(1) Facilities.
(a) Owners and operators of facilities in operation at the time this chapter is adopted must meet the advance notice requirements in WAC
173-185-070 on the effective date of this chapter.
(b) Owners and operators of new facilities must meet the advance notice requirements in WAC
173-185-070 immediately upon beginning operations in the state.
(2) Transmission pipelines.
(a) Owners and operators of transmission pipelines in operation at the time this chapter is adopted must meet the biannual notice requirements in WAC
173-185-080 on the effective date of this chapter.
(b) Owners and operators of new transmission pipelines must meet the biannual notice requirements in WAC
173-185-080 immediately upon beginning operations in the state.
[Statutory Authority: Chapter
90.56 RCW, RCW
90.56.005,
90.56.050 and
90.56.565. WSR 21-04-126 (Order 19-09), § 173-185-030, filed 2/2/21, effective 3/5/21. Statutory Authority: RCW
90.56.565. WSR 16-17-144 (Order 15-13), § 173-185-030, filed 8/24/16, effective 10/1/16.]