agency considers significant with respect to the agency's role in
environmental reviews, permits, or other approvals for the project; the
reasons these features are significant; and any concerns the agency may
have about the alternative because of potential adverse impacts of
these features on resources or social policies within the agency's
jurisdiction;
(ii) For each feature for which the agency raises concerns,
recommendations on how the potential adverse impacts could be avoided,
minimized, and mitigated;
(iii) For each feature for which the agency raises concerns, an
assessment of the relative ranking of each alternative with respect to
whether and to what extent these concerns apply;
(iv) Recommendations the agency may have as to which alternatives
should be retained or dropped from further consideration, and ways in
which alternatives might be modified or combined to address the
agency's concerns, recognizing that final decisions can be made only
through the applicable environmental review, permit, and other approval
processes and that the agency making them is not bound with respect to
any future decisions it may make regarding the project; and
(v) Other information the agency requests the department to
consider in deciding whether, when, where, or how to proceed with the
project.
(b) After all state and local agencies on the interagency
communication list have responded, or at least ten days after
expiration of the specified response time, the department must complete
step 4 by:
(i) Selecting a preferred alternative for purposes of all
environmental reviews, permits, and other approvals needed for the
project;
(ii) Providing all agencies on the interagency communication list
a description of the preferred alternative and summary of the other
results of step 4, including a statement that the department considers
step 4 to be complete or complete except for specified issues remaining
to be resolved with specified agencies; and
(iii) Making the preferred alternative and summary available to the
public. The preferred alternative must be identified in all
environmental reviews, permits, and other approvals needed for the
project.
(5) Step 5: Completing environmental reviews and applications for
permits and other approvals. (a) At any time after completing step 4,
the department must initiate step 5 by providing notice to all agencies
on the interagency communication list and the public. A draft
environmental impact statement or supplemental environmental impact
statement, the department's draft plans and specifications for the
project, and draft applications for some or all permits and other
approvals may be provided with the notice or when they subsequently
become available. Within thirty days, or a longer time if specified by
the department, each state, local, and federal agency must be
encouraged to identify:
(i) All concerns the agency previously raised regarding the
alternative, and other alternatives still under consideration, that
have not been resolved to the agency's satisfaction;
(ii) Additional concerns the agency may have, particularly concerns
resulting from additional information about the project location and
design, and other new information received since the completion of step
4;
(iii) Additional environmental reviews, permits, or other approvals
needed for the preferred alternative because of changes in laws, rules,
regulations, or policies or changes in the project location or design
since these issues were last reviewed in step 3 or 4;
(iv) Changes in applicable requirements for complete applications
for permits or other approvals under the agency's jurisdiction since
these issues were last reviewed in step 3 or 4;
(v) Other changes in applicable laws, rules, regulations,
ordinances, or policies administered by the agency since these issues
were last reviewed in step 3 or 4; and
(vi) Whether a draft application proposed by the department for a
permit or other approval from the agency is complete and, if not, what
additional information or other changes are needed for the draft
application to be complete.
(b) When all state and local agencies on the interagency
communication list have responded, or at least ten days after
expiration of the specified response time, the department must complete
step 5 by:
(i) Completing some or all environmental review processes and draft
application forms for permits and other approvals that it reasonably
believes to be complete;
(ii) Providing all agencies on the interagency communication list
with environmental review and application documents and a summary of
the other results of step 5, including a statement that the department
considers step 5 to be complete or complete except for specified issues
remaining to be resolved with specified agencies; and
(iii) Making the completed environmental review documents and
summary available to the public. The preferred alternative must be
identified in all environmental reviews, permits, and other approvals
needed for the project.
(c) However, if an interested agency or aggrieved person files
objections within fourteen days after the preferred alternative and
summary are distributed, the objections must be addressed in subsequent
environmental reviews and agency decisions regarding the project.
(6) Step 6: Completing the environmental review, permit, and other
approval processes. (a) At any time after completing step 5, the
department must initiate step 6 by providing notice to all agencies on
the interagency communication list and the public and filing
applications for some or all permits and other approvals needed for the
project. Within thirty days, or a longer time if specified by the
department, each state, local, and federal agency must be encouraged
to:
(i) Acknowledge receipt of draft environmental review documents
provided to the agency and to provide comments on them;
(ii) Acknowledge receipt of final environmental review documents
and determine that they are adequate for purposes of their roles
regarding the project or specify what additional information or changes
are needed for them to be considered adequate;
(iii) Acknowledge receipt of each application filed with the agency
and determine that the application is complete or specify what
additional information or changes are needed for the application to be
considered complete;
(iv) Acknowledge that the applications submitted to the agency will
be processed under the laws, rules, regulations, ordinances, and
policies previously identified under steps 3, 4, and 5 or specify what
changes have occurred in the governing standards that were in effect on
the date a complete application was filed and, as a result, apply to
the project;
(v) Identify the significant steps necessary for the agency to
reach a final decision on applications and the estimated time needed
for each step; and
(vi) Identify ways its decision-making process might be made more
efficient and effective through additional coordination with other
agencies, with any recommendations for such methods as joint
solicitation and review of public comments and jointly conducting
public hearings.
(b) It is recognized that step 6 may require an iterative process
with several drafts of various environmental review documents and
applications being considered and revised, and that changes in project
location or design resulting from the permit decisions of one agency
may require revising applications or even reopening permit decisions of
other agencies. All state and local agencies are expected, and federal
agencies are encouraged, to communicate and cooperate to minimize the
number of iterations required and make the process as efficient and
effective as possible. Unless significant new information is obtained,
decisions made under step 6 should not be reopened except at the
request of the department, and the most recent information available
under steps 3, 4, and 5 should be presumed accurate until significant
new information becomes available.
(c) If all environmental reviews have not been completed and all
permits and other approvals obtained within forty-five days after step
6 are initiated, the department, by providing notice to all agencies on
the interagency communication list and the public, may set a deadline
for completing reviews and decisions. At any time after the deadline,
the department may terminate the coordination process of this section
as to some or all of the reviews and decisions that are still not
completed.
NEW SECTION. Sec. 3 (1) This section establishes procedures for
city, town, and county governments to participate in the processes
identified in this chapter to provide for coordinated,
multijurisdictional environmental review and permitting decisions for
transportation projects of at least five million dollars.
(2) Each city, town, and county, within its boundaries is located
or partially located one or more projects identified in subsection (1)
of this section, must elect whether or not to participate in
coordinated processes for environmental review and permitting of those
projects as required in this chapter. If the city, town, or county
elects to participate, it may do so as either a participating entity or
as an assigning entity.
(a) If a city, town, or county elects to be considered as a
participating entity, the department must include a representative
designated by the city, town, or county in the coordinated review of
the project. The department must compensate the jurisdiction for
technical support required for participation in the process. The
jurisdiction is also eligible for reimbursement for permit fees set by
local ordinances and other agreed upon costs associated with the
issuance of project permits.
(b) For the purposes of expediting the permit process, a city,
town, or county may elect to assign its permit responsibilities under
chapter 39.34 RCW to the department simultaneously with its
notification to the department as specified in subsection (4) of this
section. The city, town, or county electing to assign its
responsibilities must enter into an agreement with the department to
define the local permit requirements that must be met. Permits issued
under the agreement are presumed to at least meet local environmental
permit requirements. A city, town, or county choosing to use this
option is eligible for a permit fee set by local ordinances associated
with the issuance of the project permits.
(3) If the city, town, or county elects not to participate in the
coordinated processes for transportation projects of at least five
million dollars, the department must issue the locally required
permits, when allowable. The department must comply with all city,
town, and county ordinances, and the department permit approval is
presumed to at least meet the local environmental review and permit
requirements.
(4) Any city, town, or county must notify the department within
sixty days of receipt of the department's notification of project
designation, as to whether it elects to be considered as a
participating entity or an assigning entity, or elects not to
participate in the coordinated process provided in this chapter.
(5) The department must review and evaluate the process by which
local governments review and approve transportation projects of at
least five million dollars, and must provide recommendations to the
legislature, by January 1, 2014, to improve the coordination of the
local process with state and federal reviews as part of the reports
required under this chapter.
(6) A city, town, or county is not liable for decisions made by the
department that result in a failure to comply with city, town, or
county ordinances except as provided in the interlocal agreements, and
the department must defend and answer to any actions or complaints
challenging the validity of permits issued under this section.
NEW SECTION. Sec. 4 The legislature finds that an essential
component of streamlined permit decision making is the ability of the
department to demonstrate the capacity to meet environmental
responsibilities. Therefore, the legislature directs that:
(1) Qualified environmental staff within the department must lead
the development of all environmental documentation associated with
department projects and permit activities in accordance with the
department's project delivery tools;
(2) The department must conduct special prebid meetings for
projects that are environmentally complex. In addition, the department
must review environmental considerations related to these projects
during the preconstruction meeting held with the contractor who is
awarded the bid;
(3) Environmental staff at the department must conduct field
inspections to ensure that project activities are performed under
permit conditions. These inspectors:
(a) May issue stop work orders when compliance with permit
standards are not being met; and
(b) For this portion of their job duties, are accountable to the
director of the department of ecology; and
(4) Failure to comply with a stop work order may result in civil
penalties being assessed against the department and individuals
involved. Willful violation of a stop work notice issued by the
department is subject to civil penalties assessed on the agency as well
as the individuals involved. Persistent violations by the department
may result in loss of permit drafting and program management
responsibilities.
NEW SECTION. Sec. 5 The legislature expects the department to
continue its efforts to improve training and compliance. The
department must:
(1) Provide training in environmental procedures and permit
requirements for those responsible for project delivery activities;
(2) Require wetland mitigation sites to be designed by a qualified
interdisciplinary team that meets training requirements developed by
the department in consultation with the department of ecology.
Environmental mitigation site improvements must have oversight by
environmental staff;
(3) Develop an environmental compliance data system to track all
permit conditions;
(4) Report all noncompliance activities to applicable agencies of
jurisdiction along with a remedy plan;
(5) Fund the departments of ecology, natural resources, and fish
and wildlife operating under their permit-granting authority to conduct
audits of the department's permit drafting and compliance activities.
The department of ecology must collate the audits in an annual report
to the legislature, beginning January 1, 2014;
(6) Seek federal funding for dedicated technical staff at federal
permit decision-making agencies and for state costs associated with
implementation of this chapter;
(7) Fund dedicated technical staff at federal permit decision-making entities, as appropriate, and the departments of ecology,
natural resources, commerce, and fish and wildlife to implement the
requirements of this chapter; and
(8) Fund a technical specialist at the northwest Indian fisheries
commission and the Columbia river inter-tribal fish commission for the
purpose of implementing this chapter.
NEW SECTION. Sec. 6 If any provision of this act or its
application to any person or circumstance is held invalid, the
remainder of the act or the application of the provision to other
persons or circumstances is not affected.
NEW SECTION. Sec. 7 This act is necessary for the immediate
preservation of the public peace, health, or safety, or support of the
state government and its existing public institutions, and takes effect
immediately.
NEW SECTION. Sec. 8 Sections 1 through 7 of this act constitute
a new chapter in Title