1210-S.E2 AMS WAGO S5966.1
2ESHB 1210 - S AMD 886
By Senator Wagoner
NOT ADOPTED 03/06/2026
On page 3, beginning on line 10, after "include" strike ":
(A) Verification" and insert "verification"
On page 3, beginning on line 13, after "met;" strike all material through "project;" on line 15
Correct any internal references accordingly.
EFFECT: Removes the requirement for the owner of the clean energy transformation business facility to submit a copy of the executed community workforce agreement or project labor agreement used for the construction of the project after the completion of the project.