Washington State Energy Strategy.
The Department of Commerce (Commerce) was directed in 2019 to update the State Energy Strategy, and to align the strategy with the requirements of the Energy Independence Act, the Clean Energy Transformation Act, and the state's greenhouse gas emissions reduction targets. Commerce published the State Energy Strategy in 2021.
A successful State Energy Strategy must balance three goals:
Nine principles guide the development and implementation of the State Energy Strategy in achieving these goals. One of these nine principles directs the state to reduce dependence on fossil fuel energy sources through improved efficiency and development of cleaner energy sources, such as bioenergy, low carbon energy sources, natural gas, and leveraging the indigenous resources of the state to produce clean energy.
Interagency Clean Energy Siting Coordinating Council.
Enacted legislation in 2023 created an Interagency Clean Energy Siting Coordinating Council (Coordinating Council), to be cochaired and costaffed by the Department of Ecology (Ecology) and Commerce. The Coordinating Council's responsibilities are enumerated and include:
The Coordinating Council must provide an annual report to the Governor and the Legislature beginning October 1, 2024. The report must summarize progress on clean energy project siting and permitting, areas of additional work, resource needs, recommendations for future nonproject EISs for categories of clean energy projects, and any needed policy changes to help the state achieve its clean energy goals.
Nonproject Environmental Impact Statements.
The State Environmental Policy Act (SEPA) establishes a review process for state and local governments to identify environmental impacts that may result from governmental decisions, such as the issuance of permits or the adoption of land use plans. The SEPA environmental review process involves a project proponent or the lead agency completing an environmental checklist to identify and evaluate probable environmental impacts. If an initial review of the checklist and supporting documents results in a determination that the government decision has a probable significant adverse environmental impact, known as a threshold determination, the proposal must undergo a more comprehensive environmental analysis in the form of an EIS. If the SEPA review process identifies significant adverse environmental impacts, the lead agency may deny a government decision or may require mitigation for identified environmental impacts.
The SEPA rules lay out the specifics for how a nonproject EIS may be conducted and then used for a specific project. A nonproject EIS is essentially an upfront, preproject environmental analysis of the types of environmental impacts that could be expected from a type of governmental decision. Under the rules, when a lead agency prepares an EIS on a nonproject proposal, the lead agency has less detailed information available on environmental impacts and the environmental impacts of any subsequent project proposals that may follow the EIS. The lead agency's nonproject EIS discusses impacts and alternatives in the level of detail appropriate to the scope of the proposal and the level of planning for the proposal. If a specific geographic area is the focus of a nonproject EIS, site specific analyses are not required but may be included for specific areas of concern. After the approval of a nonproject EIS by the lead agency, when a project is proposed that is consistent with the nonproject EIS, the EIS for the project proposal must focus on the impacts and alternatives, including mitigation measures, that are specific to the subsequent project and that were not analyzed in the nonproject EIS. The SEPA procedures allow for the adoption and use of portions of the nonproject EIS in a subsequent project-level SEPA review.
Legislation enacted in 2023 directed Ecology to prepare three nonproject EISs? one for solar energy projects, one for onshore wind energy projects, and one for green electrolytic or renewable hydrogen projects? and the Energy Facility Site Evaluation Council to prepare nonproject EISs for certain electrical transmission facilities.
Projects of Statewide Significance.
A project may apply to Commerce for designation as a Project of Statewide Significance, which provides for voluntary expedited permitting treatment by local government jurisdictions in partnership with the Governor's Office for Regulatory Innovation and Assistance.
The following are designated as Projects of Statewide Significance, with specifications:
Additional criteria for Projects of Statewide Significance include providing significant economic benefit to the local or state economy and alignment with the state's comprehensive plan for economic development.
The State Energy Strategy.
The state must ensure that the pursuit of cleaner energy sources actively includes and supports innovative, emerging, and promising clean energy technologies, such as fusion energy, which is energy from the merger of atomic nuclei.
Interagency Clean Energy Siting Coordinating Council.
In its annual report, the Interagency Clean Energy Siting Coordinating Council must include a recommendation of whether and when fusion energy could be an appropriate category for nonproject EISs.
Projects of Statewide Significance.
Fusion energy facilities and facilities that manufacture or assemble component parts for fusion energy facilities are added to the list of Projects of Statewide Significance.