On page 54, after line 33, insert the following:
"NEW SECTION.  Sec. 1055. FOR THE DEPARTMENT OF ENTERPRISE SERVICES
Capitol Lake Long-Term Management Planning (30000740)
The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely to advance the preferred alternative of the environmental impact statement (2022). At a minimum, the department shall:
(1) Make tangible progress toward the next phase of design and permitting;
(2) Advance the memorandum of understanding for governance and funding of a restored estuary to an interlocal agreement that will govern long-term management of the restored estuary; and
(3) Initiate grant funding applications for design and permitting.
Appropriation:
State Building Construction AccountState
. . . .
$3,000,000
Prior Biennia (Expenditures)
. . . .
$6,849,000
Future Biennia (Projected Costs)
. . . .
$225,000,000
TOTAL
. . . .
$234,849,000"
Renumber the remaining sections consecutively and correct any internal references accordingly.
EFFECT: Adds a new project to advance the estuary alternative of the 2022 Final Environmental Impact Statement for Capitol Lake.
FISCAL EFFECT: $3,000,000 state bonds.