SENATE BILL REPORT
SB 6076
As of January 19, 2026
Title: An act relating to streamlining consumer-owned utility procurement requirements for clean energy generation, energy storage, transmission, and distribution projects until the 2045 carbon free compliance date under the clean energy transformation act.
Brief Description: Streamlining consumer-owned utility procurement requirements for clean energy generation, energy storage, transmission, and distribution projects.
Sponsors: Senators Goehner, Salomon, Lovelett and SaldaƱa.
Brief History:
Committee Activity: Environment, Energy & Technology: 1/20/26.
Brief Summary of Bill
  • Increases public works contract thresholds for public utility districts (PUDs) for certain energy projects until January 1, 2045. 
  • Allows electronic submission of bids under the public works procurement process for PUDs.
  • Expands the range of items that a PUD may purchase through the preapproved vendor list process. 
  • Exempts competitive bidding for municipalities under certain conditions relating to energy generation and transmission until January 1, 2045. 
SENATE COMMITTEE ON ENVIRONMENT, ENERGY & TECHNOLOGY
Staff: Kimberly Cushing (786-7421)
Background:

Public Utility Districts. A public utility district (PUD) is a type of special purpose district authorized for the purpose of generating and distributing electricity, providing water and sewer services, and providing telecommunications services.

 

Contracts for Purchasing or Work. A PUD must contract for: 

  •  any items of similar materials, equipment, or supplies estimated to cost more than $30,000;
  •  any items of similar materials, equipment, or supplies estimated to cost more than $12,000, if purchased within a single calendar month; and  
  •  any work ordered by a district commission estimated to cost more than $150,000 if more than a single craft or trade is involved, or $75,500 if only a single craft or trade is involved with the public works project.

 

Contracts are not required for work accepted as an industry practice under prudent utility management. Prudent utility management means performing work with regularly employed personnel, using material of a worth not exceeding $300,000 in value. This limit does not include the value of individual items of equipment. 

 

Competitive Bidding. Before awarding a contract for public works projects or for purchasing materials, equipment, or supplies, a PUD must publish advance notice to invite sealed proposals, then publicly open and read them and award the contract to the lowest responsible bidder.

 

As an alternative to formal competitive bidding to secure contracts, state law allows certain agencies to use vendor lists up to a certain dollar amount established in statute. The agency must advertise the existence of each vendor list at least twice a year in a newspaper of general circulation and solicit names for the list. To make a purchase using the vendor list, an agency should secure quotes from at least three of the vendors on the list, if possible, and award the contract to the lowest responsible bidder. 

 

Competitive bidding requirements may be waived by the municipality’s governing body for purchases from sole source suppliers, purchases involving special facilities or market conditions, purchases in the event of an emergency, purchases of insurance or bonds, and public works in the event of an emergency.

Summary of Bill:

Until January 1, 2045, a separate category of work is created under PUD procurement law for electric generation facilities fueled by non-emitting or renewable resources, energy storage, or transmission or distribution projects (PUD energy projects). 

 

Contracts for Work. For PUD energy project work without a contract:

  • the maximum dollar amount increases from $75,500 or less—single craft, or $150,000 or less—multiple craft, to $500,000 or less; and
  • performed by regularly employed personnel, the maximum dollar amount of the work increases from $300,000 to $1 million or less. 

 

Competitive Bidding Requirements for Public Utility Districts. PUDs with a purchasing department may receive electronic bids as well as hard copy bids. 

 

When a PUD opens bids it may award the contract to the lowest responsive, as well as responsible, bidder based on the filed plans and specifications. 

 

The maximum amount a contract may be awarded for is increased from 15 percent to 25 percent in excess of the estimated cost of the materials or work. 

 

For contracts to purchase any item or items of the same kind of materials, equipment or supplies for PUD energy projects, in the amount of $50,000 or more but less than $250,000 per calendar month, exclusive of sales tax, PUDs may use the vendor list process. A PUD may waive the deposit or bid bond in securing bid quotations. 

 

Competitive Bidding Requirements for Municipalities. Competitive bid requirements may be waived for municipalities until January 1, 2045, for purchases: 

  • involving any type of electric generating plants and facilities including, but not limited to, nuclear and other thermal power generating plants and facilities, renewable energy facilities, energy storage facilities, and transmission facilities; and
  • relating to energy generation, storage, transmission, or distribution facilities if the governing body determines that the expedited procurement action is: 
    1. for proprietary or specialized technologies with no comparable alternatives; 
    2. necessary to ensure compliance with electrical reliability standards; and 
    3. to prevent threats to grid reliability.
Appropriation: None.
Fiscal Note: Requested on January 16, 2026.
Creates Committee/Commission/Task Force that includes Legislative members: No.
Effective Date: Ninety days after adjournment of session in which bill is passed.