PDFRCW 80.50.071

Council to receive applicationsPayment of costs incurred by the councilNotification requirements.

(1) The council shall receive all applications for energy facility site certification. Each applicant shall pay actual costs incurred by the council in processing an application.
(a) Each applicant shall, at the time of application submission, pay to the council for deposit into the energy facility site evaluation council account created in RCW 80.50.390 an amount up to fifty thousand dollars, or such greater amount as specified by the council after consultation with the applicant. The council shall charge costs against the deposit if the applicant withdraws its application and has not reimbursed the council for all actual expenditures incurred in considering the application.
(b) The council may commission its own independent consultant study to measure the consequences of the proposed energy facility on the environment or any matter that it deems essential to an adequate appraisal of the site. The council shall provide an estimate of the cost of the study to the applicant and consider applicant comments.
(c) In addition to the deposit required under (a) of this subsection, applicants must reimburse the council for actual expenditures that arise in considering the application, including the cost of any independent consultant study. The council shall submit to each applicant an invoice of actual expenditures made during the preceding calendar quarter in sufficient detail to explain the expenditures. The applicant shall pay the council the amount of the invoice by the due date.
(2) Each certificate holder shall pay the actual costs incurred by the council for inspection and determination of compliance by the certificate holder with the terms of the certification relative to monitoring the effects of construction, operation, and site restoration of the facility.
(a) Each certificate holder shall, within thirty days of execution of the site certification agreement, pay to the council for deposit into the energy facility site evaluation council account created in RCW 80.50.390 an amount up to fifty thousand dollars, or such greater amount as specified by the council after consultation with the certificate holder. The council shall charge costs against the deposit if the certificate holder ceases operations and has not reimbursed the council for all actual expenditures incurred in conducting inspections and determining compliance with the terms of the certification.
(b) In addition to the deposit required under (a) of this subsection, certificate holders must reimburse the council for actual expenditures that arise in administering this chapter and determining compliance. The council shall submit to each certificate holder an invoice of the expenditures actually made during the preceding calendar quarter in sufficient detail to explain the expenditures. The certificate holder shall pay the amount of the invoice by the due date.
(3) If an applicant or certificate holder fails to provide the initial deposit, or if subsequently required payments are not received within thirty days following receipt of the invoice from the council, the council may (a) in the case of the applicant, suspend processing of the application until payment is received; or (b) in the case of a certificate holder, suspend the certification.
(4) All payments required of the applicant or certificate holder under this section are to be made to the council for deposit into the energy facility site evaluation council account created in RCW 80.50.390. All such funds shall be subject to state auditing procedures. Any unexpended portions of the deposit shall be returned to the applicant within sixty days following the conclusion of the application process or to the certificate holder within sixty days after a determination by the council that the certificate is no longer required and there is no continuing need for compliance with its terms. For purposes of this section, "conclusion of the application process" means after the governor's decision granting or denying a certificate and the expiration of any opportunities for judicial review.
(5)(a) Upon receipt of an application for an energy facility site certification proposing an energy plant or alternative energy resource that is connected to electrical transmission facilities of a nominal voltage of at least one hundred fifteen thousand volts, the council shall notify in writing the United States department of defense. The notification shall include, but not be limited to, the following:
(i) A description of the proposed energy plant or alternative energy resource;
(ii) The location of the site;
(iii) The placement of the energy plant or alternative energy resource on the site;
(iv) The date and time by which comments must be received by the council; and
(v) Contact information of the council and the applicant.
(b) The purpose of the written notification is to provide an opportunity for the United States department of defense to comment upon the application, and to identify potential issues relating to the placement and operations of the energy plant or alternative energy resource, before a site certification application is approved. The time period set forth by the council for receipt of such comments shall not extend the time period for the council's processing of the application.
(c) In order to assist local governments required to notify the United States department of defense under RCW 35.63.270, 35A.63.290, and 36.01.320, the council shall post on its website the appropriate information for contacting the United States department of defense.
[ 2022 c 183 s 8; 2016 sp.s. c 10 s 1; 2011 c 261 s 1; 2010 c 152 s 3; 2006 c 196 s 5; 1977 ex.s. c 371 s 16.]

NOTES:

Effective date2022 c 183: See note following RCW 80.50.010.
Construction2016 sp.s. c 10: "Nothing in this act extends or modifies the jurisdiction of the energy facility site evaluation council or the utilities and transportation commission with respect to any energy facility that is not subject to the jurisdiction of the energy facility site evaluation council or the utility [utilities] and transportation commission as of June 28, 2016." [ 2016 sp.s. c 10 s 2.]
Rule-making costs proportionately divided2010 c 152: "Rule-making costs incurred by the energy facility site evaluation council in implementing and administering this act shall be proportionately divided among the certificate holders and applicants directly affected by this act." [ 2010 c 152 s 4.]