Upon a call for projects by the county road administration board, each application by a county for county ferry capital improvement funds shall be made no later than December 31st of the same year.
Project applications shall be submitted on application forms supplied by the county road administration board and shall include the following information:
(1) Project description and scope;
(2) Engineering drawings accurately describing the complete project;
(3) Engineering analysis and cost estimate;
(4) Evidence the applicant first sought funding through the public works board assistance account or any other available revenue source; and
(5) Comprehensive project financial plan including match funding amounts and sources as required by WAC
136-400-065 and amortization and cash flow schedules.
[Statutory Authority: RCW
36.78.070. WSR 23-23-013, § 136-400-050, filed 11/2/23, effective 12/3/23. Statutory Authority: Chapter
36.79 RCW. WSR 08-10-026, § 136-400-050, filed 4/28/08, effective 5/29/08; WSR 99-01-021, § 136-400-050, filed 12/7/98, effective 1/7/99. Statutory Authority: 1991 c 310 § 1(4). WSR 91-21-138 (Order 85), § 136-400-050, filed 10/23/91, effective 11/23/91.]