    On page 2, beginning on line 6, strike all of subsection 2 and insert the following:

 

    "(2) At the time the public entity establishes the low responsive bidder, the list of subcontractors who will perform work on the building envelope must be provided to the public entity. The public entity may void the contract if the prime contract bidder fails to provide the list of the names of these subcontractors, names itself to perform the work, or names two or more subcontractors to perform the same work."

 

 

    EFFECT:  Just the list of subcontractors working on the building envelope will be provided at the time of award instead of all subcontractors.

 

 